HomeMy WebLinkAbout10-09-14 Civic Center PSA-At-Risk-CW Driver GMP #2CITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No.
September 14, 2010
I[ 0�:[ 0 L4[ 07: 7_\: 34:8JiUf fir e]: LVI oil �LIWYAiI :IA:We]aI.I:9y1WYK0111►[yl11111
FROM: Public Works Department
Stephen Badum - sbadum @newportbeachca.gov
949 - 644 -3311
SUBJECT: NEWPORT BEACH CIVIC CENTER PROJECT: PARKING
STRUCTURE, GUARANTEED MAXIMUM PRICE (GMP), PHASE TWO
ISSUE: Staff is requesting the approval and funding of the next phase of the Newport
Beach Civic Center Project which includes the design and construction of a
Parking Structure.
RECOMMENDATIONS:
1) Approve an amendment to the Construction Manager At Risk Contract with C.W.
Driver, Irvine, California, amending the Guaranteed Maximum Price (GMP) to add
the design and construction of the parking structure and miscellaneous items of
work (GMP #2) for the Newport Beach Civic Center project at a not -to- exceed
price of $7,426,853 and authorize the Mayor and City Clerk to execute the
contract.
2) Establish a budget of 5% of GMP #2 ($350,000) as the City's contingency for
unforeseen costs and authorize the Public Works Director and City Manager
execute change orders upon concurrence by the City Council Building Committee.
3) Approve Budget Amendment No. 11BA -- appropriating $7,776,853 from the
Major Facilities Master Plan Fund to Newport Beach Civic Center Project Account
No. 7410- C1002009.
DISCUSSION:
The following bids were received from prequalified contractors for the Newport Beach
Civic Center parking structure:
Prequalified Design Assist / Build Contractors
Amount
Bomel Construction
$6,367,000
McCarthy Builders
$6,713,000
ARB Structures
$6,894,361
Preliminary Estimate — Design Development Phase (4/27/10)
$8,018,500
Preliminary Estimate — Schematic Design Phase (11/10/09 ) - normalized'
$11,021,000
Newport Beach Civic Center Project
Parking Structure, GMP Phase 2
September 14, 2010
Page 2
As shown by the above table, the City has benefitted from the current downward trend
in construction costs:
• Parking Structure. The lowest bid received was almost $2 million (about 20 %)
less than our April 2010 estimates. The initial, preliminary estimates for the
structure were set at $11 million back in November 2009 ('normalized to delete
the Shoring Wall, which was later considered part of the "Mass Ex" package).
• Mass Excavation and Shoring Wall. This contract, let in April 2010, secured
savings of almost $1 million (about 12 %) from initial estimates.
On April 27, 2010, the City Council approved a Construction Manager at Risk Contract
with C.W. Driver in the amount of $14,617,374 with included general conditions for the
entire project ($7,169,255); mass excavation and shoring construction (GMP #1,
$6,726,574); direct expenses for the GMP #1($265,412); and the project fee for GMP #1
($456,133). Additionally, a City contingency was approved in the amount of $673,000
bringing the total cost to $15,290,374.
In an effort to expedite the project, the City elected to start the early phases of the
project such as grading and the construction of the parking structure in advance of the
final design completion of the parks, City Hall building, and Central Library Expansion.
To accomplish this goal, the City Council entered into a phased Construction Manager
at Risk (CM @R) contract with C.W. Driver. To review, the current contract is broken
down into four components.
Basic Services / General Conditions. The first component is the basic services or
general conditions. These include the fixed costs for the construction field office
(including construction trailers, office equipment, portable restrooms, copiers,
computers, telephone and equipment) and the necessary personnel to staff the project
(including superintendent, inspection and support staff). The work scope included in
basic services includes:
• Managing the public bidding and award process in full compliance with the
California Public Contract Code.
• Providing full and complete construction administration, coordination and
construction observation services during and following construction, including
but not limited to the following:
:• Onsite administration and management
Project and construction cost management
❖ Quality assurance, inspection, and quality control
❖ Coordinate with the City's Building Inspectors
❖ Dispute resolution
❖ Submittal coordination
Management of Requests for Information (RFI)
❖ Change order review and negotiations
❖ Manage construction materials testing, and specialty inspection services
Newport Beach Civic Center Project
Parking Structure, GMP Phase 2
September 14, 2010
Page 3
❖ Provide schedule analysis and continuous updates
❖ Manage project close -out, including assuring the A &E team provides
complete record (As- Built) drawings
Construction punch -list management and completion
❖ Manage substantial and final completion processes, and project acceptance.
❖ Compile program warranties
❖ Deliver operations and maintenance manuals
❖ Coordinate the installation of FF &E and move -in activities
Manage final payment and project closeout for all consultants and contractors
under direct contract with the City
❖ Coordinate warranty work for a period of up to one year.
The Basic Services, based upon the current project schedule for the entire project, are
estimated at a not -to- exceed cost of $7,169,255. Basic Services are billed monthly on
a time and material basis at the agreed rates as shown on Exhibit A of the CM @R
contract. City Council approved these costs as a part of the original contract with C.W.
Driver on April 27, 2010 and no adjustments are proposed for GMP #2.
Construction Costs / GMP. The second component of this contract is the actual cost
of the construction work. The cost of the work is set as a Guaranteed Maximum Price
(GMP). The GMP will include the actual bid plus a contingency. Under the CM @R
project delivery method, C.W. Driver will bid out the various construction trade contracts
in accordance with the Public Contract Code and oversight from the City Clerk. The
City Council will then approve the expenditure and accept C.W. Driver's GMP proposal
for the work. C.W. Driver will then be responsible for delivering all work and
construction included in the approved work scope for the maximum cost stated in the
GMP. Any costs exceeding the GMP will be borne by C.W. Driver. Any savings under
the GMP will be shared by the City and C.W. Driver. The City will receive 75% of any
savings and C.W. Driver will receive 25% of any savings as an incentive to reduce
overall costs.
The first phase of the project, the Mass Excavation and Shoring Construction Phase
(GMP #1), is already underway. The second phase of the GMP is the Design
Assist/Build for the parking structure and miscellaneous items of work. This
phase (GMP #2) will design and construct a 450 - space, mechanically vented parking
structure. On June 21, 2010, the City Clerk oversaw the public opening of the sealed
proposals for this phase of the work. Upon scoring of these proposals, the top three
firms, Bomel Construction, McCarthy Builders, and ARB Structures were invited to meet
with the design team, City staff, BCJ and C.W. Driver, to discuss cost - saving proposals
and alternative construction. The design team revised the bridging documents to
incorporate the desired proposals and alternative designs and asked each firm to
submit a bid based upon the revised bridging documents. A summary of those bids is
attached for Council review.
C.W. Driver has compiled GMP #2 which includes the lowest bid from Bomel
Construction ($6,637,858), the relocation fiber optic cable that was discovered during
Newport Beach Civic Center Project
Parking Structure, GMP Phase 2
September 14, 2010
Page 4
the grading operation ($42,630) and incidental work items for a total of $6,721,558. A
breakdown of the project components is listed in exhibit A. Subsequent GMP phases
will include a third phase for the City Hall, library expansion, and park improvements.
Upon City Council approval, Bomel will complete parking structure plans and
specifications; submit and obtain a building permit; and construct the parking structure.
Direct Expenses. The third component is the Direct Expenses which include the direct
costs for bond premiums; field office expenses such as equipment and supplies;
general liability insurance; and additional services as requested by the City. Direct
expenses will include known costs and allowances for variable items. The Direct
Expenses for the Parking Structure Design Assist and Construction Phase (GMP #2)
total $137,757 including general liability insurance cost of $64,224 and an allowance for
bonds and expenses at $73,533.
Construction Management Fee / Profit. The fourth component is the project fees for
managing the construction. These construction management fees represent the
markup, overhead, and profit. The Basic Services, Direct Expenses, and GMP
represent actual costs without any markups, overhead or profit. The rate for the
construction management fee is set at 3.25% for the entire project. The maximum
construction management fee for this phase of work (GMP #2) is calculated at
$231,460. The actual amount paid to C.W. Driver is based upon actual work completed
(i.e., the amount could be less if the construction contingency is not spent).
More about Contingencies. There are typically two contingencies in a project like this
— a "Construction Contingency," for unforeseen changes that arise during actual
construction. For the parking structure, this is set at 5% of the bid. There also is an
"Owner's Contingency" that the City can use if needed to add elements to the project if
it so chose. For the parking structure, this is also set at 5% of the bid. The following
chart shows more:
Parking Structure Contingencies
The total cost of the proposed amendment GMP #2, Parking Structure Design
Assist/Build is $7,426,854. To provide for potential unforeseen costs, staff
recommends that a contingency of $350,000 (5 %) be established. Unforeseen costs
may include delay and recovery costs should we discover changed foundation
conditions and delays due to environmental or weather conditions. Staff also proposes
that any adjustments to the CM @R contract compensation be authorized by the Public
Works Director and City Manager with concurrence by the City Council Building
Committee. With the approval of GMP #2, the total cost allocated to the project to date
How much is City
eligible to get if saved?
Bid Price Bomel
$6,721,558
Construction Contingency
$350,000
$262,500 75%
Owner's Contingency
$350,000
$350,000 (100 %)
The total cost of the proposed amendment GMP #2, Parking Structure Design
Assist/Build is $7,426,854. To provide for potential unforeseen costs, staff
recommends that a contingency of $350,000 (5 %) be established. Unforeseen costs
may include delay and recovery costs should we discover changed foundation
conditions and delays due to environmental or weather conditions. Staff also proposes
that any adjustments to the CM @R contract compensation be authorized by the Public
Works Director and City Manager with concurrence by the City Council Building
Committee. With the approval of GMP #2, the total cost allocated to the project to date
Newport Beach Civic Center Project
Parking Structure, GMP Phase 2
September 14, 2010
Page 5
is $23,067,227. The following chart lists the various components of the project costs
including construction and owner's contingencies.
Construction Manager at Risk Costs to date
Amount
General Conditions /Basic Services (for all phases of the Project)
$ 7,169,255
GMP #1 -Mass Excavation & Shoring Construction
includes 8% construction contingency)
6,726,574
Direct Expenses (GMP #1)
265,412
Construction Management Fee (GMP #1)
456,133
Subtotal
$7,448,119
Owner's Contingency GMP #1 (10 %)
673,000
GMP #1, Subtotal
$8,121,119
GMP #2 Parking Structure Design Assist/Build (includes 5%
construction contingency)
$7,057,636
Direct Expenses (GMP #2)
137,757
Construction Management Fee (GMP #2)
231,460
Subtotal
$7,426,853
Owner's Contingency GMP #2 (5 %)
350,000
GMP #2, Subtotal
$7,776,853
Project Total to date
$23,067,227
ENVIRONMENTAL REVIEW:
CM @R services are not projects as defined in the California Environmental Quality Act
(CEQA) Implementing Guidelines. An EIR for the Newport Beach Civic Center Project
was certified by City Council in November 2009.
Newport Beach Civic Center Project
Parking Structure, GMP Phase 2
September 14, 2010
Page 6
1111 \IQIZ"IX17-11IA_1:1IIIes
With the approval of the recommended budget amendment in the amount of
$7,776,853 sufficient funds are available in the following account:
Account Description
Newport Beach Civic Center
Submitted by:
Stephen G. Badum
Public Works Director
Account Number Amount
7410- C1002009 $ 7,776,853
Attachments: Amendment to PSA with C.W. Driver, including work scope, schedule and fee
exhibits
CM @R contract with C.W. Driver — GMP Breakdown
Budget Amendment