HomeMy WebLinkAbout10-09-14 About the Civic Center GMP Contract (goes with GMP #2 staff report)The GMP, City, and CW Driver
September 14, 2010
Newport Beach City Council
When the Public Sector Builds
Our Approach /Principles:
Cities don't build projects like this often —many
private sector companies do.
Hire a private company, through a competitive
bidding process.
Make them part of the design and do
constructability analysis /value engineering from the
start.
Assign the risk (and some reward) to them.
Three Models
Design then Build —Two or More Contracts
Independent architect designs project
Project put to bid to construction company (handles
all sub -trade bids)
Advantage — common - place, relatively simple.
Disadvantage — subcontract detail remains
unknown to the public agency. Folks in NB have
been concerned about this in the past, with Edison
and UUDs.
Three Models, continued
Design -Build — One Contract
Design and construction put out to bid.
One company handles design contract and
construction sub -trade bids.
Advantage — also commonplace, even simpler than
Design then Build.
Disadvantage — subcontract detail remains
unknown to the public agency. Folks in NB have
been concerned about this in the past, with Edison
and UUDs.
Three Models, continued
• Construction Manager at Risk (CM @R)
1. Construction Manager (CM) hired early to work
with owner and architect
2. CM promises project delivery at a set price
within a contract called a Guaranteed Maximum
Price (GMP) contract:
• Typically executed when 100% CD plan set
complete and;
• After opening and" normalizing" (malting sure
the bidders didn't make any errors) sealed
sub -trade bids
More about CM at Risk
• Construction Manager @ Risk (CM @R) —
cont'd
3. Within GMP, CM usually gets a set profit / % -age
(typically 3 to 7% of total project cost) plus an incentive
to bring the project on time & under budget
- Incentive = share of unspent construction
contingency usually 25 to 50%
- Penalty = CM responsible for all costs over
agreed -upon guaranteed maximum price
About this CM at Risk Contractor
In 2008:
City issued an RFQ for construction services. 24 firms
responded
Seven (7) firms were interviewed by staff and a Council
Committee using a Qualification -Based Selection (QBS) process .
The seven were:
Barnhart, Inc, (Heery Intl.),
C.W. Driver
Gafcon, Inc.
Griffin Structures, Inc.
Pinnacle One (Arcadis Co.)
Traker Development
Voit Development
CW
Driver was ranked as the
top
firm and then hired at a
City
Council
Meeting
(January
13,
2009).
Driver's contract
was a part of the staff report.
QBS v Low Bid
Qualification Based Selection (QBS)
Required for specialized services, like engineering,
design, construction management.
Firm selected based on qualifications.
Prices can be negotiated. Price may not be the
determinate factor.
Lowest Responsible Bidder
Required for public works projects
construction, street repair, etc.
Company selected based on lowest responsible
bid.
Price is as submitted / no negotiation.
About this Contract
Term = 2 '/2 Years
GMP Contract includes 4 major
components:
Direct Costs — actual costs for insurance
and bonding
($403,169 to date for amendments I & 2)
About this Contract Contd.
2. General Conditions /Basic Services
$7,169,255 (not- to- exceed) over 30 months.
Includes all staffing (superintendent, inspection,
support), trailers, fencing, traffic control,
stormwater control, restrooms, computers,
telephone, more.
NO PROFIT built into these numbers.
3. Construction Management Fee (Profit)
CW Driver receives 3.25% profit on all actual costs
for completed construction and basic services
performed.
About this Contract Contd.
4. Actual Cost of Construction Work (sub -trade
bids)
StAmendment = mass excavation & shoring wall ($6.73M):
8% construction contingency (included in $6.73M)
Any savings of construction contingency split 75% City, 25%
Driver.
2nd Amendment = parking structure ($7,057,636)
5% construction contingency (included in $7.06M)
Any savings of construction contingency split 75% City, 25%
Driver.
3rd (and Subsequent) Amendments
AmountTBD —based upon actual sub -trade bids, opened in
public, for remainder of Civic Center Project Qan. 2011).
Will also assume construction contingency with same split.
About this Contract Contd.
• Not included in GMP Contract:
1. Owners Contingency - if unused, 100% goes
to City.
- For Mass Ex — 10% (about $630,000)
- For Parking Structure — 5% (about
$350,000)
Contractor and Subs
EXAMPLE:
A Long - Awaited Home Remodel — Construction Costs
The Contract
0 Contractor profits 3.25% of:
• Direct Costs (=$196)
• Actual work completed with
each VkUA* (= $2,080)
* If any construction contingency
saved, divided 25%- 75 %.
(= $1,250)
Your Home —Trade Bid Prices
Foundation = 10,000+ 1,500
HVAC= 7,000 +350
Frami ng/Carp a ntry = 12,000+
1,200
Plumbing= 6,090 +600
Tile /Masonry = 3,000+ 150
*
windows /Door5 = 3,000 +150
Sheetroc k = 4,000 + 200
*
Electrical = 4,000 + 200
0
Decking= 3,000+ 150
Painting/Stucco = 5,000+ 250
Cabinetry= 7,000 +250
Subtotal Trades = $64,000
Constr.
Contingency= $5,000
Owner's Contingency =10 %or $6,900
Your Contractor's Direct Costs
GCs- Construction Fence, ta:
john, extra laborer= $5,015.00
DCs - Insurance,bondsforthis
specific project ($1,000)
.Subtotal Direct Costs = $6,015.00
The Contract
0 Contractor profits 3.25% of:
• Direct Costs (=$196)
• Actual work completed with
each VkUA* (= $2,080)
* If any construction contingency
saved, divided 25%- 75 %.
(= $1,250)
Estimated Hard Costs (based on actual bids) $ 64,000
Estimated Construction Contingency (percentage varies bytrade) $ 5,000
Estimated Direct Costs $ 7,000
Estimated Profit for Contractor (3.25% of actual work done) $ 2,470
Estimated Retained Construction Contingency $ -
Estimated Owner's Contingency (10% of Work Done Exposure) $ 6,900
Your Starting Estimate $ 85,370
hen the Proj _
Actual Work Done
- Subtrades $ 64,000
- Construction Contingency (none spent - great contractor!) $ -
SubtotalActual Work Done $ 64,000
Direct Costs
- General Conditions (fencing, etc)
$
5,015
- Bonding, Insurance
$
1,000
Subtotal Direct Costs
$
6,015
Contractor's Profit
- On Actual Work Done (3.25 %)
$
2,080
- On Direct Costs (also 3.25 %)
$
195
Contractor's Share of Unspent Construction Contingency (25 %)
$
1,250
Total - Contractor's Profit and Incentive
$
3,525
Amount in Contract (Subtrades + Profit + Incentive)
$
73,540
Retained Construction Contingency
$
3,750
Retained Owner's Contingency (none spent - great control!)
$
6,900
Project Cost at Project Completion $ 73,540
Contractor earns
more ($1,250) by saving
more contingency than
contractor would if
entire contingency used
(only would earn
$162.50)
North Park, including Dog Park
• Bid Price TBD (Dec2010j
• Construction Contingency -5 %?
EXAMPLE;
The Civic Center Project — Construction Costs
C
Civic Center —Trade Bid Prices
• Parking Structure- $6.7M +$350K.
• City Hall -TBD
• Parks -TBD
• Library Expansion - TBD
• Mass Ex /Shoring Wall - $6.2M + $490K
Subtotal Trades = $12.7M+ more to be added
Constr. Contingency= $240K+ moreto be added
Owner's Contingency = Currently $1.023M ($350K
+$5j +more to be added.
0
f
E
Central and South Park(s) _
• Bid Price TBD (12- 2010,; - 'a�r.��5= ructure
• ConstCont =S %? • = '-'''e'- 57.057M inclu
�! Cu'6- Conting =$350K
7 BifficeBu d:ng
d Price TBD IDec2011
CW Driver's Direct Costs
• GCs - Construction Fence, RR ft
john, extra laborer = NTE $7.2M
• DCs - Insurance, bonds for this
specific project ($231K +$265K+
more to be added
Subtotal Direct Costs = NTE
$7.696M now, but more to be
added
The CM at Risk Contract
• Contractor profits 3.25 %of:
• Direct Costs
• Actual work completed with
each�e�
• If any construction contingency
saved, divided 25% - 75 %. So far,
max to be saved is $840K. At 25%
split, that's $210K.
Our
Co ntinge n cy —
10%% ? I
W111111=
G M P Contract Grows Over Ti me as
Construction Elements Added
.,
.1
70
60
50
40
30
20
0
In April In May By By Early
2010 2010 September 2011
2010
F City Office Building
North Park, Central
Park
Library Expansion
Parking Structure
Mass Ex & Shoring Wall
General Conditions
Similarities — Home, Civic Center
Yes, the contract amount grows over time
as subtrade bids are added to it.
It's supposed to do that.
Profit remains 3.25% of actual work done.
Profit v. Saving Construction Contingency.
Just like the home example, there is more
reward to the construction manager to save
construction contingency than to spend it all
and make profit.
Questions Raised
"What is C. W. Driver making ?"
They will make a 3.25% profit over actual opened public bids,
actual work completed, and General Conditions.
Their "General Conditions" payments are made monthly (not to
exceed $7.169M) and reflect the actual cost of managing the
Project (actual costs, no profit — about 30 months) — includes:
Staffing (superintendent, inspection, support), trailers, fencing, traffic
control, stormwater control, restrooms, computers, telephone, more.
They get 25% of unused Construction Contingency.
City gets 75% of unused Construction Contingency and 100% of
unused Owner's Contingency.
* CW Driver has risks, too:
They must deliver on time and on budget. CW Driver is
responsible for cost overruns (costs exceeding GMP)
Issues Raised (cont'd)
"Has this been an open & public process ?"
Yes.
Contractors prequalified using State - approved
process.
All contracts competitively bid with City oversight
— opened by City Clerk.
Monthly billings show actual costs and charges on a
time and materials basis.
All C.W. Driver and City project records are public
(on the City's website) and available for review.
Questions Raised (cont'd)
Are there more affordable j`ordable project managers?
Going profit rate is 3% to 7 %.This is 3.25%
Incentive = 25% of construction contingency.
Often 30 -35% goes to construction manager.
Will always be firms offering to undercut
competition. Qualifications and expertise prevail.
Laguna Niguel's contract with CW Driver is a
different style — called Multiple Prime — as such:
City of LN retains risks of cost overruns
Much less complex site - GCs are 4% of project costs
Profit is 1.75% of project costs