HomeMy WebLinkAbout2.0 - Back Bay Landing PCDP and EIR - PA2011-216Memorandum
CITY OF NEWPORT BEACH
COMMUNITY DEVELOPMENT DEPARTMENT
PLANNING DIVISION
100 CIVIC CENTER DRIVE
NEWPORT BEACH, CA 92658 -8915
(949) 644 -3209
To: Planning Commission
From: Jaime Murillo, Senior Planner
Date: November 1, 2013
Cc: Brenda Wisneski, James Campbell, Leonie Mulvihill, and Tony Brine
Re: Back Bay Landing PCDP and EIR (PA2011 -216)
The following two documents are being forwarded to you in advance of the
November 7, 2013, Planning Commission Study Session to provide you with an
opportunity to preview the project and to begin reviewing the Draft Environmental
Impact Report for compliance with the California Environmental Quality Act (CEQA).
The documents can also be accessed online at:
http://www.newportbeachca.gov/cegadocuments.
Draft Back Bay Landing Planned Community Development Plan (PCDP)
The purpose of the PCDP is to establish appropriate zoning regulations
governing land use and development of the project site. The PCDP provides a
vision for the land uses on the site, and sets the development standards and
design guidelines for specific project approvals for the future Site Development
Review process. The PCDP also regulates the long term operation of the
developed site.
Draft Environmental Impact Report (EIR
The Draft EIR analyzes potential environmental impacts resulting from a future
project developed consistent with the development limits, standards, and guidelines
established in Draft PCDP and required public improvements. The Draft EIR was
released for a mandatory 45 -day public review period that began on October 4, 2013,
and concludes on November 18, 2013. Responses to comments will be included with
the project staff report to be distributed in advance of the anticipated December 19,
2013, Planning Commission meeting.
Please keep these documents for the December 19, 2013, meeting.
BACK BAY LANDING PROJECT
Planning Commission Study Session
November 7, 2013
PURPOSE OF MEETING
• Project preview to facilitate Planning
Commission review of the documents in
advance of public hearings
• Provide status of the Draft EIR
• Answer questions
PROPOSED PROJECT
• The Back Bay Landing project involves two
stages of approvals:
1. Legislative Approvals (e.g., General Plan Amendment, Coastal
Land Use Plan Amendment, Planned Community Development
Plan), which comprise the current "proposed project "; and
2. Administrative Approvals (e.g., Site Development Review,
Coastal Development Permit), which will be pursued at a later
date for a future development on the project site.
PROPOSED PROJECT
While only Legislative Approvals are currently
being sought, the EIR will evaluate impacts of the
currently proposed Legislative Approvals, as well
as those of the future development project to the
extent feasible.
Balboa
�4 +Ill I is[1I7
Newport
Beach
BACK BAY
LANDING
MIXED -USE
'ROJECT AREA
Newport Bay
Back Bay Landing is located immediately
north east of East Coast Highway in
/Newport Beach, California. The site is
bounded by East Coast Highway and
Newport Harbor on the south and west,
Bayside Drive to the south, the Newport
Back Bay channel to the west and Bay -
side Village Mobile Home Park to the
southeast.
Legend
— Project Area (Parcel 3 of PM 93 -111)
Beck Bey Landing Mixed -Use Project Area
— Existing PC -9 Boundary
— Proposed PC -9 Boundary Expansion
C w 'rBaysitle Village
F
� bile Home Pad
�.
Lot Line`
d'us1 ent
l l
1
PARCELI
(PM93 -111)
rte: r� BACK BAY
``� LANDING
• MIXED -USE
,... PROJEC`T•AR�
Parking 8 Marine
jEquipment Storage Sewer •:: °r
Under Coast Hwy Bridge Pump House
SO Property)
oil
III
bl
P
Source: Google Earth
EXISTING CONDITION, PROJECT BOUNDARY
& LOT LINE ADJUSTMENT 30.20
N.T.S.
9
Lot Line Adjustment Area
'� - --
Back Bay Landing Mixed -Use Project Area
Project Area (Parcel 3)
�.
Parcel 1 & 2 Boundary Line
�t ......••
Existing PC -9 Boundary
......••
Proposed PC.9 Boundary Expansion
Storage Garages &
Marina/ Bayside Village
Guest Parking
rte: r� BACK BAY
``� LANDING
• MIXED -USE
,... PROJEC`T•AR�
Parking 8 Marine
jEquipment Storage Sewer •:: °r
Under Coast Hwy Bridge Pump House
SO Property)
oil
III
bl
P
Source: Google Earth
EXISTING CONDITION, PROJECT BOUNDARY
& LOT LINE ADJUSTMENT 30.20
N.T.S.
9
PROPOSED PROJECT
• Legislative Approvals currently being
requested:
— General Plan Amendment (GPA)
— Coastal Land Use Plan (CLUP) Amendment
— PC -9 Amendment (Zone Change)
— Planned Community Development Plan (PCDP)
— Lot Line Adjustment (LLA)
— Traffic Study
General Plan
Coastal Land Use Plan
Zoning
Existing & Proposed
Existing & Proposed
Existing & Proposed
Land Use Designations
Land Use Designations
Zoning Designation
Changes: CM 0.3 no change, CM 0.5 & RM
Changes: CM 0.3 no change, CM -B 0.5 FAR &
Changes: PC -9 boundary extended to include (PC-1
changed to MU -H7
RM -C changed to MU -H
MHP) LLA & project area south of CH centerline
Existing
Existing
Existing
ENTITLEMENTS
/
atl6
wa«mwa
/Wnm Cu,mmltlY
8-30-2013
u i
aw
C9IIFOitN`P
wI�
ARM
M-C
RuL
PL 1 MMp b
> a�w
d
vvs{ wi.l. cv.vwad
n.ma.wa
A
m cam.
CMOs [uc.
CM B LMe
v•
PG9
wmc�.ao. e,. cam<nn
un
wsm�c°°°'a uuo""q
�w.waauw. ww.<µ
CM 03
CMA
w EM
���
Proposed
Proposed
Proposed
i
M6Po 'r wr w no
MLLR M+
CA
Mn<ixWn Emlfgy MBM�il{TMeE
�
1Y<wbNa EM Ga<My MV- MPoPOiM m[biP[elgnlo f[e
Mm CUmgal E�a'�MPEP <mMib
ym�y,m�� CM.rIeILxM USe PIJn lkaynif�n a
Ea. Ry<
Oavp09mivMbwrvWVYt Sr
CM03
Wwu ror mmnva rycurie row
Ym4tWU MnWP
ajFM ruHSIOY Sw EPJWbna in POOP.
Source:
Anomaly 0
Nonresidential
Only
131,290 SF
MAMWOI 0=2
171,289 SF
1:1 ratio
49 units
Anomaly 0
296 units
EXISTING & PROPOSED
LAND
USE
��WPORr
DESIGNATIONS
&
RE
-VESTED
ENTITLEMENTS
8-30-2013
u i
aw
C9IIFOitN`P
Planned Community Development Plan
Purpose
• establish zoning regulations governing
land use and development of the site
• provides a vision for land uses on the site
and establish design guidelines
• regulates long -term operation of the site
Planned Community Development Plan
Permitted Uses
• marine - related (e.g. enclosed dry -stack boat storage, marina,
boat sales, boat rentals, boat service, kayak and paddleboard
rentals, etc.)
• visitor - serving commercial and recreational uses (e.g. retail,
restaurant, personal services, office, etc.)
• residential (vertical mixed -use and freestanding)
Development Standards
• Setbacks, Building Heights, Residential, Parking,
Landscaping, Bulkhead, Dredging, Public Bayfront
Promenade and Trail, Vehicular Circulation, Lighting,
Signage, Utilities, Sustainability, Public Improvements
Planned Community Development Plan
Design Guidelines
• Architectural Theme, Site Planning, Building Massing,
Fagade Treatments, Public Views, Parking Structure,
Public Spaces, Landscaping, Hardscape, and Signs
Implementation
• Site Development Review- Planning Commission Public
Hearing
• Ensure future development is fully consistent with
General Plan, Coastal Land Use Plan, and Back Bay
Landing Planned Community Development Plan,
including design guidelines.
1
RECREATIONAL &
MARINE COMMERCIAL
(0.642 ac)
PARCEL 3
I Planning Area 3
EXISTING PRIVATE MARIN
ACCESS AND BEACH
(0.&59 ac)
Planning Area 5
Bayside Village
Mobile Home Park
0
.OT LINE ADJUSTMENT AREAS-- ti
(0.304 AC. in Parcel
CJ0
aeo
�' �` Parcel 3 Summary
P. A.
Description
Acres
Mixed -Use Area-
5.132
(North of CH centennial
ac
Recreational Its Marine Commercial
0.542
(South of CH centerline)
ac
Existing Private Marina
0.659
Access and Beach
ac
Marina and Bayside Village
0.541
Mobile Home Park Storage and
are
Guest Parking
Submerged Fee -Owned
24.457
Lands (Area includes De Anza
ac
Bayside Marsh Peninsula)
Parcel 3 Total Area'
31.431
ac
'Includes 0.304 ac LLA from Parcel }
Newport Dunes
Waterfront
Resort & Manna
i' ,�" MARINA AND BAYSIDE VILLAGE
!j MOBILE HOME PARK STORAGE
AND GUEST PARKING
(0.541 ac)
East Coast Highway
C
PlanninLy Areas
Conceptual Site Plan
Coastal Public View Tower
Public Marina
Public Walkway
& Vehicle Turn - Around
Lockers & Resbooms
Connection
Primary Entry
Offalte Exiling =�
Mobile Homes
Public Bayfront
Access
OMafte Existing
- -
- - - - •
Mobile Homes
I
mn v>w. F,�.aPo I
O11
I
�� mrsb,ea.
ee°ryw
II
Stand
Patltlle Board
-
Rental,
�-
- - Storage
-
East Coas
Conceptual Site Plan
/ - -- Elevation ll'--1r
_ - Elecafmn 14'
/ PA 1
/ i 3511 Building
Height Zone
% J IorMYror Meaewam
of HegM: 111
/ 1
L ding one e—I w X sell e moll
Building Height Zones
East Coast Highway —
Bridge Over Newport Bay
ECH Elevation
Buildin
Grade Baseline Elevations
to Measure Building Height
East Coast Highway
Aoorox. 56011
Heights
PA 4
la,aoa w M.mxwnM
aHeiglK tx)
' PA t
26 It Building
Height Zone
Rtra
d M mmR
nMghr nc 14 u'::
tmm31 to xs a nn ma
or 31 X ebpetl moX
I
PA 1
3511 Building
10011
Low Profile Building
From ECH
East Coast Highway
65' Coastal Public Remodeled
View Tower Existing Sewer
(Public 8 ADA Accessible) Pump Station
35 ft
EXHIBIT 3
BUILDING HEIGHTS
DESIGN GUIDELINES
East Coast Highway is approximately
22 feet above the Back Bay Landing
development site limiting the
development's impact on views from
East Coast Highway.
There are three finished grade
baseline elevations indicated on the
exhibit from which the building
heights are measured: 11, 12, or 14
feet.
Bayside Drive
Existing 2 -story Mobile Home
8
Paboo view
mto site nom
cant. ways
Perk
Castaways
Park
East Coast Highway —
Bridge Over Newport Bay
Coastal Public View Tower
(Public & ADA Accessible)
East Coast Hlgh"'i
O
©
O
View Corridor
View Corridor
View Corridor
at angled condition
TT
ECH SECTION /ELEVATION AND VIEW CORRIDOR
View Corridors
View Corridor
—f
O
View Corridor
i
East Coast Highway
Remodeled
Existing Sewer
Pump Station
EXHIBIT 13
EAST COAST HIGHWAY
VIEW CORRIDORS
DESIGN GUIDELINES
Varied roof heights and undulating build-
ings add variety to the street scene. Along
the East Coast Highway and Bayside
Drive, Five scenic view corridors are pre-
served (3,4,5,6,7). Two new view corridors
were created (1,2).
O O
View Corridor View Corridor
eaysitle Drive
Existing Mobile Home
East Coast Highway and Bayside Ddw
Coastal Public View Tower
Public Sayfront Promenade
Vlsitor'Serving Commercial
View from Bridge along East Coast Highway
Coastal Mediterranean Theme
,a
/ m
s
2 LCa,^
q
�\ BACK BAY
� LANDING
1. Regional Trail Connections
UWu
Newport
6nlpoa
Lateral Access--
...... . ........... .. .........
Proposed Coastal
Public View Tower
2. Proposed Coastal Access
3. Current Lack of Trail Connection
New Public
k Bayfront Access
New Class 1 & 3
991$093 Off-Street Bikeway
-,"• �& Pedestrian Trail
cy
It t.�, „n n�
e=�4•„� h New Class 1 & 2
-y Off- Street Bikeway
„�cws' "4 ^• +r & Pedestrian Trail
4. Critical Trail Connections
Public Access and Trail
COASTAL ACCESS
AND REGIONAL TRAIL
CONNECTIONS
Back Bay Landing provides coastal access
and a critical link between existing regional
trails.
1. Regional Trail Connections
2. Proposed Coastal Access
3. Current Lack of Trail Connection
4. Critical Trail Connections
Legend
Trail Types
•••••
New Public Bayfront Access
Accessible to Pedestrians & Cyclists
eeeeee
New Class 1 & 2 Off-Street
Bikeway & Pedestrian Trail
New Class 1 & 3 Off - Street
Bikeway & Pedestrian Trail
Existing Class 1 Trail
Existing Class 2 Trail
Existing Class 3 Trail
mommomme
Lateral Access
mommomme
Vertical Access
♦
Public Beach Access Location
{p
Public View Point
Coastal Public View Tower
(Public & ADA Accessible)
Waterfront
Boat Launching Outdoor Dining
and Haul Out Aroa�
Bayside Plaza
Public Bayfront
Promenade
.—I
Kayak &—
Stand Up
Paddle Board
Rental.
Launch &
Storage
Boat service
Vlnn Mm
A)5N
Poai Cry SaakHwi
Omt Y.uuye
l
Public Parking
for Kayak Launch
Public Spaces
H«b.,
P sEeeNN
sm.ax
Access Gate to Marina
Pedestrian /Auto Plaza
Public Marina Lockers
& Restrooms
rRetail on Ground Floor
—�
` r 1
Hm.i.r Restaurant
H�,emra
Connects to
Regional Trail
rm
Dining
J� Gmt+g
neiyi sHmn 'i
.y Bayside�Drive Trail
_ J'J
Bus Stop Retail Plaza
Public Use of Enclosed a
Dry Stack Boat Storage East Coast Highw Y '
(Privately Owned)
Public Parking for Retail, Marina & Bayside Village Mobile Home Park
Upper Parking Deck Provides Views to the North and South
Bulkhead
The project bulkhead may be built to the
Highest High Water elevation of 7.86'
relative to Mean Lower Low Water (0.0') or
7.48'INAVD 88 to preserve the natural
profile along the shoreline adjacent to the
County Tidelands, subject to consistency
findings in the Coastal Act and City of
Newport Beach Coastal Land Use Policies.
12 - 0'
Public Bayfronnt Promenade
Finished Grade at Top of Bulkhead Wall +10'
-- -- - - - - -' �-- --- - -- Back Fill Area
Front of Bulkhead Wall
Highest High Water line ( +7.86')
_ — above Mean Lower Low Water (0)
_ _ _ _ — — Existing Grade
Depth to be Determined
Bulkhead
Mobile Home
Guest Parking
Adjusted Property
Line
Existing Bayside Village Circulation
Existing Gated .
Marina Access
Fire Truck
Turn Around
J
Original -
Circulation
' Mobile Home
Guest Parkina
Proposed Bayside Village and Back Bay Landing Auto Circulation
Existing Back - Bay Landing Property
Entry Location
Entry Location
(Moved approximately 45 It
north of existing entry)
Relocated Drivewav /Lot Line Adi 0
IF
Z
v
2
c�
z s
(ON � ,E'
' • - '/ CIASS2 '
10"6 Elf
BIKE LANE
` cuss r
.IF ARBETj `
BIREWAV6
rain '
` anow goo % Mobile
Fire Truck
Turn- Arountl
1
i
Emergency
�r
Turn - Around
Under Bridge
Primary Vehicular
IAccess
I
OCTA Bus Stop ,
Optional Secondary Access
Deceleration and right -tum movements only
Street Imbrovements
0�
C�
Newport Dunes
Waterfront
Resort & Manna
Secondary Gate
Guarded Vehicular
Access for Marina
Parking, Public
Storage and Existing
Restrooms
i
•
Utlll
Proposed
Join Existng Storm Drain
24" Water Line
_Si
' r ``r`\i`•�� •C•�
Proposed -i, i• i --• -
Storm Drain ' ' �, /'; `•fC+ '
• ^ Y =��
Y '�a!�su Water V ro be R em + Proposed 30]�
'pygd Steel Water Line
s AIL 2
Proposed 8' Water
Proposed 8' Sewer 0
Y Existing Sewer
Y _ Pump Station
NY
Join Existing`
12' Storm Drain 1
F Proposed
Storm Drain
Proposed 8" Water
Proposed 8" Sewer
1/\
Join Existng
12" Water Line
r -;
r Jolp Existing
38'Seyrer Line
i
r y
r1 v - - -- I Join Existing
� 30" Water Line
Proposed 30-
36M Will rw
'Jinn Existing- �' % °�=
30" Storm Dwin Y �s
ovements
Legend
�r-
s -
Proposed 8" Water
30" Steel Water Line - All 1
30- Steel Water Line - All. 2
Proposed Sewer
Proposed Storm Drain
Existing Water
Existing Sewer
Existing Storm Drain
ENVIRONMENTAL IMPACT REPORT
• The Draft EIR analyzes potential
environmental impacts resulting from a
future project developed consistent with the
development limits, standards, and
guidelines established in Draft PCDP and
required public improvements.
• 45 -day public review period —
October 4, 2013 to November 18, 2013
• Responses
to
comments to be
provided with
December
19,
2013,
Planning
Commission
agenda packet
ENVIRONMENTAL ISSUES TO BE
ANALYZED IN THE EIR
• Aesthetics • Land Use /Planning
• Air Quality • Noise
• Biological Resources • Population /Housing
• Cultural Resources • Public Services (Fire,
(Archaeology, Police, Schools, Libraries,
Paleontology, and Parks)
Historic Resources) • Recreation
• Geology /Soils
• Greenhouse Gas
Emissions
• Hazards /Hazardous
Materials
• Hydrology /Water Quality
• Transportation /Traffic
• Utilities and Services
Systems (Water, Sewer,
Solid Waste)
• Project Alternatives
t SEW ART
• Growth Inducement @�
a..
C9GI F05t
Maximum Development Scenario
Maximum Development Scenario
North of East Coast Highway Centerline (PA 1 and 4)
Retail /Marine Sales and Repair
Quality Restaurant
High- Turnover Restaurant
Office
Enclosed Dry -Stack Boat Storage
Storage Area (resident and boat lockers)
32,859 square feet
4,100 square feet
3,500 square feet
8,685 square feet
32,500 square feet (up to 140 spaces)
4,000 square feet
Non - Residential Total North of East Coast Highway Centerline: 85,644 square feet
Residential Total North of East Coast Highway Centerline: 85,644 square feet (up to 49 units)
South of East Coast Highway Centerline (PA 2)
Non - residential (marine services, office) 8,390 square feet
Project Site Total 179,678 square feet
Marina (existing) 220 wet slips
Next Steps:
*Harbor Commission- Nov. 13, 2013
*Planning Commission Public Hearing — Dec. 19, 2013
For more information contact:
Jaime Murillo. Senior Planner
949 - 644 -3209
imurilloCa)newportbeachca.4ov