Early Look
Fiscal Year 2021-22
Capital Improvement Program
City Council Study Session
March 9, 2021
City Council Goals for Allocation to CIP
✓ Budget Focuses Resources on Maintaining or
Replacing our Existing Infrastructure to keep it in Good
Working Condition
✓ Assumes $5,000,000 General Fund Investment
towards Citywide Infrastructure Maintenance & Repair
✓ Continued Investment in Newport Harbor, Parks and
Replacement or Rehabilitation of Public Buildings
How New Projects are Selected for the CIP
Identified & Scheduled through City Master Plans
• Facility Finance Plan (updated yearly)
• Facility Maintenance & Management Plan (updating in 2021)
• Pavement Management Plan (updated yearly)
• Water Master Plan (updated in 2019)
• Sewer Master Plan (updating in 2022)
Identified/Requested by Community, Council or
City Department Staff
Developed to Support City Council Goals and Objectives
Required by Federal, State Law or Legal Action
Significant Projects Recently Completed — $14.9 M
➢ Bison Avenue, San Joaquin Hills Road and San Nicolas Drive Pavement
Rehabilitation
➢ Bonita Canyon Drive and Ford Road Pavement Rehabilitation
➢ West Coast Highway Median Landscaping
➢ 2019-20 Playground Improvement Program
Newport Shores Park, Bob Henry Park and Mariners Park
➢ Concrete Street Pavement Reconstruction
Anade Ave., Montero Ave., Alvarado Pl. and 6t" St.
➢ 2019-20 Slurry Seal Program
Newport Coast and North CDM
➢ Cameo Highlands Street Reconstruction
➢ Police Station Gun Range Remodel
➢ Newport Pier Area Water Main Replacement
Significant Projects Under Construction - $28.4 M
➢ Grant Howald Park Rehabilitation
➢ Big Canyon Restoration Project — Phase 2A
➢ Fire Station No. 2
➢ Via Lido Soud and Nord Water Main Replacement
➢ Assessment District 111 and Underground
District 22 — Phase 2
➢ Arches Dry Weather Diversion Project
➢ FY 19-20 Traffic Signal Rehabilitation Project
➢ Water Transmission Main Valve Replacement
➢ Balboa Boulevard Crosswalk Improvements
➢ Corporate Yard Rear Fence Replacement
$30.6
$39.2
tkQBU H p?$2
C/7y.pFN�WFO�T ge HWMIJ
Million New Funding
Million Re -budget from FY 2020-21
Some Large Re -budget Projects - $26.3 Million
• East Coast Hwy Rehab
$3.6 M
N award Summer
• American Legion Bulkhead
$1.4 M
- award Summer
• 161h Street Pump Station Rehab
$2.0 M
N award Summer
• Utilities Undergrounding ADs
$5.9 M
N award Summer
• Superior Ave Overcrossing
$3.5 M
N award Fall
• Newport Bay Water Wheel
$1.4 M
^' design 2020-22
• Harbor Dredging & Ocean Piers
$4.9 M
N design 2020-22
• Balboa Island Drainage Imp.
$2.2 M
N design 2020-23
• Bay/Channel Utility Crossings
$1.4 M
"' design 2021-23
Deferred Projects list from FY 2020-21
a o N
O
Ln a LL
�
N w o
Project Title
Notes
PROJECTS THAT WERE PARTIALLY DEFERRED
Alleys Reconstruction Undertake Design in FY 2021-22. Programing with alternative funding
$400,000
X
Facilities Maintenance Master Plan Normal annual Programing of $1,500,000/year. Could return supplemental funding when surplus allows.
$500,000
$500,000
Design Underway. Construct only missing sidewalk and modest viewing area now. Defer remaining pavement
Ocean Boulevard Concrete Pavement
replacement to at least 2023-24.
$1,600,000
$250,000
$1,350,000
Streetlight Rehabilitation Program Design Complete (includes Spyglass Walkway). Program Construction in FY 2021-22 if NE funding is available
$700,000
$416,000
PROJECTS THAT WERE DEFERRED
Balboa Boulevard Median Improv Design Underway. Program Construction Funding in FY 2021-22? Proposed $850k BVAC, $1 mil NE
$1,872,236
$1,850,000
Balboa Island Enhancements Could be used for Benches/Other, Deferred, or Returned to GF
$88,400
Central Library Lecture Hall Continue with Design Only in FY 2021-22 (encumbered). Release and Reprogram Construction Funding
$7,360,052
$7,260,052
Cliff Drive Mobility Improvements Program funding and start Study/Project in FY 2022-23.
$250,000
$250,000
Cliff Drive Park Clubhouse Complete Design 2021. Program Construction Funding in FY 2021-22. Change Funding from FFP to BET
$540,000
x
Collins Islands Bridge Replacement Allow School Traffic Patterns to normalize. Begin Design/Permitting in FY 2021-22.
$150,000
x
Facilities Strategic Planning Proposed to be used for Pool Study. Defer or Cancel?
$50,000
$50,000
Junior Lifeguards Building Continue Design Only in FY 2021-22 (encumbered). Release and Reprogram Construction Funding
$3,179,991
$3,079,991
Landscape Enhancement Program Address a couple of Community Request (Breakers Drive, Lido Park Rehab, Lido Island Median,?) in FY 2021-22.
$623,512
$350,000
Marine Ave Rehabilitation Work on Island Drainage, Undergrounding & Utility Imp. Include with future Island Street Replacement
$231,129
Newport Blvd Landscape Rehab Continue with Design only in FY 2021-22 (encumbered). Propose Construction 2022-23
$711,270
$711,270
Ocean Boardwalk / Parking Lot Improv Award Study/Design in FY 2021-22
$350,000
$350,000
Orange Coast River Park Vision Plan City Council Approved Funding Match Assistance. Defer until Directly Requested
$20,000
$20,000
Park Walls and Staircases Rehab Continue to Defer - Staff to Monitor
$500,000
$500,000
Continue with Design Only in FY 2021-22 (encumbered). Defer Construction Funding Pending Outcome of 20b
Santa Ana Avon Slope Improvements
Resident Undergrounding effort
$335,070
$335,070
West Newport Park Rehabilitation Looking for Other Funding Solution, Maybe out of Operating Budget
$225,500
x
West Newport Streetscape Continue with Design only in FY 2021-22 (encumbered)
$486,560
$100,000
$486,560
$100,000
WC Highway Median Landscaping Continue to Defer. Re-evaluate in FY 2022-23
Note: X Denotes project Funding being supplied by other source Total > >
$20,273,7201$3,216,000
1
$14,642,943
FACILITIES [New proposed funding]
➢ Central Library Lecture Hall (Design)
➢ City Yard Fueling Support Facilities (Design)
Rebudgeting - $306,616 for a total of $406,616
➢ Cliff Drive Park Clubhouse Rehabilitation
➢ Facilities Maintenance Master Plan
Rebudgeting - $743,956 for a total of $2,243,956
➢ Junior Lifeguards Building (Design)
➢ Junior Lifeguards Bdg. — Parking Lot Imp. (Design)
➢ Transfer Station Upgrades & Refuse Scale (Design)
TOTAL FACILITIES (New $)
* FY 2020-21 Deferred Project
$100,000 FFP
$100,000 GF
$350,000 * BET
$175007000 FMMP
$100,000 FFP
$75,000 GF
$50,000 GF
$2,275,000
GF - General Fund FFP - Major Facilities Finance Plan
FMMP - Facilities Capital Maintenance Program BET - Building Excise Tax
STREETS & DRAINAGE [New proposed funding]
➢ Alleys Reconstruction $250,000 * GF
Rebudgeting - $522,273 for a total of $772,273
➢ Collins Island Bridge Replacement (Design) $150,000 * GF
➢ Concrete Replacement Program (Newport Heights) $700,000 GF
➢ Slurry Seal Program (Newport Heights) $9961000 GF
➢ East Coast Hwy Pavement Rehab $400,000 GT
(MacArthur Blvd. to Newport Coast Drive)
Rebudgeting - $3,634Y 050 for a total of $4,034, 050
STREETS & DRAINAGE CONTINUED...
* FY 2020-21 Deferred Project
GF - General Fund GT- Gas Tax
STREETS & DRAINAGE [New proposed funding]
➢ Jamboree Road Pavement Rehab
(Ford Road to Coast Highway)
Rebudgeting - $1,236 for a total of $5,035,786
➢ Newport Coast Drive Pavement Rehab (Design)
➢ Old Newport Blvd/WCH Modifications (Row)
Rebudgeting - $5,440 for a total of $105,440
➢ Pavement Management Plan Update
$5,034,550 SB1/GT/
M2/WF
$400,000 GT
$100,000 GF
$30,000 GF
➢ Street Pavement Repair $700,000 GF
(Mission Bay Drive and other Spot Repairs)
Rebudgeting - $122,090 for a total of $822,090
STREETS & DRAINAGE CONTINUED...
GF - General Fund WF - Water Fund GT- Gas Tax S81 - S81 RMRA M2 - OCTA Measure M
STREETS & DRAINAGE [New proposed funding]
➢ Via Lido Nord & Soud Pavement Rehab
Rebudgeting - $150, 000 for a total of $1,350, 000
➢ Balboa Boulevard Pavement Rehab (Design)
(West Coast Hwy to 23rd Street)
➢ Beach Access Street Ends - Peninsula Point (Design)
("G'; `7' and 1" Streets)
$172007000 GF/WF
$150,000 GF/WF
$150,000 OEF
TOTAL STREETS & DRAINAGE (News) $%2603550
GF - General Fund OEF - Oceanfront Encroachment Fund WF- Water Fund
TRANSPORTATION [New proposed funding]
➢ Balboa Peninsula Summer Trolley (7 year program)
Rebudgeting - $697,394 for a total of $847,394
➢ Neighborhood Traffic Calming (Dover shores)
➢ Traffic Signing, Striping and Marking
Rebudgeting - $165,027 for a total of $215,027
➢ Traffic Signal Rehabilitation Program
Rebudgeting - $963,668 for a total of $1,713,668
TOTAL TRANSPORTATION (News)
$150,000
U . o
$1457000 GF
$50,000 GF
$750,000 GT
$1,095,000
GF - General Fund GT- Gas Tax BVP - Balboa Village Parking Mgmt District
a
a
WATER QUALITY & ENVIRONMENTAL
[New proposed funding]
Newport Bay Water Wheel
Rebudgeting - $1,390,400 for a total of $1,890,400
Santa Ana Delhi Channel Dry Weather Diversion
TOTAL WATER QUALITY & ENVIRONMENTAL (New $)
M2 - OCTA Measure M UNB - Upper Newport Bay Reserve
$5007000 M2
$360,000 UNB
$860,000
PARKS, HARBORS & BEACHES
[New proposed funding]
➢ Superior Pedestrian Bridge and Parking Lot
Rebudgeting - $3,538,768 for a total of $7,200, 000
➢ Playground Refurbishment Program
Rebudgeting - $305,598 for a total of $605,598
➢ Newport Coast Pickleball Courts (8)
➢ Dog Park Refurbishment
➢ 38th Street Park - Fencing
SUBTOTAL PARKS (New $)
$3,6617232 FFP
$300,000 GF/BET
$15000,000 FFP
$2207000 GF
$50,000 GF
$5,231,232
GF - General Fund FFP - Major Facilities Finance Plan BET - Building Excise Tax
PARKS, HARBORS & BEACHES
[New proposed funding]
➢ Beach and Bay Sand Management
➢ Harbor Bulkheads/Seawalls/Structure Repairs
Rebudgeting - $374,463 for a total of $774,463
➢ Harbor Maintenance/Minor Repairs
Rebudgeting - $100, 000 for a total of $150, 000
➢ Harbor Piers Rehabilitation
Rebudgeting - $621,170 for a total of $921,170
➢ Harborwide Dredging/Planning
Rebudgeting - $4,557,972 for a total of $7,107,972
$3005000 TL
$4007000 TL
$50,000 TL
$300,000 TL
$2,5505000 TL
HARBOR & BEACHES CONTINUED...
TL - Tidelands
PARKS, HARBORS & BEACHES
[New proposed funding]
➢ Newport Pier Bldg Platform and Piles/Restaurant
Rebudgeting - $1,618,814 for a total of $2,143,814
➢ Ocean Piers Inspection and Maintenance
Rebudgeting - $360,152 for a total of $500, 000
➢ Balboa Island Seawall Assessment
SUBTOTAL HARBORS & BEACHES (New $)
$5257000 TL
$1397848 TL
$75,000 TL
$433399848
TOTAL PARKS, HARBORS & BEACHES (News)
TL - Tidelands
$9,558,964
WATER [New proposed funding]
➢ 16TH St Pump Station / Backup Generator
Rebudgeting - $2,022,552 for a total of $2,800, 000
➢ Advanced Metering Infrastructure
➢ Grade Adjustments — Water Valves
Rebudgeting - $49,840 for a total of $99,840
➢ Water System Rehabilitation
Rebudgeting - $100,335 for a total of $468,335
TOTAL WATER (News)
CF - Contributions & Grants WF - Water Fund
$7777448 WF
$3,0997000 WF/CF
$50,000 WF
$3681000 WF
$4,294,448
WASTEWATER [New proposed funding]
➢ Grade Adjustments — Sewer Manhole Covers
Rebudgeting - $254,215 for a total of $354,215
➢ Sewer Main Lining and Repairs
Rebudgeting - $3,201 for a total of $253,201
TOTAL WASTEWATER (News)
SF - Sewer Fund
$100,000
$250,000
$350,000
SF
SF
MISCELLANEOUS [New proposed funding]
➢ Peninsula Encroachment Removal Program
➢ Oil Well 5 Rehabilitation
➢ Oil Well 12 Rehabilitation
➢ Oil Well 15 Rehabilitation
TOTAL MISCELLANEOUS (News)
OEF - Oceanfront Encroachment Fund TL - Tidelands
$550)000
$250,000
$250,000
$2505000
$1,300,000
OEF
TL
TL
TL
Proposed Fiscal Year 2021/22 Tentative
Summary of New Funding by Type
Funding Type
Proposed New Funding
General Fund
$5,000,000
Roadway Funding (SBI, GT, M2)
$6,284,550
Water/Wastewater
$4,095,448
FFP/FMMP
$6,361,232
Tidelands
$5,089,848
Grants & Contributions
$1,999,000
Other
(Upper Bay, Oceanfront Encroach., Building Excise Tax, BVAC)
$1,810,000
TOTAL
$30,640,078
Recommended Projects from Unfunded Needs List
Identified Projects for Consideration in
FY 2021-22 CI P (Not in any priority order)
Cost
Estimate
Comments
Suggested Deferred Projects to Fund
Streetlight Rehabilitation Program - $416,000
Part of $1,050,000 funding rehabilitation of 2 old circuits + EI Capitan Trail
Balboa Blvd Median Improvement - $1,850,000
Currently Under Design. Proposed $1mil NE, $850K BVAC
Ocean Blvd. Pedestrian Improvement - $250,000
Currently Under Design. Construct Sidewalk Imp near Fernleaf
Landscape Enhancements - $350,000
Addresses community request for Breakers Dr, Lido Park, Lido Isle median
Oceanfront Boardwalk/Parking Lot Imp. - $350,000
Begins Review, Community work &Concept Development of Oceanfront
Total FY 2020/21 Deferred Projects Funding
$3,216,000
Recommend Reprogramming of some Deferred Projects
General Plan Update - Additional Funding
$650,000
Also will be requesting $650K more in FY 22-23 & 23-24
Permanent Supportive Housing Project
$1,000,000
Estimate $3 mil total with $1 mil coming from Development Agmt.
Other?
Total >> >> $4,866,000 ($4,016,000 -General Fund, $850,000 - BVAC)
5 -Year Look Ahead - Significant Projects
Construction Start Dates
➢ FY 22-23
Library Lecture Hall
City Corp Yard Fueling Facilities
Junior Lifeguard Building
Newport Coast Drive Pavement Rehab
Bay/Channel Water Main Crossings Replacements
➢ FY 23-24
z
Balboa Island Drainage Project (Pump Station)
West Coast Hwy Intersection Improvements/Ped. Bridge
Eastbluff Drive Pavement Rehab
Balboa Blvd. Pavement Rehab (Coast Hwy to 23rd Street)
Coast Hwy Water Main Relining
➢ FY 24-25
Balboa Island Drainage Project (West Side Piping)
Balboa Library/Fire Station No. 1
CDM Flower Streets Reconstruction
CDM Ocean Blvd Pavement Reconstruction
Bonita Creek Field Turf Replacement
5 -Year Look Ahead - Significant Projects
➢ FY 25-26
Balboa Island Drainage Project (East Side Piping)
Miramar Drive Concrete Pavement Reconstruction
E. Ocean Blvd and Street Ends Concrete Pavement Reconstruction
Seaview Ave Pavement Rehab (Carnation to Narcissus)
➢ FY 26-27
Mariners Fire Station 6 - Living Quarters Rebuild
San Joaquin Hills Drive Pavement Rehab (Spyglass Hill to Newport Coast)
East Coast Hwy Pavement Rehab (Jamboree to MacArthur)