Loading...
HomeMy WebLinkAboutH-7 - Long Range Plans for Use of City Dump♦ - • CITY OF NEWPORT BEACH OFFICE OF THE CITY MANAGER TO: CITY COUNCIL FROM: City Manager • SUBJECT: LONG RANGE PLANS FOR USE OF CITY DUMP SITE r u, / December 11, 1967 In September, 1965 the City entered into an agreement with Engineering - Science, Inc. of Arcadia to conduct a refuse disposal study and to evaluate the existing use of the City dump facility. The resultant report indicated that: 1. The value of the property was approximately $580,000: JN61L• 2. The annual increase in property value would exceed the addi- tional annual cost of hauling rubbish collected westerly of the Upper Bay to the County dump in Coyote Canyon, assuming ?OSITION: there was an immediate and complete cessation of hauling refuse to the City dump: E:w n � 3. Sanitary landflling had degraded 17 of the 40 acre parcel to th t t that th rti n ssibl ma n ion er be ec n- e ex en is po o po y y o g o omcally used for future building; and t� ��.�I� 4. Over one million cubic yards of saleable aggregate material dfr i��ivaue✓ remain should the City wish to allow further aggregate mining .� �1 7 /�b 7 d of the property (which would have a partial depreciating tee // affect on the property's value). CS)WtaL� 16t2lf -e-c� A-1 C� In a report dated September 7, 1966, the City Council was advised that if the City plans to allow further aggregate mining, such mining should be preceded S �o, by a complete engineering plan and a precise program for the removal of these ,,�- L;,,,,,Diaterials in terms of profiles and schedules. In addition, it was suggested that before proceeding further, it would be desirable to have an economic land use before made in order to obtain the maximum benefit from the property. The esti- mated cost for this engineering plan and economic land use study was $10,000. On September 26, 1966, the City Council authorized discontinuation of the City dump property as a refuse disposal site in preference for using the Orange County Dump; holding the City dump property as a reserve refuse disposal site until such time that it will never be needed for that purpose; and the solicita- tion of proposals by the City Manager from recognized qualified consultants for an economic land use study and engineering plan for future use of the abandoned dump site. Proposals for performing the economic land use study and engineering plan under a single project were solicited from three :firms -- Wilsey and Ham, Arcadia; Quinton Engineers, Los Angeles; and Voorheis - Trindle and Nelson, Westminster. Although all three firms are well qualified to undertake this project, it is felt that the firm of Wilsey and Ham is best suited to handle this particular City Council • Page 2 • December 11, 1967 analysis primarily because of their outstanding and diversified experience in the areas of engineering and land use planning. They also have submitted the lowest estimate for this work. To determine the value of the site to the City in the immediate as well as ultimate future, and also learn how the property might best be used or disposed of, the project would include the following: 1. A determination of surrounding land values: 2. An analysis of needed horizontal and vertical controls, including a topographic map: 3. A study of the potential value to the City of a gravel mining operation: 4. A determination of the possible value of the property to other parties in terms of potential future development; 5. A review of the General Plans of the Cities of Newport Beach and Costa Mesa; 6. The taking of a series, of soil borings of varying depths; 7. A review of the traffic capabilities of adjacent streets; i 8. A study of the City's ability to service the area with water, sewer and storm drainage; 9. Ascertaining the existing site deficiencies and developing additional data sufficient to answer any of these deficiencies; 10. A determination and analysis of the various alternate solutions avail- able to the City; and 11. The preparation of 15 copies of the final report which would contain sufficient background data to support the recommendations made to the City. The estimated cost for this project is $5,700. The project will be completed, including the submission of the .final report, within sixty days from the date the contract is awarded. Monies were provided for this project in the 1966 -67 Budget. However, they were not encumbered during that period and through an oversight, funds were not carried over to the current Budget. Therefore, special provisions must be made for financing before this project can proceed. Various methods of financing are being explored and the method may depend to some extent on mid -year Budget analysis. For this reason, the financing question should be held in abeyance for the next 15 to 30 days until a firm recommendation can be made on financing methods. RECCI44ENDATION: It is recommended that the firm of Wilsey and Ham be selected to perform the economic land use study and engineering plan as outlined above at a cost not to exceed $5,700. HLH /JPD:ep /� ME i