HomeMy WebLinkAboutS20 - 2007-08 Master CIP Schedule UpdateCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. S20 October 23, 2007 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Stephen G. Badum 949 - 644 -3311 orsbadum @city.newport- beach.ca.us SUBJECT: FY 2007 -08 MASTER CIP SCHEDULE UPDATE RECOMMENDATION: Receive and File. DISCUSSION: Attached is the 2nd Quarter Master Project Schedule update. For the most part, our projects are proceeding on schedule. Highlights of progress made in the 1st quarter and changes from the 1st quarter schedule are depicted as follows: Proiects completed in 1st Quarter 1. Police Facility Perimeter Fence 2. FY06 /07 Citywide Street and Storm Drain Improvements 3. Santa Ana Heights Fire Station # 7 & Training Tower 4. Newport Coast Community Center 5. Back Bay Science Center Projects Delayed Birch Street Pavement Rehabilitation, Bristol to MacArthur. This project involves grant funding under the Arterial Highway Rehabilitation Program (AHRP). Caltrans did not approve our project in September due to funding shortages in the current program. That situation has been rectified and the revised schedule has construction of the project beginning in April 2008. 2. Back Bay View Park Enhancements: The project schedule has been adjusted to allow for optimal planting conditions for native plants which occurs in the fall. Buck Gully Force Main Replacement, Poppy Avenue: While the project was awarded on time, the contractor has fallen behind schedule and has not started work. In an effort to minimize impacts to the community, we have directed the contractor to delay work until after the holiday season. Work will start after January 1, 2008. FY 2007 -08 Master CIP Schedule Update October 23, 2007 Page 2 4. Buffalo Hills Lighting Project: The adjacent homeowners association has asked us to delay the project while they confirm the membership's support for installing bollard lighting on the park walkways. Staff expects this issue to be resolved soon and it is anticipated that the project will be awarded during May 2008 with construction starting after the summer months. 5. Corporation Yard Building Fleet Maintenance Locker Room: This project has been delayed by two months. It has been decided that the General Services Department will handle much of the work in -house (design and construction). The work will commence in January 2008. 6. Directional and Wayfinding Signage — Citywide: The completion of this project has been delayed six weeks due to the addition of a monument sign for the easterly entrance of Corona del Mar Village. 7. Fire Station #3 Water Piping Replacement: Fire Department resources have been focused on completing the Training Tower in Santa Ana Heights. Work will resume in January 2008. 8. Flashing Crosswalk — Newport Blvd @ 23`d St.: This project was originally scheduled for award in December. The design consultant has fallen behind and we expect award in February 2008. 9. Industrial Way — 36" Water Transmission Main Replacement: Due to numerous interfering utilities that were not accurately located, the project plans required redesign which delayed the construction start. Work should start in January 2008. 10. Irvine Avenue Dover Drive Water Main Replacement: This project was delayed by two months due to groundwater issues and traffic control difficulties. Construction should be completed by 12/14. 11. Iris Avenue/ Coast Highway Traffic Signal: This project was delayed to allow more discussion with the local community. The design was originally scheduled to begin in October, but it now appears that the project could be delayed by one or two months depending on how quickly community consensus is reached. 12. Newport Coast Drive /Pelican Hill Road North Intersection Improvements: This project is two months behind schedule due to negotiations with the adjacent homeowners' association. 13. San Joaquin Hills Road Median Trees: This project was delayed by one month to allow for discussions with The Irvine Company's landscaping representatives. FY 2007-08 Master CIP Schedule Update October 23, 2007 Page 3 14. Sunset Ridge Park Conceptual Design: This project was on -hold during. the land acquisition process. At the end of that process, it was necessary to retain a new design consultant as the original consultant's contract had expired and the consultant was unable to continue. The first public outreach meeting is scheduled for November 8. 15.Traffic Signal Modernization: This project was delayed one month while our consultant investigated opportunities associated with the newly acquired radio tower at the Utilities Yard. Proiects Advanced 1. Coast Highway Sidewalk — Morning Canyon to Seaward: This project is being advanced so that it can be combined with the River Avenue Pedestrian Improvements project which is scheduled for award in February 2008. 2. HR Recruitment Trailer Installation: This project is ahead of schedule. Award of the site preparation and installation work will occur in November, one month ahead of the original schedule. New projects 1. Assessment District 99 Revised: With the recent failure of AD 99, staff is working with the residents and utilities to re- formulate the district boundaries. 2. Castaways Park Marine 111 Memorial: Staff is working with the artist to complete the site design. Construction is planned for spring 2008. McFadden Square Centennial Plaza: The project plans are currently out to bid. It is expected that work will begin in January 2008. The Master Project Schedule is posted on the City's web page under Public Works at http:/A,vww.citv.newport-beach.ca.us/Pubworks/CIP.htmi and is updated quarterly. Submitted Badum -�, , i 7 � -riles Director L 41 42 rlw 2 27 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter Task Name 38th Street Tidal StructurafMoloriied Tide Val" (1) Design - In House - (p. 23) (2) Award (3) Construction ($135,000) Arroyo Park, Avon St. at Tustin Ave., Com Area Parking Lots, Irvine Terrace, Newport Heights and West Balboa Slurry Seal (1) Design - In House - (p. 24, 25, 33, 45, 49 & 61) -- (2) Award ($48,000, 69,1)00, 120,000, 395,000, 580,000 & 89,000) (3) Construction ($1,301,000) - ASSS Assessment Program (1) Prop 40/50 Grant contract ($397,500) - (p. 90) (2) Public Use and WO Assessments (Weston) (3) Cross contamination impact study (Everest) (4) Pilot Renovation Program (Cal. State Fullerton) - - - (5) Bioassay Study (Weston) Final Integrated Coastal Watershed Management Plan Assessment District 19 - Santa Ana Heights (1) Utility Company Design Efforts & Assessment Engineering (p. 139) (2) Underground Construction ($7.411,200) (3) Street Improvements (4) Utility Systems Installation and Wiring g (5) Resident Conversion Assessment District 69 - West Newport (5) Utility Systems Installation and Wiring 56 (6) Resident Conversion Assessment District 87 - Balboa Island (1) Utility Company Design Efforts & Assessment Engineering (2) Pudic Hearing - District Approved (3) Underground Construction (4) City Water System Improvements (5) Street Improvements 7 (6) Utility Systems Installation and Wiring i (7) Resident Conversion I Assessment District 99 - Balboa Peninsula (1) Utility Company Re- Design Efforts & Assessment Engineering i (2) Public Hearing - District Approved (3) City Water System Improvements (4) Underground Construction 1 1I (5) Street Improvements 1 (6) Utility Systems Installation and Wiring I (7) Resident Conversion _._ _ ., __ J J A S O �' N Sat 09/01/07 Mon 07/14/08 Sat 09101/07 Mon 12/31/07 Tue 0226108 Tue 02/26/08 Tue 0001/08 Mon 07 /14/06 Tue 01 /01,08 Fri 09105 %08 - Tue 01/01/08 Mon 04/14/08 - Tue 05/27/08 Tue 05/27/08 - Mon 06/16/08 Fri 09/05/08 Thu 01/05/06 Mon D6/02/OB Thu 01 /05106 Wed 06 /21/06 Mon 04/30/07 Mon 03/31/08 - Wed 11/01106 Mon 03/31/08 Mon 01115107 Mon 03131/08 -- —T Fri 12101/06 Mon 03131108 _ -- -- Mon 06102/06 Mon 06 102/08 _- Tue 0921/04 Fri 08/08114 T" 0921104 Thu 07117108 Fri 07/18/08 Thu 11119109 Fri 11/20/09 Thu 04/08/10 Fri 04/09/10 Thu 01/12!12 Fri 01113/12 Fri 08106/14 Tue 08/09105 Fri 0229108 Tue 12/27105 Fri 09128107' Tue 08/09/05 Fri 02/29108 -- Wed 01101/97 Fri 01/07/11 Wed 01/01/97 Wed 11/28/07 _- Tue 05/13/08 Tue 05/13108 Mon 09/08/08 Fri 01108/10 Mon 09 /06/08 Fri 0220/09 Mon 11/02/09 Fri 0423/10 Wed 07/01/09 Tue 01126110 Mon 09/07/09 Fri 01/07111 Tue 10109107 FA 02/26/10 Tue 10/09/07 Fri 03128/08 :— Tue 06/10/06 Tue 06110108 Mon 06/11/08 Fri 10/31/08 Mon 10 113108 Fri 06/12/09 - Mon 09/07/09 Fri 02/26/10 Wed07/01/09 Tue01/26/10 Mon 09107/009 Fri 02/26/10 Thu 10/18/07 Page 1 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter ID Task Name clan rattan i_ J innle J A S 0 N D J f na A M J J A. 10 N j 372 Back Bay Science Center, Including Admin. Bldg. Mon 05/15/08 Thu 11101107 —. 373 (4) Construction ($4,494,033 & $1,082,358) - Bemards Mon 05/15/06 Thu 11101107 154 Back Bay View Park Replenishment & Enhancement Toe 10/23/07 Thu 12/18/08 155 (1) Design - SWA - (p. 78) - ($100,000) Tue 10/23/07 Toe 0129/08 156 (2) Permitting (it required) Wed 01/30/08 Tue 06103108 157 (3) Award Tue 07/08108 Tue 07/08/08 *07;06 158 (4) Construction (§250,000) Fri 08/07/08 Thu 72/18108 71 'Balboa Island Bulkhead Repairs Mon 09103107 Fri 02127109 72 (1) Design - In House - (p. 26) Mon 09/03/07 Thu 02/28/08 73 (2)Award Tue 06/10/08 Tue 06110108 _ 74 (3) Construction ($160,700) Mon 09/15108 Fri 02/27109 - - 20g Balboa Island Water Main Replacement Mon 10101107 Fri 02/20/09 210 (1) Design - In House Mon 10/01/07 Thu 05/29/08 �;- 211 (2) Award Tue 0722/08 Tue 0722/08 ♦ p712� 212 (3) Construction ($1,000,000 - FY08109) Mon 09/08/08 Fri 02/20109 217 Balboa Peninsula Walkway, East Coast Highway Curb and Gutter, Park Mon 011=07 Thu 12127107 now Asphalt Walkway Replacement with Annual Sidewalk, Curb and Gutter Replacement Program (along with ADA Improvements) 218 (1) Design - In House (p. 59.88, 141. 38, & 21 - FY 06/07) Mon 01 /08107 Fri 04/06107 - 219 (2) Award - ($541,006) - Nobest Tue 06/26/07 Tue 06126/07 _ 220 (3) Construction - ($100,000, 86.000, 115,000 & 301,216) Mon 09/17/07 Thu 12/27/07 205 Balboa Village Alley Replacement Man 07/02/07 Fri 12119108 206 (1) Design - In House (p. 27) Mon 07/02/07 Wed 04/30/08_ -' - -- - -�.i 207 (2) Award Tue 06/10/08 Tue 06/10 108 208 (3) Construction ($177.390 8 §200,000) Mon 0910 8/08 Fri 12/19/08 170 Bay Crossing Water7ransmission Main Replacement Thu 11/01/07 Mon 04105!10 171 (1) Design ($300,000) - Consultant - (p. 118) Thu 11101/07 Tue 10114/08 172 - (2) Permitting Wed 10/15/08 Toe 05112!09 - _- - 173 (3) Award Tue 07/14/09 Tue 07/14/09 - 174 (4) Construction (not funded) Tue 09/08/09 Mon 04/05/10 108 Sayside Drive (Jamboree to El Paseo). CDM Area South or Coast Highway Mon 07102/07 Fri 07125/08 and Dove Street Rehabilitation 109 (1) Design - In House - (p. 28,34 & 35) Mon 07/02/07 Wed 02/06/08 _ 110 (2) Award Tue 03/11/08 Tue 03/17/08 111 (3) Construction ($211,000. $1,000,000 & $97,0D0) Man 04 /14/08 Fri 0725/08 36 Bayside Waterfront Walkway to Balboa Isi. Bridge Tue 08/14107 Fri 02/20/09 37 (1) Design - URS (Cash) - ($40,000) - (p. 631 Tue 08/14/07 Thu 12/27107 38 (2) Coastal Permitting Fri 1228/07 Thu 06119/08 - 1 39 (3) Award Tue 0729/08 Tue 07/29/08 40 (4) Construction (FY 08/09 Development Funding) Mon 09108/08 Fri 0220109 120 Beach Sand Study & Monitoring Program Mon 10110105 Wed 061251(18 121 Design & Coastal Permitting - Moffatt & Nichol - $200,000 - (p. 83) Mon 10110105 Wed 08/25/08 Thu 10/18/07 Page 2 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter 367 Big Gnyon Creek Restoration i Fri 09101/08 768 (1) Design - W RC /Mark ReaderRse - (P. 106) Fri 09/01/06 369 (2) Coastal Permitting Thu 10/25/07 370 (3) Award Tue 07108/08 371 (4) Construction (not funded) Mon 09/08/08 342 Birch Street Pavement Rehab. - Bristol to MacArthur Mon 01/01/07 343 (1) Design - In House /Emmet Berkery - (p. 29) Mon 01/01/07 344 (2) Calfrans Processing Mon 06/18/07 (3) Award Tue 03/11/08 346 (4) Construction ($293,000, $176,000 8 $253,000) Mon 04/14/08 233 Bridge Seismic Retrofits - Jamboree and Goldenrod Foot Mon 08101/05 294 - (1) Design - Dokken ($278,000) - (p. 30) Mon OB/01/05 235 (2) Caltrans Processing/Coastal Permitting Mon 06/05/06 236 (3) Award Tue 02/12/08 237 (4) Construction ($312,400 8 $1,270,700) Thu 05/01/08 314 Bristol Street Sign Bridge Improvements Wed 01102/08 315 (1) Design - Consultant - (p. 64) Wed 01102/08 316 (2) Award Toe 05/27/08 317 (3) Construction ($100,000) Mon 07/14/08 88 Buck Gully Arundo Removal Project Wed 08/01 /07 89 (1) Design - In House (p. 114) Wed 08101/07 90 (2) Award Tue 09125107 91 (3) Construction ($45.000) Thu 11 /01107 52 Buck Gully Erosion Control Project Mon 07103/06 M Award Mon 03/02109 53 Concept Plan - RBF ($418,000) - (p. 145 FY 06/07) Mon 07103/06 57 Construction (Not Funded) Fri 05/01/09 54 Council Concept Plan Review Tue 12/11 /07 55 Final Construction Docoements (Not Furded) Wed 01102/08 130 Buck Gully Force Main Replacement - Poppy Ave. from Hazel Dr. to ECH Mon 01/02/06 131 (1) Design - ($22,000) - Nolan Consulting (p. 122) Mon 01102/06 132 (2) Award Tue 08/14/07 133 (3) Construction ($274,633) - Mike Pitch 8 Sons Wed 01102108 84 Buck Gully Maintenance Road 8 Wetlands Project Fri 07/01 /05 85 (1) Design, Permits and Easement (Dudek) - $125,000 in 107) Fri 07/01/05 86 (2) Award - ($386,323.60) Tue 07/24/07 87 (3) Construction ($115.823. $67.500 8 $203,000) - McKenna General Eng. Wed 08/15/07 7 ' Buck Gully Resource Management Plan Tue 09/25/07 8 Consultant Study- ($170,000) Toe 09/25/07 _� Fri 04103/09 MIMMOMMONEWE Toe 01/29/08 - -- -- -- _ —� Tue 05/20108 Tun 07108/08 _ Fn 04/03/09 - Fri 07/25/08 Fri 05/18/07 Wed 02/13/08_ 1 Tue 03 /71108 Fri 07/25/08 -- Wed 11/26108 Wed 01102108. Wed 01/02108 Toe 02/12/08 Wed 11/26108 Fri 11128/18 - Toe 04/15/08 Toe 05/27108 ♦ - -0513 Fri 11/28/08 _ -- Tue01/22/O8 Tue 08/21/07'. Tue 09 /25/07 Tue 01/22/08 Thu 02/04/16 Mon 03102109 Thu 11101107 - -- -J Thu 02/04110 Tue 12111 /07 2/11 Tue 01/27/09 ! •_" ._ .__. -. Tue 03/25108 Fri 06/29/07 Toe 08/14/07 ...p8 Tue 03/25/08 - Fri 12/28107 Thu 05131/07. —� Tue 07/24/071 7/24 Fri 12/28107 Tue O7 /01/08 Tue 07/01/08 Thu 10/18/07 Page 3 248 222 405 407 23 24 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter Buffalo Hills Park Lighting (1) Design - JMDiaz - (p. 85) (2) Award (3) Construction ($215,000) Central Library Emergency Generator (1) Design - In Flo" - (P. 1) (2) Award (3) Construction ($40.000) Cliff Drive Park Stairway and Handrail Replacements (1) Design - In House (p. 86) (2) Award (3) Construction ($147,426.60) - G2 Construction Coast Highway Channelizatlon • CDM Medians - Phase Ito (1) Design TLC /DMC - (37.650) - (p. 15) (2) Award (3) Construction ($253,740) - Mega Way Coast Highway Sidewalk - Morning Canyon to Seaward (1) Design - In House/Civilworks - (p. 32) (2) Award (3) Construction ($250,000) Corporation Yard Building Fleet Maintenance Locker Room (1) Design - In House - (p.5 ) (2) Construction ($65,000) Corporation Yard Building G Roof Repair and Rehabilitation (1) Design - In house/Consultant - P. 4 ) J (2) Award (3) Construction ($120,000) CYC Rehabilitation (1) Master Planning - Consultant - (p. 6) Directional and W ayfinding Signage - Citywide (2) Award (3) Consfucton ($225,000 8 $102,000) Dover Drive a Westcliff Drive Medians Renovation (1) Design - In House/Consuftant - (p. 36 8 62) (2) Award (3) Construction ($125,000 8 $80,000) Dover Drive Sidewalk Improvements (1) Design - ($69,838) Van Dell (p. 37) (2) Permitting (3) Award (4) Construction ($84,000, $102.645 8 $278,500) Wed 01/02/08 Wed 01102/08 Tue 05/13/08 Mon 09/08/08 Mon 10/01/07 Mon 10/01/07 Tue 04/15108 Mon 06/02/08 Tue 05/01/07 Tue 05/01/07 Tue 09111/07 Thu 11/01/07 Thu 06/01/06 Thu 06/01 /06 Tue 07/10/07 Wed 08/01107 Wed 08/01107 Wed 08/01/07 Tue 02/12/08 Mon 03/10/08 Wed 08411107 Wed 08/01107 Wed 01/02/08 Thu 11101107 Thu 11/01107 Tue 0325/06 Thu 05/01108 Wed 06!01107 Wed 08/01/07 Tue 06/12/07 Tue 06/1207 Mon 07116/07 rue 01101108 Tue 01/01/08 Tue 05/27/08 Tue 07/01 /08 Man 10104104 Mon 10/04/04 Mon 06/26/06 Tue 02/12/08 Tue 04/01/08 J A ti U N D =FIM A IM Id - -J AS- Fd 0123/09 - Tue 04115/08 Tue 05/13/08 -OU11� Fri 01 /23109 Fri 10/17108 r Thu 02/14/08 Tue 04115/08 —� Fri 10/17108 _.- Tue 01122/08 Mon 07/02/07 Tue 09 /11107 d t Tue 0122108 Tue 1127/07 �EMW Wed 05/02/07. Tue 07/10107 y n0. Tue 11/27107 Fri 07125108 Wed 12/26107 Tue 02/12/08 72 Fn 0725/06 Thu 0221/08 Fri 12/28107 — - Thu 02/21108 ' Wed 08 113/08 Tue 02/12/08 Tue 03/25108 Wed 08/13/08 Fri 06/27/08 Fri 06/27/08 Tue 0226108 Tue 06/12107 Tue 02126/08 Mon 09,0&08 Mon 04114/08 - - -� Tue 05/27108 -05727 Mon 09 /08/08 Mon 07114108 Fri 06 /23106 Wed 01102/08 T Tue 02/12/08 Mon 07/14108 ' Thu 10/1&07 Page 4 Thu 10/18107 Page 5 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter ID Task Name Stan Finish J I J_. A_ S -N _D F I M I A I M I J J A 5 O N D _ 229 East Bay Avenue and A street Rehabilitation and East Bay Storm Drain Wed 08101/07 Mon 06/23/08 Upgrade: Tidal Valve Install 230 (1) Design - In House - (p. 38 8 39) Wed 08/01 /07 Fri 12/14/07 L---- ---- -- 231 (2) Award Tue 02/12/08 �T-- Tue 02/12/08 - 232 (3) Construction ($113,000 8 $30.000) Tue 04/01/08 Mon 06/23/08 T 197 Eastblull Drive Street Rehabilitation Sat 09/01/07 Fri 1084108 198 (1) Design - DMS - (p. 40 8 56) Sat 09 /01107 Wed 02127/08 199 (2) Award Tue 04/22108 Tue 04/22/08 2(10 (3) Construction ($1.180,000 8 $200,000) Mon 06/09/08 Fri 1084/08 391 Fire Facilities Assessment and Preliminary Design Mon 10/01/07 Mon 12/31107 392 Study- Consultant - (p. 7)- ($280,000) Mon 10/01 /07 Mon 12/31/07 25 Fire Station 1 Gender Modifications Tue 04/22/08 Fri 07/18108!,, 26 (1) Award - (p. 8) Tue 0482/08 Tue 04/22/06 :. 27 (2) Construction ($180,000 8 $74,800) Mon 06/02/08 Fn 07/18/08 393 Fire Station 3 Water Pipe Replacement Thu 11/01107 Thu 02/07/08 ! - - 394 (1) Design - Consultant - (p. 9) Thu 11101/07 Tue 12/18107 395- (2) Award Tue 01/08/08 Tue 01/08108 _ 01/08 396 (3) Construction ($30,000 8 $65,000) Tue 01106/08 Thu 02/07/08 382 Fire Station No. 7 Training Tower Thu 02/01107 Mon 10/01107 383 -- (2) DesgrVBuild - (p. 3, 81 8 128) - $740.000 Thu 02101/07 Wed 06 /06/07 384 (3) Construction ($863,770) - Nielsen Mon 06/25/07 Mon 10/01/07 374 Fire Station Number 7 Tue 01103/05 Mon 04130107 375 (3) Construction ($6,495,000) - Bernards Tue 01 /03106 Mon 04130/07 298 Flashing Crosswalk - Newport Boulevard at 23rd Street Wed 08/01/07 Mon 0683108 299 -- (1) Design - KOA - (p. 66) Wed 08/01/07 Mon 12/31107 —Z. L 300 (2) Award Tue 02/12/08 Tue 02/12/08 301 (3) Construction ($110,000) Tue 04/01/08 Mon 06/23/08 _ - 46 Harbor Area Management Man ($345,800) Tue 05/08/07 Tue 0782/08 49 (1) Consultant Award - Weston - (p. 76 FY 06/07) Tue 05/08/07 Tue 0$/08/07 rS /08'; 50 (2) Prepare assessment, studies and recommentations Tue 05/08/07 Thu 05/15/08 51 (3) Prepare Final Plan Fri 05/16/08 Tue 07/22108 347 Hoag Health Care Center - Traffic Signal Improvements Tue 05/01/07 .— Thu 12118108 348 (1) Design - Consultanl/Emmet Berkery, Tue 05/01107 Fri 10/19/07 349 (2) Right-of-Way Acquisition Mon 10/22/07 Thu 03/06/08 350 -... (3) Award Tue 0482/08 Tue 04/22/08 :. — ..0482_ -- 351 (4) Construction ($330,000,$800,000, 8 $130,000) Fn 08/01/08 Thu 12/18/06 134 HR Recruitment Trailer Project Mon 08113107 Mon 12!24107 135 - (1) Design - In House - (p. 21) Mon 08/13107 Thu 09/27/07 136 (2) Award Tue 11113/07 Tue 11/13107 .,11113 137 (3) Construction ($58,000) Wed 11/14/07 Mon 12/24/07 Thu 10/18107 Page 5 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter ID Task Name 250 Indian Spring Lane, Polaris, Santiago & Spyglass Hills Subdralns 251 (1) Design - In House (P. 42. 51 & 55) 252 (2) Award with FY 08/09 Street Projects 253 (3) Construction ($50,000, $270.000 & $75,000) 122 Industrial Way - 364nch Water Transmission Main Replacement - Superior Avenue to Old Newport Road 123 (1) Design ( $122,000) - HDR - (p. 102 - FY 06/07) 124 (2) Award - ($990.285) - SJB Group 125 (3) Construction ($144,500 & $919,785) 92 Interpretive Resources and Facility 93 (1) DesgriBuild - (p. 114) 94 (2) Construction ($26,700) 310 Iris Avenue and Coast Highway Traffic Signal 371 (1) Design - Consultant - (p. 67) 312 - (2) Award 313 (3) Construction ($100,000 & $180,000) 397 Irrigation - Citywide Central Computer Program 368 (1) Ongoing irrigation management program (p. 94) ($90,000) 399 Irrigation - Newport Coast Central Computer System 400 (1) Newport Coast Central Computer System Program (p.95) ($100,000) 116 Irvine Avenue and Dover Drive 244nch Water Transmission Main _ Replacement - Santiago to Westcliil 117 (1) Design - ($ 140.000) Stantec - (p. 92 & 90 FY 05M(i) 118 (2) Award 119 (3) Construction ($2.827,049) Vadrms 79 Irvine Avenue Drainage Improvements (Beacon to Clay) g0 Design - In House Design Only) 337 Irvine Avenue Reallgnment - University to Bristol (County Lead) 238 (1) Design - County /Emmet Berkery (p. 43) 339 (2) Right -of-Way Acquisition 340 (3) Award (County Administration) 317 - (4) Construction ($330.200 & $800,1700) 360 Irvine Terrace Landscape Improvements - Phase 1 361 (1) Design - Pendian - (p. 44) 362 (2) Award 363 —' (3) Construction ($130,000 & $20,000) 334 Jamboree Road Widening over SR -73 (ON HOLD) 335 (1) Design - ($923,483) - RBF/Emmet Berkery (P. 46) -336 (2) Right-of-Way Acquisition ($299,100 & $115,000) Tue 01/08/08 Tue 01108/08 Tue 12/09/08 Mon 02/02/09 Wed 05/11/05 Wed 05/11/05 Tue 05108/07 Mon 07/16/07 Mon 07/02107 Mon 07102/07 Mon 10101/07 Mon 10/01107 Mon 10/01107 Tue 04129 /08 Mon 06/02/08 Non 07AM07 Mon 07102/07 Mon 07102107 Mon 07/02/07 Mon 06107/04 Mon 06/07/04 Tue 06/13/06 Man 12/11/06 Tue 04/01/08 Tue 04101 /08 Thu 12/28/00 Thu 12128100 Fri 12/01/06 Tue 09/11/07 Mon 12/03/07 Mon 07 /02/07 Mon 07/02/07 Tue 04/22/08 Mon 06/02/08 Tue 02108/05 Tue 02108105 Wed 02/01/06 J J A$ 1 O N D 1 J F M A M J J _ Fri 05/15/09 Mon 10113108) Tue 12/09/08 Fri 05/15/09 -- - Tue 04122/08 Tue 03/1 3/07 Tue 05/08/07 5/0 Tue 04/22108. Fri 11/23/07 Thu 09/20/07 - — Fri 11/23/07 Wed 02/27/08 Fri 10/17108 - Fn 03/07/08 Fri 08/22108 Tue 04129108 -04/29 Fn 10/17108 Mon 01108/07 Mon 06 /30/08 Tue 06/05/07 Mon 06/30/08 Mon 06 /30/08 Mon 06/30/08 Wed 12/12107 A S O N D Fri 05/05106 _ Tue 06113/06 Wed 12112/07. -... Mon 08/111/08 Mon 08/18/08 - -- - Fri 08101/08 Fri 06/29 /07 Fri 06/29/07 Tue 09/11/07 Fri 08/01108 Fri 08122/08 - — Wed 02/27/08 Tue 04/22/08 Fri 08/22108 Tue 08/05107. Mon 01108/07 Tue 06/05/07 Thu 10/18/07 Page 6 1 Thu 10/18/07 Page 7 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter ID Task Name Start Finish _ A O NIOIJIFIMIAIMIJiJ ASON D 356 Little Corona Restroom Facility Remodel Toe 06101107 Fri 06/13/08 357 (1) Design - In- House /Mark Reader - (p. 12) Toe 05101/07 Fri 11/23/07 -7 358 (2) Award Tun 01/08/08 Toe 01/08108 359 _ (3) Construction ($350,000 Not Funded) Mon 03/03/08 Fit 06/13/08 364 Marina Park Improvements Wed 08101107 Fri 09126/08 365 (1) Preliminary Design - Robbers Herman DesigNMark Reader Wed 08/01 /07 Fri 05/02/08 366 (2) Coastal Permitting (not (unclad) Mon 03/03/08 Fri 09126108 --- ' - -��� 11 Mariners Mile Waterfront Walkway - Prel- Plans/Permits Toe 06/01/09 Mon 12/31/07 12 Pierhead Line Extension - Cash & Assoc. ($175,750) Toe 06/01104 Mon 12/31/07 - - -:, 75 Mariners Park Restroom Tue01/01108 Fri 09103/09 76 (1) Design - Consultant - $26,000 - (P. 91) Toe 01/01/08 Mon 06123/08 77 (2) Award Toe 06112/08 Tue 08/12/08 12 78 (3) Construction (not- funded) Mon 091 Fri 04/03/09 58 Mariners Park Sports Field Improvements Mon 01115107 Thu 03127108 —MMMOMMEMW 59 (1) Design - RJM - $130,000 - (p. 89) Mon 0111907 Fri 08/03/07 60 (2) Award Tura 09/11107 Toe 09/11/07 ♦1I¢ I I ',, 61 (3) Construction ($792,587 & $68,629) - Environmental Construction Mon 10/08/07 Thu 03127108 13 Mesa -Birch Park Mon 0820107 Thu 03/20/08 14 (1) Design - Pederson - (P. 100) Mon 08/20/07 Fri 08131/07 15 (2) Award Toe 10/09/07 Too 10/09107 . 10 09 y - 16 (3) Construction ($357,000) - Belaire -West Landscape Men 11/05107 Thu 03120/08 306 Nelghborhood Traffic Management Improvements - Phase 2 Mon 10/01/07 Fri 08== 307 - (1) Design - Consultant - P. 68) Mon 10/01/07 Thu 03/13/06 308 (2) Award Toe 04/22/08 Toe 04122/08 ♦04122 309 (3) Construction ($150,000 & $49,200) Mon 06/02/08 Fri 08/08/08 J _ i Newport Bay Watershed Management Program ($650,000) Mon 01/08107 Wed 07/30108 — - 2 (1) Phase 1 Watershed Management Plan collaboration with IRWD Mon 01/08/07 Wed 12/05/07 3 (2) Prop 50 grant applications [$5 million] Mon 01106/07 Wed 12/05/07 4 (3) Final Watershed Management Plan including HAMP Mon 0907/07 Wed 02)06/08 5 - (4) Prop 84 grant applications [$10 million) Mon 09/03/07 Thu 04/10/08 ITS —- -- ` - - - - -- . 6 (5) Web portal and websde maintenance Mon 08106/07 Wed 07/30108 81 Newport Boulevard Right Tom Lane @ Hospital Road Toe 0327/07 Toe 11127107 82 (2) Award - ($786.889) - Hillcrest Contracting Toe 0327/07 Toe 03/27107 - - '.. 83 - (3) Construction ($541,109 & $321,780) Mon 06/11 /07 Toe 11/27/07 �- 352 Newport Center Park Wed 07105106 Fri 01=109 353 (1) Design - Hall & Foreman / Mark Reader - (p. 93) Wed 0710906 Fri 03128/08 - - -- -- 354 (2) Award Toe 0527/08 Toe 05/27108 355 (3) Construction ($200.000 & $600,000) Mon 07107/08 Fn 01/30/09 376 Newport Coast Community Center Thu 06/01/06 Toe 10/02/07 M 377 (3) Construction ($8,159.000) Thu 06/01/06 Toe 10/02/07 Thu 10/18/07 Page 7 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter ID Task Name Alan 302 Newport Coast Dr. at Pelican Hills Rd. North - Intersection Improvements Tue 04 110/07 303 it) Design - RBF - $100,000 Toe 04/10/07 364 (2) Award Tue 02/12/08 305 (3) Construction (not funded) Tue 04/01/08 95 Newport Coast Rain Gauges Mon 07102107 96 (1) Design (2 locations) - Geomatrix ($24,000) Mon 07/02/07 97 (2) Permits and easements (County and State Parks) Mon 08/13/07 98 (3) Installation ($20.000) Thu 07/24408 185 Newport Shores Street Ends Improvements - Phase 11 Tue 06/12/07 786 (2) Award Tue 06/12/07 187 (3) Construction ($74,150) Mon 07/09/07 385 Newport Termites Landfill Gas Remedialion Mon 04/04/05 386 0) Design - SCS /Gail Pickan - (p. 99) Mon 04/04 /05 387 (2) Award Tue 07/24/07 388 (3) Construction Mon 0903/07 378 Newport Theatre Arts Center Entry Improvements, Utilities Yard Building 3 Mon 100305 Remodel & Radio Tower Facilities Building 379 (1) Design - Jorgensen/Ruffing (p. 5,133, 100 & 105 - FY 06/07) Mon 1003/05 380 (2) Award - Big West Construction Tue 0522/07 381 (3) Construction ($300,286, 25,000, 125,000, 50,000 & 240,000) Mon 07/0207 389 Oasis Center Concept Study Fri 0601107 390 Study - Coffee/Was Morgan - (p. 14) - $52,100 Fn 06/0107 291 Ocean Birch Dr. and Oceanfront Alley Water Main Repl. Btw. 14th and 201h Wed 01102/08 292 (1) Design - In -House (p. 119, 120 & 123) Wed 01 /0208 293 _ (2) Award Tue 07/08/08 294 (3) Construction ($314,000, $750,000 & $100,000) Mon 08/11 /08 112 Ocean Pier FY 07108 Repairs and Inspection Tue 01/01108 113 (1) Design - M House (P• 96) Tue 01/01/08 114 (2) Award Tue 0708108 115 (3) Construction ($500,000) Mon 09/15/08 401 011field Improvement Program Mon 070207 402 (1) Ongoing oilfield management program (p. 133) ($453,400) Mon 070207 263 Pedestrian Coastal Access & Circulation Improvements - River Sidewalk Mon 0811307 264 - (1) Design - In House /Civilworks (p. 69) Mon 08113/07 285 (2) Award Tue 02/12/08 286 (3) Construction ($399,100) Mon 03110/08 225 Police Department Gas Pump Canopy Repair Fri 060107 226 (1) Design /Build - Shook Building Systems - (p. 15) Fri 0610107 227 (2) Award Mon 10/0107 228 - (3) Construction ($25,000) -- - Mon 10/15/07 Thu 10/18107 Finish _ 2008 _ J J A S O N D J F M A M J J I A S Mon 08/18/08 � Thu 12/27/07 Tue 02/72/08 Mon 08/18108 Wed 11105/08 �. Fn 08/10107 Wed 07123108 f Wed 11/05/08 Tue 11/13/07 Tue 06/12/07 12 Tue 11113/07 Thu 03/27108 MENOMMMMMMMMUMOMEMMONW Fri 05/11 /07 7 Tue 07/24/07 Thu 03/27/080— T� . Wed 04/02/08 Fri 03/09/07 Tue 05 /2207 2 - Wed 04/02108 -� Thu 08/30107 s 1 a Thu 08/30107 Fri 10/31106 Tue 05/20 /08 .. .._.._ Tue 07/08/08 Fri 10/31/08 - - -� Fri 12126108 Mon 05 /19108 Tue 07/0808 - Fri 12/26/08 - Mon 06/30/08 Mon 06 130/08 Fri 07 /25/08 - Wed 12/26/07 Tue 02/12/08 Fri 07125/08 Thu 01103/08 - - - Wed 0 ARVol Mon 10/01/07 -. � 1001 Thu 0110308 Page 8 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter start Finish 12M J A' S O N D J F M 28 Police Department Lobby Remodel -- — _ - - Tue 04=08 Fri 07/18/08 29 (1) Award . lip. 19) Tue 04/22/08 Tue 04/22/08 : LOS122 j 30 (2) Construction ($249,900 & $43,700) Mon 06/02/08 Fri 07/18/08 177 Public Docks Access Improvements Tue 01/01/08 Fri 11/28/08 178 (1) Design - Consultant - (p, 97) Tue 01/01/08 Mon 04/14108 �. 179 (2) Award Tue 06/10/08 Tue 06/10108 180 (3) Construction ($140,000) Mon 09 108108 Fri 1128/08 - - -- - 66 Rhine Whart Repairs & Rhine Channel Visitors Ship Dock & Ramp Fri 12101/06 Fri 11/21/08 . 67 (1) DesignfBuild - (P. 99) Fri 12/01/06 Thu 05/24/07 88 (2) Coastal Permitting Mon 10/01/07 Thu 03113/08 .� 69 - (3) Award Tue 05/13/08 Tue 05/13/08 aci 70 (4) Construction ($330,000 & $240,000) Mon 07/07MB Fn 11121108 31 SAN Joint Use Channel Maintenance & Equestrian Facility Thu 0201107 Fri 06/13108 32 (1) Design - Consultant -(P. 20) Thu 02/01/07 Wed 04/25107 _ -33 (2) Coastal Pemuning /Final Design Thu 0426107 Mon 07128/08 34 (3) Award Tue 03/11/06 Tue 03/11/08 _ t - -35 (4) Construction ($81,650) Mon 04 114108 Fri 06/13/08 146 San Joquin Hills Road Median Trees Mon 09 /03/07 Fri 07/04/08 147 (1) Design In House - (p. 53) Mon 09/03107 Thu 12/13/07 148 (2) Award Tue 01/22/08 Tue 01122/08 149 (3) Construction ($50,000) - Mon 03/0308 Fri 07 /04108 + �� 17 Semenluk Slough Dredging Project Tue 07/04/06 Too 03117/09 — 18 (1) Engineering. Permit and USACE Coordination - ($105K) - Noble Tue 07/04/06 Thu 05129/08 t9 (2) Award - (p. 115) - Army Corps Administered Tue D6/10/08 Tue 06110/08 . nsil n 20 (3) Consauchon ($350,000 & $300,000) Wed 10/01/08 Tue 03/17/09 150 1 Sewer Master Plan Update Thu 06101/05 Mon 06/02/08 Study - AKM Consulting - (p. 109) - $632,776 - FY06 /07 Thu 06101106 Mon 06102/08 : 165 Sewer Pump Station Improvements - Back Bay, Bren Tract, Diamond, Mon 10101107 Fri 08/28/09 Harbor Ridge and Polaris 166 (1) Pre - Design ($34,000) - Civillec - (P. 124) Man 10/01107 Thu 02/28/08 167 (2) Final Design ($200.000) - Consultant Tue 04/08108 Mon 11/03108 - -_- _ - 168 (3) Award Tue 12/09/08 Tue 12/09/08 -- -- 169 (4) Construction ($1,500,000 - FY 08109) - Mon 02702/09 Fri 08128109 104 Sidewalk, Curb and Gutter Replacement and ADA and Median Maintenance Mon 09/03107 Fri 08129108 Strips - City -Wide lmprovemems _ 105 (1) Design - In House . (P. 54 & 47) Mon 09703/07 Thu 12/13107 106 (2) Award Tue 01122A08 Tue 01 /22/08 107 (3) Construction ($695,600, $109,500 & $200,000 ) Mon 03/10/08 Fri 08/29/08 -, 21 Slope Repairs Thu 11/01/07 Tue 05127108 22 Design - In- House /Geotechnical - (p. 140) - $100,000 Thu 11/01/07 Tue 05/27/08 � � f �,'. - 403 Streetlight Replacement Program Mon 07102/07 Mon 06/30/08 404 (1) Ongoing streetlighl replacement Program (p. 57) ($240.000) Mon 07102/07 Mon 06/30/08 ' _ - -- - _ - -- - - -- Thu 10/18/07 Page 9 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter 152 Sunset Ridge Park 153 Concept Design - EPT DesgntW es Morgan (p. 101) - $150,000 188 Superior Avenue Median Improvements 189 (1) Design - ($30,000) - In- house/TCLA - Ip 58 & 56) 190 (2) Award 191 (3) Construction ($376,600, $200.000, $50.000 & $176.000) 192 Superior Avenue Street Rehabilitation 193 (1) Design - In House - (p. 59) 194 (2) Caltrans Processing 195 (3) Award 196 (4) Construction ($641,000 & $400,000) 279 Tennis Court Fencing Replacement- West Newport Park 280 (1) Design - Recreation Dept./In House - (p. 102) 281 (2) Award 282 (3) Construction ($130,000) 322 Traffic Signal Modernization Ph. 1 - Newport Center 323 (1) Design - Consultant - (p. 70) 324 (2) Award - ($1,071,685) 325 (3) Construction ($335,000, $59,400, $200,000 & $477,285) 326 Traffic Signal Modernization Ph. 2 - Jamboree Road SO (1) Design - Consultant - (p. 71) 328 (2) Award 329 (3) Construction ($750,000 & $300,000) 330 Traffic Signal Modernization Ph. 3. Airport Area 331 (1) Design Consultant - (p. 72) - ($150,000 & $100,000) 332 (2) Award 333 (3) Construction (Not Funded - FY 08/09) 318 Tragic Signal Replacement Program 319 (1) Design - Consultant - (p. 74) 320 (2) Award 321 (3) Construction ($251,800 8 $240,000) 9 Upper Bay Comprehensive Resource Management Plan (On Hold) 10 - Consultant Study - ($120,000) 62 Via Lido Crib Well Replacement, 36th Street at Finley Bulkhead Repairs, _ Rivo Alto Coping Repairs & 26th Street Tidal Structure and Bulkhead 63 (1) Design - In House - (P. 60 and P. 22, 52, & 21) 64 (2) Award - ($79,200. $281,000, $75.000.$108.000 & $389,000) 65 (3) Construction - ($836,000) -John. S. Meek Company 175 Water Master Plan Update 176 Study - In -House /Consultant - (Not Funded) Thu 10/18/07 Start Wed 08/01/07 Wed 08/01/07 Mon 03112/07 Lion 03/12/07 Toe 09/25107 Mon 10/08/07 Fri 12/01/06 Fri 12/01/06 Mon 06/04/07 Tue 01/08/08 Mon 02/04/08 Tae 05101107 Tue 05/01107 Tue 1127/07 Mon 12!10107 Thu 02/01/07 Thu 02101/07 Tue 0226/08 Tue 04/01/08 Thu 11101107 Thu 11/01/07 Tue 07108/08 Mon 09 /08/08 Mon 03/03108 Man 03/03108 Tue 0127/09 Mon 03102/09 Tue 01/01/08 Tue 01 /01 /08 Tue 06/10/08 Finish 1 2008 J J A S O N D J F M A M J J A S O N D Fri 05/02/09 Fri 05/02/08 _ Thu 03106/08 �^ Fri 07/06/07 1. Toe 09125/07 — Thu 03/06/08 Fri 06120108 Mon 05/21107 Thu 10/18/07 - ! Tue 01108 /08 Fri 06120/08 Fri 01/18/08 —EENMMRF. Fd 10/12/07 Tue 11/27/07 L.t 1127 _ Fn 01 /18/08 �� Mon 09115 /08 —MMMMMMMMMMMMMMMMW Mon 12/31107 __- r— Too 0226108 ♦ ZV6 - Mon 09/15108 Fr10220/09 Toe 05127108 Tue 07 /08/08 _ - '. �..117f09_, Fn 02/20/09 Fri 07/17/09 Fri 12/05/08 �- -.- -' Tue 01127/09 Fri 07117/09 - - - Fff 12/19/08 IV I Mon 04/14/08 r Tue 06/10/08 Fri 12/19/08 - _�— Tue 01101108 '.. ♦ Too 01/01108 ♦ ', Tue 07101108 Fri 08/03107 Tue 09111/07 Two 07 101/08 Fri 10110/08 I'd 10/10108 Page 10 Thu 10118!07 _ _ Page 11 FY 2007 -08 MASTER PROJECT SCHEDULE - 2nd Quarter ID Task Name Start Finish ' 12008 JJ AS O N D;J F M A M J A ON D 42 _ Water Well Rehabilitation - Dolphin Deep Wed M01107 Mon 05 119/09 143 (1) Design - Richard Slade and Associates - (p. 121) Wed 08101/07 Mon 11112107 144 12) Award Tue 12/11/07 Tue 12/11/07 Mi 145 (3) Construction ($150,000) Tue 01/01108 Mon 05/19/08 159 West Coast Highway Vision Plan Thu 11/01/07 Tue 03/18/08 �. 160 Study - Consultant - (p. 76) $80,000 Thu 11/01/07 Tue 03/18/08 181 West Newport Park @ Orange Street and Newport Island Playground Tue 01 /01/08 Fri 11/28/08 Equipment 182 (1) Design - In House /Sean Levin - (p. 103) Tue 01101108 Mon 04 /14/08 - - -. 183 (2) Award Tue 06/10108 Tue 06/10/08 184 (3) Construction ($32.000. $60.000 8 $60.000) Mon 09/08r08 Fri 11128108 138 WestcllR Street Light Improvements and Bonita Creek/San Miguel Mon 10/02/06 Mon 07/28/06 Lightpole Reptacernann - - 139 (1) Design JMD.0 - (30,000) - (p. 84 E 57) Mon 10102/06 Thu 09/27/07 140 (2) Award Tue 11/27 /07 Tue 11/27/07 141 (3) Construction ($353,5008 125,000) - Tue 01 /01/08 Mon 0728/08 Thu 10118!07 _ _ Page 11