Loading...
HomeMy WebLinkAboutX2019-3127 - Soils (2)X 2otci �I Z"I ENGINEERS + GEOLOGISTS + ENVIRONMENTAL SCIENTISTS March 4, 2022 J.N. 19-265 NICHOLSON CONSTRUCTION 1 Corporate Plaza, Suite 110 Newport Beach, California 92660 Attention: Ms. Nanci Glass Subject: Final Soils Report, Geotechnical Observations and Testing, Foundation Excavations, Slab Subgrades and Utility Trench Backfill, 304 Goldenrod Avenue, Corona Del Mar Area, City of Newport Beach, California References: 1) Geotechnical Investigation, Proposed Two -Unit Condominium Building, 304 Goldenrod Avenue, Corona Del Mar Area, City of Newport Beach, California; report by Petra Geosciences, Inc., dated July 31, 2019 (J.N. 19-265). 2) Geotechnical Report of Rough Grading, Proposed Two -Unit Condominium Building, 304 Goldenrod Avenue, Corona Del Mar Area, City of Newport Beach, California; report by Petra Geosciences, hie., dated August 27, 2020 (J.N. 19-265). Dear Ms. Glass: Petra Geosciences, Inc. (Petra) is submitting herewith a summary of our observations of foundation excavations for the site structures, and our observations and test results pertaining to slab subgrade soils, and placement and compaction of backfill within utility trenches located in landscape areas, and under slabs within the subject site. Representatives from our firm performed on -call field density testing and field observations at the request of the project superintendent during post -grade operations. SUMMARY Foundation Excavation Observations Excavations of footing trenches for the residence and site structures were observed and found to be excavated into engineered fill per the foundation plans and the recommendations presented in our reference reports. Utilitv Trench Backfill 1. Backfill of interior and exterior trenches consisted of onsite soils placed above select sand bedding. The sand bedding placed above utility lines was jetted and varied from approximately 6 inches to 2 feet in depth. Backfill materials were moisture conditioned, as necessary, to achieve optimum or above optimum moisture conditions prior to and/or during placement, and then compacted in 6- to 8-inch lifts with a pneumatic tamper to a minimum relative compaction of 90 percent (based on ASTM D 1557). Offices Strategically Positioned Throughout Southern California ORANGE COUNTY OFFICE 3186 Airway Avenue, Suite K, Costa Mesa, California 92626 T: 714.549,8921 F: 714.549A438 Farmers information visit us online at w .oetra-inacom NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar March 4, 2022 J.N.19-265 Page 2 2. Exterior trench backfill under the observation and testing of Petra consisted of sewer, water, area drain, and a common (joint) trench containing electric, gas, telephone and data lines. The approximate maximum depth of soil backfill placed over bedding sand for the various trenches was approximately 3 feet in the sewer trench excavation. 3. Utility trench backfills, where probed and/or tested, are considered to have been placed in accordance with the recommendations presented in the referenced reports. Slab Subgrades Due to the amount of time that had elapsed since the completion of rough grading, and due to disturbance during construction activities, the surficial subgrade soils of the slabs were moisture conditioned to achieve optimum or above optimum moisture content and then compacted in -place to a minimum relative compaction of 90 percent of the applicable laboratory maximum dry density in general accordance with ASTM Test Method D 1557. These subgrade soils were tested prior to concrete placement and are considered acceptable from a geotechnical point of view. The subgrade soils were also presaturated as per our recommendations. Field and Laboratory Testing 1. Field density tests results for the trench backfills and slab subgrades are summarized in Table I, and approximate test locations are shown on the accompanying Density Test Location Map (Figure 1). Field density tests were taken with a Nuclear Gauge (ASTM D 6938). 2. Field density tests were taken at vertical intervals of 1 to 2 feet. 3. The laboratory maximum dry density and optimum moisture values for the most prominent onsite soils (Soil Type A) were determined according to Test Method ASTM D 1557 and are listed in Table II. Footing trench excavations for the residence and site structures were observed to have been founded into engineered fill. In addition, where observed and tested, utility trench backfill and slab subgrade soils as discussed in this report were found to be in general compliance with our recommendations and the grading codes of the City of Newport Beach, California. The completed work within this firm's purview to the extent observed, as discussed herein, has been reviewed and is considered adequate from a geotechnical perspective. REPORT LIMITATIONS Representatives of Petra were present on -site on an on -call basis during post -grading operations for the purpose of providing the owner's representative with professional opinions and recommendations. These PETRA SOLID AS A ROCK GEOSCIENCES"° NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar March 4, 2022 J.N. 19-265 Page 3 opinions and recommendations were developed based on field observation and selective testing of the contractor's work. Our scope of services during this project did not include supervision or direction of the contractor, his personnel or his subcontractors. As documented in this report, our observations and testing did not reveal any obvious deviations from the recommendations provided in the referenced geotechnical reports; however, Petra does not in any way guarantee the contractor's work, nor do our services relieve the contractor (or any subcontractors) of their liability should any defects subsequently be discovered in their work product. Based on our findings, this report was prepared in conformance with generally accepted professional engineering practices, and no warranty is implied nor made. This report is subject to review by the controlling authorities for the project. Please call if you have any questions pertaining to this report. Respectfully submitted, INC. Don Obert NO, MDarrel Roberts Associate Engineer z Principal Geologist RGE 2872 % ; o CEG 1972 SM/DO/DR/ly Attachments: Table I — Field Density Test Summary Table II — Laboratory Optimum Moisture and Maximum Dry Density Tes Figure 1 — Density Test Location Map W120I42019�20I91200l1 265UL,. s19-2653W Fw lSoils R,.O.d.c PETRA SOLO ASA ROCK NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar TABLE FIELD DENSITY TEST SUMMARY March 4, 2022 J.N.19-265 Date of Test Test No. Location Depth* ft. Moist:. % Unit Wt: bs./co.ft. %° Ref. Comp. Soil T e 11/02/2020 1-SG Building Pad 0.0 11.7 111.8 93 A 11/22/2020 1-IT Building Pad 0.5 11.2 111.3 93 A 10/18/2021 1-S Exterior 1.0 10.8 110.6 92 A 10/18/2021 1-W Exterior 0.5 11.4 110.8 92 A 10/18/2021 1-1 Exterior 0.5 10.2 111.7 93 A 10/18/2021 I -AD Side Yard 0.0 11.9 109.7 91 A 10/18/2021 2-SG Drive Approach 0.0 11.6 110.5 92 A 10/18/2021 3-SG Entry 0.0 11.8 110.9 92 A SG - SUBGRADE IT - INTERIOR TRENCH S - SEWER W - WATER J - JOINT (ELECTRIC, TELEPHONE, TV, GAS) AD - AREA DRAIN * . DEPTH BELOW FINISH GRADE It PETNCRA SOLID ASA ROCK NICHOLSON CONSTRUCTION March 4, 2022 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 TABLE I1 LABORATORY OPTIMUM MOISTURE AND MAXIMUM DRY DENSITY TEST DATA Soil Type Optimum Moisture Maximum Dry Density c A —Brown Silty Sand (SM) 9.0 120.0 PETRA SOLID ASA ROCK Z O T- Gi V L U rc Q 7 Z w u !A Z WyN o O o Z. o N mp0 O Wes` H Vcd -° L z "00 N m {, Wmq N m a— - — - - qa --- -- — — — i — j — — LV IN. .inro arRscre 4 w F M N Z F� W w Z m to N d� d s 0� N 0 Y� LPo a N N GI ZPo N 9 N N " w .L O I�i •Mo m - (- A� O C my F 6g N .co .0 _ ! C O _ b N N G Oi O` W O N Z7J N u 3a Iz 0- 3 Co- az 0-O CD ¢ O � gfl NaAV UONN21G IOJ t ENGINEERS + GEOLOGISTS + ENVIRONMENTAL SCIENTISTS August 27, 2020 J.N.19-265 NICHOLSON CONSTRUCTION 1 Corporate Plaza, Suite 110 Newport Beach, California 92660 Attention: Ms. Nanci Glass Subject: Geotechnical Report of Rough Grading, Proposed Two -Unit Condominium Building, 304 Goldenrod Avenue, Corona Del Mar Area, City of Newport Beach, California Reference: Geotechnical Investigation, Proposed Two -Unit Condominium Building, 304 Goldenrod Avenue, Corona Del Mar Area, City of Newport Beach, California; report by Petra Geosciences, Inc., dated July 31, 2019 (J.N. 19-265) Dear Ms. Glass: Petra Geosciences, Inc. (Petra) is submitting herewith a summary of the observation and testing services provided by this firm during rough grading operations within the subject site. Conclusions relative to the suitability of the grading for the planned structures, and foundation design recommendations for the proposed residential building and other site improvements, are included herein. The purpose of the grading was to develop an engineered fill pad for the construction of a two unit condominium building and associated hardscape features. Grading began on August 6, 2020 and was completed on August 11, 2020. SUMMARY OF OBSERVATIONS AND TESTING Site Clearine Structural materials associated with the previous residential structures were removed from the site. This included previous structural features, such as concrete walkways, patios and block walls. Clearing operations also included the removal of landscape vegetation. Trees and large shrubs, when removed, were grubbed out to include their stumps and major root systems. Ground Preparation Existing fill materials and terrace deposits to depths of approximately 4 feet were found to have low in - place densities and were considered subject to compression under the anticipated footing loads. Therefore, in order to provide support of the proposed residential structure and exterior hardscape features, existing ground surfaces in shallow cut areas and in areas to receive fill were overexcavated to a depth of at least 4 Offices Strategically Positioned Throughout Southern California ORANGE COUNTY OFFICE 3186 Airway Avenue, Suite K, Costa Mesa, California 92626 T. 714.549.8921 F: 714.668-3770 For more information visit us online at mimpetra-inc.com NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 2 feet and the excavated materials then replaced as engineered fill. Prior to replacing the overexcavated soils as engineered fill, the exposed bottom surfaces were first scarified to a depth of 6 inches, moisture conditioned to achieve a uniform moisture content that was greater than optimum, and then recompacted in place to a minimum relative compaction of 90 percent of the applicable laboratory maximum dry density in accordance with ASTM Test Method D 1557. Horizontal limits of overexcavation and recompaction extended to approximately property line to property line; however, consideration was given to the protection of adjacent property line structures. Fill Placement and Testing 1. The fill materials placed within the building area consisted of onsite soils. 2. The soils were placed in approximately 4- to 6-inch-thick lifts, moisture conditioned as necessary to achieve at or above optimum moisture contents, and compacted to a minimum relative compaction of 90 percent of the applicable laboratory maximum dry density in accordance with ASTM Test Method D 1557. The maximum depth of fill within the building pad is approximately 4 feet. 3. Field density tests results are summarized in Table A, and approximate test locations are shown on the accompanying Figure 1. Field density tests were taken with a Nuclear Gauge in accordance with ASTM D 6938. 4. Field density tests were taken at vertical intervals of 1 to 2 feet. 5. The maximum dry density and optimum moisture values for the onsite soils were determined according to Test Method ASTM D 1557 and are listed in Table B. 6. Visual and tactile classification of earth materials in the field was the basis for determining -if the laboratory maximum density value presented in Table B was applicable for each density test. 7. Fill placement within the subject lot was performed in general compliance with the recommendations of our referenced report and the Grading Code of the City of Newport Beach. Laboratory Testing Several laboratory tests were previously performed on onsite soil materials obtained near finish pad grade in order to evaluate their engineering characteristics and chemical activity (Reference). These test results are provided in Table B at the end of this report. CONCLUSIONS AND RECOMMENDATIONS Regulatory Compliance Removals, overexcavation, processing of exposed surfaces, and placement of engineered fill under the purview of this report have been completed under the part-time observation of, and with selective testing PETRASOLID AS A ROCK GEOSCIENCES' NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 3 by, Petra and are found to be in general compliance with our recommendations and of the Grading Code of the City of Newport Beach. The completed work has been reviewed and is considered adequate for the construction now planned. Post -Grading Considerations Site Drainage Positive drainage devices such as sloped concrete flatwork, graded swales and area drains should be provided around the new construction to collect and direct all water to a suitable discharge area. Neither rain nor excess irrigation water should be allowed to collect or pond against building foundations. The owner is advised that the drainage system should be properly maintained throughout the life of the proposed development. The purpose of this drainage system will be to reduce water infiltration into the subgrade soils and to direct surface water away from building foundations, and walls. The following recommendations should be implemented during construction. 1. Area drains should be extended into all planters and landscape areas that are located within 10 feet of building foundations and masonry block walls to mitigate excessive infiltration of water into the foundation soils. Per the 2016 CBC, the ground surfaces within all landscape areas located within 10 feet of building foundations should be sloped at a minimum gradient of 5 percent away from the walls and foundations and to the area drains. Landscape areas located more than 10 feet from building foundations may be sloped at a minimum gradient of 2 percent. 2. Per the 2016 CBC, concrete flatwork surfaces located within 10 feet of building foundations should be inclined at a minimum gradient of 2 percent away from building foundations. Concrete flatwork surfaces located more than 10 feet from building foundations may be sloped at a minimum gradient of 1 percent. A watering program should be implemented for the landscape areas that maintain a uniform, near optimum moisture condition in the soils. Overwatering and subsequent saturation of the soils will cause excessive soil expansion and heave and, therefore, should be avoided. On the other hand, allowing the soils to dry out will cause excessive soil shrinkage. As an alternative to a conventional irrigation system, drip irrigation is strongly recommended for all planter areas. The owner is advised that all drainage devices should be properly maintained throughout the lifetime of the development. Bottomless Trench Drains When gravel filled bottomless infiltration systems are constructed near foundations, a potential exists for oversaturation of the foundation soils which conflicts with the intended purpose of onsite drainage facilities. In addition, it has been our experience that a leading cause of distress to buildings and foundations is due to poor management of water next to building foundations. Petra recommends a setback of at least 15 feet between any infiltration system and building foundations. If this setback distance cannot be maintained, 10PETRA SOLID ASAROCK NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 4 then a modified foundation system may be required to alleviate any distress that could be caused by infiltration of water near the footing. A modified foundation system could consist of constructing deepened footings within 15 feet of the infiltration system and installing extra reinforcement. Design of a modified foundation system is referred to the project structural engineer. Utility Trench BackIIII All utility trench backfill should be compacted to a minimum relative compaction of 90 percent of the applicable laboratory maximum dry density in accordance with ASTM Test Method D-1557. Onsite soils cannot be densified adequately by flooding and jetting techniques; therefore, trench backfill materials should be placed in lifts no greater than approximately 6 inches in thickness, watered or air dried as necessary to achieve a uniform moisture content that is equal to or slightly above optimum moisture, and then mechanically compacted in -place to a minimum relative compaction of 90 percent. A representative of the project geotechnical consultant should probe and test the backfills to document that adequate compaction has been achieved. For shallow trenches where pipe may be damaged by mechanical compaction equipment, such as under the building floor slab, imported clean sand exhibiting a sand equivalent value (SE) of 30 or greater may be utilized. The sand backfill materials should be watered to achieve near optimum moisture conditions and then tamped in place. No specific relative compaction will be required; however, observation, probing, and, if deemed necessary, testing should be performed by a representative of the project geotechnical consultant to document that the sand backfill is adequately compacted and will not be subject to excessive settlement. Where utility trenches enter the footprint of the building, they should be backfilled through their entire depths with on -site fill materials, sand -cement slurry or concrete rather than with any sand or gravel shading. This "plug" of less- or non -permeable materials will mitigate the potential for water to migrate through the backfilled trenches from outside of the building to the areas beneath the foundations and floor slabs. If clean, imported sand is to be used for backfill of exterior utility trenches, it is recommended that the upper 12 inches of trench backfill materials consist of property compacted on -site soil materials. This is to reduce infiltration of irrigation and rainwater into granular trench backfill materials. Where an interior or exterior utility trench is proposed parallel to a building footing, the bottom of the trench should not be located below a 1:1 plane projected downward from the outside bottom edge of the PETRASOLID ASA ROCK GEOSCIENCE15- NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 5 adjacent footing. Where this condition exists, the adjacent footing should be deepened such that the bottom of the utility trench is located above the 1:1 projection. Foundation Design Recommendations Seismic Design Parameters Earthquake loads on earthen structures and buildings are a function of ground acceleration which may be determined from the site -specific ground motion analysis. Alternatively, a design response spectrum can be developed for the site based on the code guidelines. To provide the design team with the parameters necessary to construct the design acceleration response spectrum for this project, we used the computer application that is available at the Structural Engineers Association of California (SEAOC) and California's Office of Statewide Health Planning and Development (OSHPD) Seismic Design Maps web site - https://seismicmaps.org/ which was used to calculate the ground motion parameters. To run the above computer applications, site latitude, longitude, risk category and knowledge of "Site Class" are required. The site class definition depends on the average shear wave velocity, Vs3o, within the upper 30 meters (approximately 100 feet) of site soils. A shear wave velocity of 600 to 1,200 feet per second for the upper 30 meters was used for the site based on engineering experience and judgment. The following table, Table 1, provides parameters required to construct the site -specific acceleration response spectrum based 2016 CBC guidelines. PETNRA SOLD ASA ROCK NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar TABLE I Seismic Design Parameters August 27, 2020 J.N. 19-265 Page 6 Ground Motion Parameters Specific Reference Parameter Unit Value Site Latitude (North) 33.5976 ° Site Longitude (West) - -117.8757 ° Site Class Definition''' Section 1613.3.2 D - Assumed Risk Category t" Table 1604.5 I/11/111 - S,- Mapped Spectral Response Acceleration 'r.21 Figurel613.3.1(I) 1.702 g Si - Mapped Spectral Response Acceleration Figure 1613.3.1(2) 0.623 g Fs- Site CoefficienttI.tl Table 1613.3.3(1) 1.0 - F, - Site Coefficient i1.'-1 Table 1613.3.3(2) 1.5 - S,ms- Adjusted Maximum Considered Earthquake Spectral Response Acceleration (1.21 . Equation I6-37 1.702 g Svu - Adjusted Maximum Considered Earthquake Equation I (i-38 0.935 g Spectral Response Acceleration Sos - Design Spectral Response Acceleration t"t Equation I6-39 1.134 g Sm - Design Spectral Response Acceleration Equation 16-40 0.623 e T„=0 _ Sin/ Sus" p Section 11.3 0A 10 s T,= Sm" Sus f' Section 11.3 0.549 s Tr - Long Period Transition Period °p Figure 22-12 8 s Fran - Site Coefficient(" Figure 22-7 1.000 - PGAsi - Peak Ground Acceleration at MCE O Equation 1 1.8-1 0.701 g Design PGA = ('.3 PGAm) - Slope Stability Similar to Equations 16-39 & 16-40 0.467 g Design PGA - (0.4 Sos) -- Short Retaining Walls Equation 11.4-5 0.454 e Can - Short Period Risk Coeftcient Figure 22-17 0.898 - CzI - Long Period Risk Coefficient f' Figure 22-18 0.916 - Seismic Desien Category n.47 Section 1613.3.5 D - References: 1n California Building Code (CBC), 2016, California Code of Regulations, Title 24, Part 2, Volume I and II. ('-) SEAOC & OSHPD Seismic Design Maps Web Application— haos'//seismimnans orJ (4) American Society of Civil Engineers (ASCE/SEL, 2010, Minimum Design Load for Buildings and Other Structures, Standards 7-10. Related References: Federal Emergency Management Agency (FEMA), 2009, NEHERP (National Earthquake Hazards Reduction Program) Recommended Seismic Provision for New Building and Other Structures FEMA P-750 . Notes: PGA Calculated at the NICE return period or2475 years (2 percent chance ofexceedanee in 50 )ears). PGA Calculated at the Design Level of?. of MCE; appro.xintately equivalent to a return period 0f475 years (10 percent chance ofexeeedauce in s0 vears). PGA Calculated fur shw't, stubby retaining walls with an infinitesimal (zero) fundamental period. The designation provided herein may be superseded by the structural engineer in accordance with Section 1613.3.5.1. if applicable. V PET OM SOLID ASA ROCK NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 7 FOUNDATION DESIGN GUIDELINES Allowable Bearing Capacity, Estimated Settlement and Lateral Resistance Allowable Soil Bearine Capacities Pad Footings An allowable soil bearing capacity of 1,500 pounds per square foot may be utilized for design of isolated 24-inch-square footings founded at a minimum depth of 12 inches below the lowest adjacent final grade for pad footings that are not a part of the slab system and are used for support of such features as roof overhang, second -story decks, patio covers, etc. This value may be increased by 20 percent for each additional foot of depth and by 10 percent for each additional foot of width, to a maximum value of 2,500 pounds per square foot. The recommended allowable bearing value includes both dead and live loads, and may be increased by one-third for short duration wind and seismic forces. Continuous Footings An allowable soil bearing capacity of 1,500 pounds per square foot may be utilized for design of continuous footings founded at a minimum depth of 12 inches below the lowest adjacent final grade. This value may be increased by 20 percent for each additional foot of depth and by 10 percent for each additional foot of width, to a maximum value of 2,500 pounds per square foot. The recommended allowable bearing value includes both dead and live loads, and may be increased by one-third for short duration wind and seismic forces. Estimated Footing Settlement Based on the allowable bearing values provided above, total static settlement of the footings under the anticipated loads is expected to be on the order of Y2 inch. Differential settlement is estimated to be on the order of 1/4 inch over a horizontal span of 40 feet. The majority of settlement is likely to take place as footing loads are applied or shortly thereafter. Lateral Resistance A passive earth pressure of 240 pounds per square foot per foot of depth, to a maximum value of 2,400 pounds per square foot, may be used to determine lateral bearing resistance for footings. In addition, a coefficient of friction of 0.35 times the dead load forces may be used between concrete and the supporting soils to determine lateral sliding resistance. The above values may be increased by one-third when designing for transient wind or seismic forces. It should be noted that the above values are based on the condition where footings are cast in direct contact with compacted fill or competent native soils. In cases where the PETNeRA SOLID ASA RUCK NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 8 footing sides are formed, all backfill placed against the footings upon removal of forms should be compacted to at least 90 percent of the applicable maximum dry density. Guidelines for Footings and Slabs on -Grade Design and Construction The results of our laboratory tests performed on representative samples of near -surface soils within the site during our -investigation indicate that these material predominantly exhibit expansion indices that are less than 20. As indicated in Section 1803.5.3 of 2016 California Building Code (2016 CBQ, these soils are considered non -expansive and, as such, the design of slabs on -grade is considered to be exempt from the procedures outlined in Sections 1808.6.2 of the 2016 CBC and may be performed using any method deemed rational and appropriate by the project structural engineer. However, the following minimum recommendations are presented herein for conditions where the project design team may require geotechnical engineering guidelines for design and construction of footings and slabs on -grade the project site. The design and construction guidelines that follow are based on the above soil conditions and may be considered for reducing the effects of variability in fabric, composition and, therefore, the detrimental behavior of the site soils such as excessive short- and long-term total and differential heave or settlement. These guidelines have been developed on the basis of the previous experience ofthis firm on projects with similar soil conditions. Although construction performed in accordance with these guidelines has been found to reduce post -construction movement and/or distress, they generally do not positively eliminate all potential effects of variability in soils characteristics and future heave or settlement. It should also be noted that the suggestions for dimension and reinforcement provided herein are performance -based and intended only as preliminary guidelines to achieve adequate performance under the anticipated soil conditions. However, they should not be construed as replacement for structural engineering analyses, experience and judgment. The project structural engineer, architect and/or civil engineer should make appropriate adjustments to slab and footing dimensions, and reinforcement type, size and spacing to account for internal concrete forces (e.g., thermal, shrinkage and expansion), as well as external forces (e.g., applied loads) as deemed necessary. Consideration should also be given to minimum design criteria as dictated by local building code requirements. PETRA SOLID AS AROCK NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 9 Conventional Slabs on -Grade System Given the expansion index of less than 20, as generally exhibited by onsite soils, we recommend that footings and floor slabs be designed and constructed in accordance with the following minimum criteria. Footines 1. Exterior continuous footings supporting three- and four-story structures should be founded at a minimum depth of 18 inches below the lowest adjacent final grade, respectively. Interior continuous footings may be founded at a minimum depth of 12 inches below the top of the adjacent finish floor slabs. 2. In accordance with Table 1809.7 of 2016 CBC for light -frame construction, all continuous footings should have minimum widths of 15 inches for three- and four-story construction. We recommend all continuous footings should be reinforced with a minimum of two No. 4 bars, one top and one bottom. 3. A minimum 12-inch-wide grade beam founded at the same depth as adjacent footings should be provided across garage entrances or similar openings (such as large doors or bay windows). The grade beam should be reinforced with a similar manner as provided above. 4. Interior isolated pad footings, if required, should be a minimum of 24 inches square and founded at a minimum depth of 15 inches below the bottoms of the adjacent floor slabs for three- and four-story buildings. Pad footings should be reinforced with No. 4 bars spaced a maximum of 18 inches on centers, both ways, placed near the bottoms of the footings. 5. Exterior isolated pad footings intended for support of roof overhangs such as second -story decks, patio covers and similar construction should be a minimum of 24 inches square and founded at a minimum depth of 24 inches below the lowest adjacent final grade. The pad footings should be reinforced with No. 4 bars spaced a maximum of 18 inches on centers, both ways, placed near the bottoms of the footings. Exterior isolated pad footings may need to be connected to adjacent pad and/or continuous footings via tie beams at the discretion of the project structural engineer. 6. The minimum footing dimensions and reinforcement recommended herein may be modified (increased or decreased subject to the constraints of Chapter 18 of the 2016 CBC) by the structural engineer responsible for foundation design based on his/her calculations, engineering experience andjudgment. Building Floor Slabs 1. Concrete floor slabs should be a minimum 4 inches thick and reinforced with No. 3 bars spaced a maximum of 24 inches on centers, both ways. All slab reinforcement should be supported on concrete chairs or brick to ensure the desired placement near mid -depth. Slab dimension, reinforcement type, size and spacing need to account for internal concrete forces (e.g., thermal, shrinkage and expansion) as well as external forces (e.g., applied loads), as deemed necessary. 2. Living area concrete floor slabs and areas to receive moisture sensitive floor covering should be underlain with a moisture vapor retarder consisting of a minimum 10-mil-thick polyethylene or polyolefin membrane that meets the minimum requirements of ASTM E96 and ASTM E 1745 for vapor PETRASOLID ASA BOCK GEOSCIENCES- NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 10 retarders (such as Husky Yellow Guard®, Stego® Wrap, or equivalent). All laps within the membrane should be sealed, and at least 2 inches of clean sand should be placed over the membrane to promote uniform curing of the concrete. To reduce the potential for punctures, the membrane should be placed on a pad surface that has been graded smooth without any sharp protrusions. If a smooth surface cannot be achieved by grading, consideration should be given to lowering the pad finished grade an additional inch and then placing a 1-inch-thick leveling course of sand across the pad surface prior to the placement of the membrane. To comply with Section 1907.1.1 of the 2016 CBC, the living area concrete floor slab should also be underlain with capillary break consisting of a minimum of 4 inches of gravel or crushed stone containing not more than 10 percent of material that passes through a No. 4 sieve. The capillary break should be placed below the 10-mil moisture vapor retarder. At the present time, some slab designers, geotechnical professionals and concrete experts view the sand layer below the slab (blotting sand) as a place for entrapment ofexcess moisture that could adversely impact moisture -sensitive floor coverings. As a preventive measure, the potential for moisture intrusion into the concrete slab could be reduced if the concrete is placed directly on the vapor retarder. However, if this sand layer is omitted, appropriate curing methods must be implemented to ensure that the concrete slab cures uniformly. A qualified materials engineer with experience in slab design and construction should provide recommendations for alternative methods of curing and supervise the construction process to ensure uniform slab curing. Additional steps would also need to be taken to preventpuncturing of the vapor retarder during concrete placement. 3. Garage floor slabs should be a minimum 4 inches thick and reinforced in a similar manner as living area floor slabs. Garage slabs should also be poured separately from adjacent wall footings with a positive separation maintained using 3/4-inch-minimum felt expansion joint material. To control the propagation of shrinkage cracks, garage floor slabs should be quartered with weakened plane joints. Consideration should be given to placement of a moisture vapor retarder below the garage slab, similar to that provided in Item 2 above, should the garage slab be overlain with moisture sensitive floor covering. 4. Presaturation of the subgrade below floor slabs will not be required; however, prior to placing concrete, the subgrade below all dwelling and garage floor slab areas should be thoroughly moistened to achieve a moisture content that is at least equal to or slightly greater than optimum moisture content. This moisture content should penetrate to a minimum depth of 12 inches below the bottoms of the slabs. 5. The minimum dimensions and reinforcement recommended herein for building floor slabs may be modified (increased or decreased subject to the constraints of Chapter 18 of the 2016 CBC) by the structural engineer responsible for foundation design based on his/her calculations, engineering experience and judgment. Foundation Observations All foundation excavations should be observed by a representative of the project geotechnical consultant to verify that they have been excavated into competent fill materials. These observations should be performed prior to the placement of forms or reinforcement. The excavations should be trimmed neat, level and square. All loose, sloughed or moisture -softened materials and/or any construction debris should be removed prior PETRA$0119 ASA ROCK GEOSCIENCES- NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 11 to the placement of concrete. Excavated soils derived from footing and utility trenches should not be placed in slab -on -grade areas unless they are compacted to at least 90 percent of maximum dry density. General Corrosivity Screenin¢ As a screening level study, limited chemical and electrical tests were performed on samples considered representative of the onsite soils to identify potential corrosive characteristics of these soils (Reference No. 1). The common indicators associated with soil corrosivity include water-soluble sulfate and chloride levels, pH (a measure of acidity), and minimum electrical resistivity. It should be noted that Petra does not practice corrosion engineering, therefore, the test results, opinion and engineering judgment provided herein should be considered as general guidelines only. Additional analyses would be warranted, especially, for cases where buried metallic building materials (such as copper and cast or ductile iron pipes) in contact with site soils are planned for the project. In many cases, the project geotechnical engineer may not be informed of these choices. Therefore, for conditions where such elements are considered, we recommend that other, relevant project design professionals (e.g., the architect, landscape architect, civil and/or structural engineer) also consider recommending a qualified corrosion engineer to conduct additional sampling and testing of near -surface soils during the final stages of site grading to provide a complete assessment of soil corrosivity. Recommendations to mitigate the detrimental effects of corrosive soils on buried metallic and other building materials that may be exposed to corrosive soils should be provided by the corrosion engineer as deemed appropriate. In general, a soil's water-soluble sulfate levels and pH relate to the potential for concrete degradation; water-soluble chlorides in soils impact ferrous metals embedded or encased in concrete, e.g., reinforcing steel; and electrical resistivity is a measure of a soil's corrosion potential to a variety of buried metals used in the building industry, such as copper tubing and cast or ductile iron pipes. Table 2, below, presents a single value of individual test results with an interpretation of current code indicators and guidelines that are commonly used in this industry. The table includes the code -related classifications of the soils as they relate to the various tests, as well as a general recommendation for possible mitigation measures in view of the potential adverse impact on various components of the proposed structures in direct contact with site soils. The guidelines provided herein should be evaluated and confirmed, or modified, in their entirety by the project structural engineer, corrosion engineer and/or the contractor responsible for concrete placement for structural concrete used in exterior and interior footings, interior slabs on -ground, garage slabs, wall foundations and concrete exposed to weather such as driveways, patios, porches, walkways, ramps, steps, curbs, etc. PETRASOaO AS A ROCK GEOSCIENCES'"` NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar TABLE 2 Soil Corrosivity Screening Results August 27, 2020 J.N. 19-265 Page 12 Test Test Results Classification General Recommendations Soluble Sulfates 0.0036 % so' Min. fc=2,500 psi Cal 417 pH Cal 643 6.5 Slightly Acid Type I-P (MS) Modified or Type II Modified cement Soluble Chloride 54 ppm C lz Residence: No max water/cement ratio, f c = 2,500 psi Cal 422 C24 Pools/Decking: water/cement ratio 0.40, t c = 5,000 si Resistivity I 11,000 Mildly Protective wrapping/coating of buried pipes; corrosion Cal ohm -cm Conosive3 resistant materials; or cathodic protection Notes: 1. ACI 318-14, Section 19.3 2. ACI 318-14, Section 19.3 3. Pierre R. Roberge, "Handbook of Corrosion Engineering" 4. Exposure classification C2 applies specifically to swimming pools and appurtenant concrete elements Retaining Wall Design and Construction Considerations Provided herein are geotechnical design and construction recommendations for exterior retaining walls, should they be proposed for construction onsite. Allowable Bearing Values An allowable soil bearing capacity of 1,500 pounds per square foot, including dead and live loads, may be utilized for design of 24-inch square pad footing and 12-inch-wide continuous footings founded at a minimum depth of 12 inches below the lowest adjacent final grade. Recommended allowable bearing values include both dead and live loads, and may be increased by one-third for short duration wind and seismic forces. Lateral Resistance A passive earth pressure of 240 pounds per square foot per foot of depth may be used to determine lateral bearing resistance for footings. In addition, a coefficient of friction of 0.35 times the dead load forces may be used between concrete and the supporting soils to determine lateral sliding resistance. However, when calculating passive resistance, the resistance of the upper 6 inches of the soil cover in front of the wall should be ignored in areas where the front of the wall will not be covered with concrete. The above values may be increased by one-third when designing for transient wind or seismic forces. It should be noted that the above values are based on the condition where footings are cast in direct contact with compacted fill or competent native soils. In cases where the footing sides are formed, all backfill RVP PETRA SOLID AS A RUCK NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 13 placed against the footings upon removal of forms should be compacted to at least 90 percent of the applicable maximum dry density. Reinforcement All continuous footings should be reinforced with a minimum of two No. 4 bars, one top, and one bottom. Pad footings should be a minimum 24 inches square and be reinforced at a minimum with No. 4 bars spaced a maximum of 18 inches on centers, both ways, near the bottom of the footings. Footing Embedment The base of retaining -wall footings constructed on level ground may be founded at a depth of 12 inches or more below the lowest adjacent final grade. Active and At -Rest Earth Pressures Active and at -rest earth pressures to be utilized for design of any retaining walls to be constructed within the site will be dependent on whether on -site soils or imported granular materials are used for backfill. For this reason, active and at -rest earth pressures are provided below for both conditions. 1. On -Site Soils Used for Backfill If on -site soils are used as backfill, active earth pressures equivalent to fluids having densities of 35 and 51 pounds per cubic foot should be used for design of cantilevered walls retaining a level backfill and ascending 2:1 backfill, respectively. For walls that are restrained at the top, at -rest earth pressures of 53 and 78 pounds per cubic foot (equivalent fluid pressures) should be used. The above values are for retaining walls that have been supplied with a proper subdrain system (see Figure RW-I). All walls should be designed to support any adjacent structural surcharge loads imposed by other nearby walls or footings in addition to the above recommended active and at -rest earth pressures. 2. Imoorted Sand, Pea Gravel or Rock Used for Wall Backfill Where imported clean sand exhibiting a sand equivalent value (SE) of 30 or greater, or pea gravel or crushed rock are be used for wall backfill, the lateral earth pressures may be reduced provided these granular backfill materials extend behind the walls to a minimum horizontal distance equal to one-half the wall height. In addition, the sand, pea gravel or rock backfill materials should extend behind the walls to a minimum horizontal distance of 2 feet at the base of the wall or to a horizontal distance equal to the heel width of the footing, whichever is greater (see Figures RW-2 and RW-3). For the above conditions, cantilevered walls retaining a level backfill and ascending 2:1 backfill may be designed to resist active earth pressures equivalent to fluids having densities of 30 and 41 pounds per cubic foot, respectively. For walls that are restrained at the top, at -rest earth pressures equivalent to fluids having densities of 45 and 62 pounds per cubic foot are recommended for design of restrained walls supporting a level backfill and ascending 2:1 backfill, respectively. These values are also for retaining walls supplied with a proper subdrain system. Furthermore, as with native soil backfill, the walls should be designed to support any adjacent structural surcharge loads imposed by other nearby walls or footings in addition to the recommended active and at -rest earth pressures. PETFM SOaO AS A ROCK NATIVE SOIL BACKFILL Sloped or level ground surface )mpacted on -site soil imende'd backout* ng compound 12-inch-wide column of 3/4" - 1 1/2" open graded gravel wrapped in filter fabric. ""'Filter fabric (should consist of 140N or equivalent) p6ft6rated pipe. Perforated pipe should -consist of 4" diameter ABS SDR-35 or PVC Schedule 40 or approved equivalent with the ,`,;perforations laid down. Pipe should be laid on at least 2 inches of open -graded gravel. Vertical height (h) and slope angle of backout per soils report. Based on geologic; conditions, configuration of backcut may require revisions (i.e. reduced vertical height, revised slope angle, etc.) 100 PETRA RETAINING WALL BACKFILL FIGURE RW-1 AND SUBDRAIN DETAILS I IMPORTED SAND BACKFILL Sloped or level ground surface `:'•. On -site native soil cap .;?'•.. (12"thick) .Non -expansive imported compound nstall subdraln system I cubic foot per foot min. of 3/4" -1 1 /2" )pen graded gravel wrapped in filter abric. :liter fabric (should consist of vlirafi 140N or equivalent). I inch perforated pipe. Perforated pipe should :onsist of 4" diameter ABS SDR-35 or PVC ichedule 40 or approved equivalent with the ierforations laid down. Pipe should be laid on it least 2 inches of open -graded gravel. * At base of wall, the non -expansive backfill materials should extend to a min. distance of 2' or to a horizontal distance equal to the heel width of the footing, whichever is greater. I �` PETRA I RETAINING WALL BACKFILL I FIGURE RW-2 I AND SUBDRAIN DETAILS IMPORTED GRAVEL OR CRUSHED ROCK BACKFILL / / Sloped or level ground surface on -site native soil cap (12" thick) {pensive imported or crushed rock MINi3 q s� o; ��"tiy ° f ::^Instalifilterfabric(Mirafi 140N H `bnap a e s� °d® �� •. equal)or of fies ito bto t migration Is r, ackflll compound Inch perforated pipe. Perforated pipe should Q4 ffi o� ?consist of 4"diameter ABS SDR-35 or PVC �1 : ,.,Schedule 40 or approved equivalent with the perforations laid down. If pea gravel used, ,; , •..,.. , „; pipe should be encased in 1 cubic foot per ' foot min. of 3/4" -1 1/2" open -graded gravel in filter fabric (Mirafi 140N or equal) Pipe should b laid n e d o at least 2 inches of `2 min. ravel. At base of wall, the non -expansive backfill materials should extend to a min. distance of 2' or to a horizontal distance equal to the heel width of the footing, whichever is greater. 0 PETRA RETAINING WALL BACKFILL FIGURE RW-3 AND SUBDRAIN DETAILS NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 14 Earthquake Loads Retaining Walls Note 1 of Section 1803.5.12 of the 2016 CBC indicates that the dynamic seismic lateral earth pressures on foundation walls and retaining walls supporting more than 6 feet of backfill height due to design earthquake ground motions be determined. It is unlikely that any wall retaining 6 or more feet of backfill will be constructed onsite. Accordingly, dynamic seismic lateral earth pressures are not considered necessary for this project. Subdrainage Perforated pipe and gravel subdrains should be installed behind all basement and retaining walls to prevent entrapment of water in the backfill (see Figures RW-1 through RW-3). Perforated pipe should consist of 4- inch-minimum diameter PVC Schedule 40, or SDR-35, with the perforations laid down. The pipe should be encased in a 1-foot-wide column of 1/4-inch to 1 %z-inch open -graded gravel. If on -site soils are used as backfill, the open -graded gravel should extend above the wall footings to a minimum height equal to one- third the wall height or to a minimum height of 1.5 feet above the footing, whichever is greater. If imported sand, pea gravel, or crushed rock is used as backfill, subdrain details shown on Figures RW-2 and RW-3 should be utilized. The open -graded gravel should be completely wrapped in filter fabric consisting of Mirafi 140N or equivalent. Solid outlet pipes should be connected to the subdrains and then routed to a suitable area for discharge of accumulated water. If a limited area exists behind the walls for installation of a pipe and gravel subdrain, a geotextile drain mat such as Mirafi Miradrain, or equivalent, can be used in lieu of drainage gravel. The drain mat should extend the full height and lengths of the walls and the filter fabric side of the drain mat should be placed up against the backcut. The perforated pipe drain line placed at the bottom of the drain mat should consist of 4-inch minimum diameter PVC Schedule 40 or SDR-35. The filter fabric on the drain mat should be peeled back and then wrapped around the drain line. Waterproofing The portions of retaining walls supporting backfill should be coated with an approved waterproofing compound or covered with a similar material to inhibit infiltration of moisture through the walls. PETRA SOLID ASA ROCK NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 15 Wall Backfrll Recommended active and at -rest earth pressures for design of retaining walls are based on the physical and mechanical properties of the on -site soil materials. On -site soil materials may be difficult to compact when placed in the relatively confined areas located between the walls and temporary backcut slopes. Therefore, to facilitate compaction of the backfill, consideration should be given to using pea gravel or crushed rock behind the proposed retaining walls. For this condition, the reduced active and at -rest pressures provided previously for sand, pea gravel, or crushed rock backfill may be considered in wall design provided they are installed as shown on Figures RW-2 and RW-3. Where the onsite soils materials or imported sand (with a Sand Equivalent of 30 or greater) are used as backfill behind the proposed retaining walls, the backfill materials should be placed in approximately 6- to 8-inch-thick maximum lifts, watered as necessary to achieve near optimum moisture conditions, and then mechanically compacted in place to a minimum relative compaction of 90 percent. Flooding or jetting of the backfill materials should be avoided. A representative of the project geotechnical consultant should observe the backfill procedures and test the wall backfill to verify adequate compaction. If imported pea gravel or rock is used for backfill, the gravel should be placed in approximately 2- to 3- foot-thick lifts, thoroughly wetted but not flooded, and then mechanically tamped or vibrated into place. A representative of the project geotechnical consultant should observe the backfill procedures and probe the backfill to determine that an adequate degree of compaction is achieved. To reduce the potential for the direct infiltration of surface water into the backfill, imported sand, gravel, or rock backfill should be capped with at least 12 to 18 inches of on -site soil. Filter fabric such as Mirafi 140N or equivalent, should be placed between the soil and the imported gravel or rock to prevent fines from penetrating into the backfill. If a thicker cap is desired (for planting or other reasons), consultation with the project structural engineer may be required to ascertain if the wall design is appropriate for the additional lateral pressure that a thicker cap of native material may impose. Geotechnical Observation and Testing All grading and construction phases associated with retaining wall construction, including backcut excavations, observation of the footing and pier excavations, installation of the subdrainage systems, and placement of backfill should be provided by a representative of the project geotechnical consultant. 10 PETRA SOLID AS AAOCK NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 16 Masonry Block Walls (Non -Retaining) Footings for free-standing (non -retaining) masonry block walls may be designed in accordance with the bearing and lateral resistance values provided previously for building footings. However, as a minimum, the wall footings should be embedded at a minimum depth of 12 inches below the lowest adjacent final grade. The footings should also be reinforced with a minimum of two No. 4 bars, one top and one bottom. In order to reduce the potential for unsightly cracking related to the possible effects of differential settlement and/or expansion, positive separations (construction joints) should also be provided in the block walls at each corner and at horizontal intervals of approximately 20 to 25 feet. The separations should be provided in the blocks and not extend through the footings. The footings should be poured monolithically with continuous rebars to serve as effective "grade beams" below the walls. Planter Walls Low -height planter walls should be supported by continuous concrete footings constructed in accordance with the recommendations presented previously for masonry block wall footings. EXTERIOR CONCRETE FLATWORK General Near -surface compacted fill soils within the site are variable in expansion behavior and are expected to exhibit very low to low expansion potential. For this reason, we recommend that all exterior concrete flatwork such as sidewalks, patio slabs, large decorative slabs, concrete subslabs that will be covered with decorative pavers, private vehicular driveways and/or access roads within the site be designed by the project architect and/or structural engineer with consideration given to mitigating the potential cracking and uplift that can develop in soils exhibiting expansion index values that fall in the low category. The guidelines that follow should be considered as minimums and are subject to review and revision by the project architect, structural engineer and/or landscape consultant as deemed appropriate. If sufficient time will be allowed in the project schedule for verification sampling and testing prior to the concrete pour, the test results generated may dictate that a somewhat less conservative design could be used. Thickness and Joint Spacing To reduce the potential of unsightly cracking, concrete walkways, patio -type slabs, large decorative slabs and concrete subslabs to be covered with decorative pavers should be at least 4 inches thick and provided with construction joints or expansion joints every 6 feet or less. Private driveways that will be designed for Q�� PETRA SOLID ASA ROCK GEOSCIENCES- NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 17 the use of passenger cars for access to private garages should also be at least 5 inches thick and provided with construction j oints or expansion j oints every 10 feet or less. Reinforcement All concrete flatwork having their largest plan -view panel dimension exceeding 5 feet should be reinforced with a minimum of No. 3 bars spaced 24 inches on centers, both ways. The reinforcement should be properly positioned near the middle of the slabs. The reinforcement recommendations provided herein are intended as guidelines to achieve adequate performance for anticipated soil conditions. The project architect, civil andlor structural engineer should make appropriate adjustments in reinforcement type, size and spacing to account for concrete internal (e.g., shrinkage and thermal) and external (e.g., applied loads) forces as deemed necessary. Edge Beams (Optional) Where the outer edges of concrete flatwork are to be bordered by landscaping, it is recommended that consideration be given to the use of edge beams (thickened edges) to prevent excessive infiltration and accumulation of water under the slabs. Edge beams, if used, should be 6 to 8 inches wide, extend 8 inches below the tops of the finish slab surfaces. Edge beams are not mandatory; however, their inclusion in flatwork construction adjacent to landscaped areas is intended to reduce the potential for vertical and horizontal movement and subsequent cracking of the flatwork related to uplift forces that can develop in expansive soils. Subgrade Preparation Compaction To reduce the potential for distress to concrete flatwork, the subgrade soils below concrete flatwork areas to a minimum depth of 12 inches (or deeper, as either prescribed elsewhere in this report or determined in the field) should be moisture conditioned to at least equal to, or slightly greater than, the optimum moisture content and then compacted to a minimum relative compaction of 90 percent. Pre-Moistenine As a further measure to reduce the potential for concrete flatwork cracking, subgrade soils should be thoroughly moistened prior to placing concrete. The moisture content of the soils should be at least 1.2 times the optimum moisture content and penetrate to a minimum depth of 12 inches into the subgrade. Therefore, moisture conditioning should be achieved with sprinklers or a light spray applied to the subgrade PETRASOLID AS A DOCK NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 18 over a period of few to several days just prior to pouring concrete. Pre -watering of the soils is intended to promote uniform curing of the concrete, reduce the development of shrinkage cracks and reduce the potential for differential expansion pressure on freshly poured flatwork. A representative of the project geotechnical consultant should observe and verify the density and moisture content of the soils, and the depth of moisture penetration prior to pouring concrete. Drainage Drainage from patios and other flatwork areas should be directed to local area drains and/or graded earth swales designed to carry runoff water to the adjacent streets or other approved drainage structures. The concrete flatwork should be sloped at a minimum gradient as discussed earlier in the Site Drainage section of this report, or as prescribed by project civil engineer or local codes, away from building foundations, retaining walls, masonry garden walls and slope areas. Tree Wells Tree wells are not recommended in concrete flatwork areas since they introduce excessive water into the subgrade soils and allow root invasion, both of which can cause heaving and cracking of the flatwork. FUTUREIMPROVEMENTS Should any new structures or improvements be proposed at any time in the future other than those shown on the enclosed grading plan and discussed herein, our firm should be notified so that we may provide design recommendations. Design recommendations are particularly critical for any new improvements that may be proposed on or near descending slopes, and in areas where they may interfere with the proposed permanent drainage facilities. Potential problems can develop when drainage on the pad is altered in any way (i.e., excavations or placement of fills associated with construction of new walkways, patios, block walls and planters). Therefore, it is recommended that we be engaged to review the final design drawings, specifications and grading plan prior to any new construction. If we are not given the opportunity to review these documents with respect to the geotechnical aspects of new construction and grading, it should not be assumed that the recommendations provided herein are wholly or in part applicable to the new construction or grading. POST -GRADING OBSERVATIONS AND TESTING Our firm should be notified at the appropriate times in order that we may provide the following observation and testing services during the various phases of post grading construction: 10 PETN A SOLID ASA ROCK NICHOLSON CONSTRUCTION August 27, 2020 304 Goldenrod Avenue / Corona Del Mar J.N. 19-265 Page 19 1. Building Construction • Observe all footing trenches when first excavated to verify competent soil bearing conditions. • Re -observe all footing trenches, if necessary, if trenches are found to contain a significant accumulation of loose, saturated or otherwise compressible soils. • Observe and test subgrade soils below all slab areas to verify adequate moisture content and penetration. 2. Masonry Block Walls and Retaining Walls • Observe all footing trenches when first excavated to verify competent soil bearing conditions. • Re -observe all footing trenches, if necessary, if trenches are found to contain significant slough, saturated or compressible soils. • Observe the subdrain systems installed behind the retaining walls. • Observe and perform field density testing of retaining wall backfill. 3. Utility Trench Backfill • Observe and perform field density testing of utility trench backfill. 4. Concrete Flatwork Construction • Observe and test subgrade soils below concrete flatwork areas to document field densities, moisture content, and moisture penetration. 5. Re-Grading/Additional Grading • Observe and perform field density testing of fill to be placed in temporary excavations, as well as above or beyond the grades shown on the accompanying grading plan. REPORT LIMITATIONS A representative of Petra was present on -site during grading operations on an on -call, as -needed basis for the purpose of providing the owner's representative with professional opinions and recommendations. These opinions and recommendations were developed based on field observations and selective testing of the contractor's work. Our scope of services during this project did not include supervision or direction of the contractor, his personnel or his subcontractors. Our observations and testing did not reveal any obvious deviations from the recommendations provided in the referenced geotechnical report by our firm; however, 10 PETRA SOLID AS A HOCK NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar August 27, 2020 J.N. 19-265 Page 20 Petra does not in any way guarantee the contractor's work, nor do our services relieve the contractor (or any sub -contractors) of their liability should any defects subsequently be discovered in their work product. Based on our findings, the conclusions and recommendations presented herein and within the referenced report by our firm were prepared in conformance with generally accepted professional engineering practices. No warranty is expressed or implied. This opportunity to be of service is sincerely appreciated. Please call if you have any questions pertaining to this report. Respectfully submitted, f�T INC. Don Obert I, J n,t Darrel Roberts 5g\O GF Associate Engineer i 1 Principal Geologist RGE 2872 CEG 1972 O a OAiQ�LR[]BFA SM DOlDR kg NO. Iffm 0 CEFMFI® _— Bi61NEMIN3 Attachments: Table A — Field Density Test Results Nj GEOIAGN Table B — Laboratory Data Summary 9 t Figures RW-1 through RW-3 — Retaining Wall Details �OF CAl-\F Figure 1— Density Test Location Plan W:@0142019\2 M00\19-265 Nicholson Conshuelion(3M Goldenrod Ave., Corona del Mar)\Rcport\19-265200 Rough Grade Re,uMdocx �°6° • NICHOLSON CONSTRUCTION 304 Goldenrod Avenue / Corona Del Mar TABLE A Field Density Test Results August 27, 2020 J.N. 19-265 Date of Test Test No. Location *Depth ft. Moisture % Unit Wt. lbs./cu.ft. % Rel. Comp. Soil Type 8/6/20 1 Building Pad 2.0 11.3 111.7 93 A 8/7/20 2 Building Pad 1.0 12.1 112.9 94 A 8/7/20 3 Building Pad 3.0 11.8 111.4 93 A 8/7/20 4 Building Pad 1.0 12.7 111.9 93 A 8/10/20 5 Building Pad 2.0 12.2 110.6 92 A 8/10/20 6 Building Pad 0.0 11.7 111.2 93 A 8/11/20 7 Building Pad FP 11.1 112.9 94 A * Depth below finish grade FP — Finish Pad PETRASOLID AS A ROCK GEOSCIENCES- m r N M N V a a � a a a 0 0 0 o d m - d d F F73 F R U « U U U a 0 6 ° a � Z c°> Q 7 Z m 'E i i w .0 a) 0 !7 �7�7�..J A911V rvR Q % N N a Lu U Q c N w { a n ,e o 0 0 CU m y _ - n/ .Pnnrana orx y w Q Z sl O �pmFPpU VmU w w � (0 C O 0 j M 0 U W z (n �U w F Z. w m w too gis o j\ Po i pr _.� v 35� 5