<,FORN'P City Council Staff Report
February 11, 2020
Agenda Item No. 12
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Patrick Arciniega, Senior Civil Engineer,
parciniega@newportbeachca.gov
PHONE: 949-644-3347
TITLE: Restroom Buildings Maintenance Project — Notice of Completion for
Contract No. 7509-1 (18F02)
ABSTRACT:
On November 27, 2018, City Council awarded Contract No. 7509-1 for the Restroom
Buildings Maintenance Project (18F02) to TL Veterans Construction, Inc. While TL
Veterans completed a majority of the work, they were unable to satisfactorily complete
the entire scope of the project. As a result, staff deleted the remaining work and requests
City Council acceptance and close out of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
FUNDING REQUIREMENTS:
The construction contract was expensed from the following accounts:
Account Description
FMMP
Account Number
57101-980000-18F02
Amount
$ 130,883.45
Total: $ 130,883.45
12-1
DISCUSSION:
Restroom Buildings Maintenance Project — Notice of Completion for
Contract No. 7509-1 (18F02)
February 11, 2020
Page 2
Overall Contract Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$164,500.00
$130,883.45
10% or less
-20.5%
-20.5%
0.0%
Allowed Contract Time +
120
Actual Time
-36
Approved Extensions (days) =
Under (-) or Over (+)
This project's scope included repair and updates to eight (8) of the City's public restrooms.
These restroom facilities are located at 58th Street, Channel Place Park, Eastbluff Park,
Port Westbourne Park, Irvine Terrace Park, Buck Gully/Little Corona Beach, Balboa Pier,
and Corona Del Mar State Beach. The planned work included new paint, flooring,
plumbing, ventilation screens, LED light fixtures and lamps upgrades, water bottle filling
stations, security gates, and some timber support beam replacements.
Five (5) of the restrooms were restored at 100% of scope. The remaining three (3)
locations were not completed to the satisfaction of the Public Works Department. The
original project foreman left TL Veterans near the start of construction and was never
replaced. The restroom remodel work was not progressing in a satisfactory manner, and
in an effort of good faith, staff agreed to allow TL Veterans to return after the summer to
complete the remaining work after Labor Day.
Throughout construction TL Veterans failed to complete basic construction tasks such as
providing submittals in a timely manner, providing supervision to workers, clearly
communicating with the Public Works Department, and updating project schedules.
Staff eliminated the remaining work at the following three locations: Channel Place Park
Restrooms, Balboa Pier Restrooms, and Corona del Mar Restrooms. Planned work
completed in these locations varied from 0% - 87%. The remaining work will now be rebid
in the upcoming "Multi -Facilities Rehabilitation Project" being prepared currently and
planned for construction in Fall 2020.
The portion of the work that was finished was completed to the satisfaction of the Public
Works Department. A summary of the construction cost is as follows:
Original Bid Amount:
$
164,500.00
Actual Cost of Bid Items Constructed:
$
128,683.45
Total Change Orders:
$
2,200.00
Final Contract Cost:
$
130,883.45
12-2
Restroom Buildings Maintenance Project — Notice of Completion for
Contract No. 7509-1 (18F02)
February 11, 2020
Page 3
The final contract cost for all the work completed was $130,883.45, which was
approximately 20.5 percent lower than the original bid amount. The actual cost of bid
items constructed ($128,683.45) was less than the original bid amount ($164,500.00) due
to the deletion of the remaining work on this contract.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule 06/17/19
Actual Start of Construction Per Notice to Proceed 02/07/19
Contract Completion Date 11/04/19
Construction Stop Date (date contract was terminated) 09/19/19
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301 (a) (Interior or exterior
alterations) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3,
because it has no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
12-3
CITY OF COSTA
MESA
Q
0
17T
15TH S
PROJECT LOCATIONS
JOHN WAYNE
AIRPORT
p4CIF/C
ocFq1v
Attachment A
s�
1 �
I Cl TY OF
/// IRVINE
P�
UNIVERSITY
VICINITY MAP
NOT TO SCALE
RESTROOM BUILDINGS
MAINTENANCE PROJECT
LOCATION MAP
�I
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-7509-1 1 2/11/20