HomeMy WebLinkAboutX2018-3239 - Soils (2)COAST GEOTECHNICAL, INC.
1200 W Commonwealth Avenue, Fullerton, CA 92833 Ph: (714) 870-1211 Fax: (714) 870-1222 Email: coastgeotec@sboglobal.net
July 1, 2019
Mr. Gary Uecker
C/o C.J. Light Associates
1401 Quail Street, Suite 120
Newport Beach, CA 92660
References:
W.O. 544317-03
Subject: Rough Grade Compaction Report for
Proposed New Residence at 1076 Pescador
Drive, Newport Beach, California
1. Geotechnical Engineering Investigation of Proposed New Residence at 1076 Pescador Drive,
Newport Beach, California; by COAST GEOTECHNICAL, INC., W.O. 544317-01, dated
January 17, 2018.
2. Response to First Geotechnical Report Review Checklist for New Residence at 1076 Pescador
Drive, Newport Beach, California, by COAST GEOTECHNICAL, INC., W.O. 544317-02, dated
January 31, 2019.
Dear Mr. Uecker:
Forwarded herewith is the rough grade compaction report for the subject site. The grading
operation for construction of the building pad was conducted from June 18, 2019 through June
26, 2019.
PLACEMENT OF FILL
Compacted fill material was placed on the subject site to provide adequate support for the
proposed structure.
Overexcavation extended down to competent native earth material. The depth of the
overexcavation was approximately three to four and a half feet below finish grade for the house
pad. The bottom of the excavations exposed competent material. The exposed surface was
scarified, heavily watered, and compacted to a minimum of 90% relative compaction.
Subsequent fills were placed in six to eight inch loose lifts and compacted to a minimum of 90%
relative compaction by rubber tire loader. Import soil was used to get finish pad grade elevations.
This process was followed to final grade.
Limits of grading are shown on the attached Plate 1.
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 2 W.O. 544317-03
Rough Grade Compaction Report July 1 2019
Equipment used for the compaction of fill soils consisted of a Cat 973D track loader and Kubota
SVL95 rubber track loader. Soils were moisture conditioned by a water hose as needed.
Earthwork was by Tight Quarters Inc.
TESTING
Maximum density optimum moisture relationship determinations were performed for each soil
type encountered during grading operations. Test results were as follows:
Laboratory Standard: (ASTM:D-1557)
4 -inch diameter mold; 1/30 ft3 volume.;
5 layers at 25 blows per layer;
10 lb. hammer dropped 18 inches
Compaction tests were performed a minimum of every two feet and/or 500 cubic yards of
compacted fill soils placed. These tests were performed in accordance with ASTM test methods.
The test results are summarized in Table 1. The approximate test locations are shown on Plate 1.
FOUNDATIONS ON COMPACTED FILL
Foundations for the proposed residence shall be supported by continuous spread footings or
isolated pads placed a minimum depth of 24 inches below lowest adjacent grade inches utilizing
an allowable bearing value of 1,800 pounds per square foot. Minimum foundation width shall be
fifteen inches. This value is for dead plus live load and may be increased 1/3 for total including
seismic and wind loads where allowed by code.
Isolated pads shall be connected to adjacent foundations in at least two directions with grade
beams or continuous footings.
It is recommended that all footings be reinforced with a minimum of four. #5 bars (two top and
two bottom). The structural engineer's reinforcing requirements should be followed if more
stringent.
Footing excavations shall be observed by a representative of COAST GEOTECHNICAL, Inc.
pnor to p acement of steel or concrete to verify competent soil conditions. If unacceptable soil
conditions are exposed mitigation will be recommended.
sification
OM41sture%
Max DryDens3?
Brown Silty Sand
9.5
_ .
125.0
ty, Sandy Clay
NVI
12.0
118.0
wn Silty, Slightly10.0
127.0
ey Sandray
Siltstone
13.0
110.0
Compaction tests were performed a minimum of every two feet and/or 500 cubic yards of
compacted fill soils placed. These tests were performed in accordance with ASTM test methods.
The test results are summarized in Table 1. The approximate test locations are shown on Plate 1.
FOUNDATIONS ON COMPACTED FILL
Foundations for the proposed residence shall be supported by continuous spread footings or
isolated pads placed a minimum depth of 24 inches below lowest adjacent grade inches utilizing
an allowable bearing value of 1,800 pounds per square foot. Minimum foundation width shall be
fifteen inches. This value is for dead plus live load and may be increased 1/3 for total including
seismic and wind loads where allowed by code.
Isolated pads shall be connected to adjacent foundations in at least two directions with grade
beams or continuous footings.
It is recommended that all footings be reinforced with a minimum of four. #5 bars (two top and
two bottom). The structural engineer's reinforcing requirements should be followed if more
stringent.
Footing excavations shall be observed by a representative of COAST GEOTECHNICAL, Inc.
pnor to p acement of steel or concrete to verify competent soil conditions. If unacceptable soil
conditions are exposed mitigation will be recommended.
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 3 W.O. 544317-03
Rough Grade Compaction Report July 1 2019
FOUNDATIONS ON NATIVE SOILS
Secondary structures may be supported by continuous spread footings placed a minimum depth
of 24 inches below lowest adjacent grade may utilize an allowable bearing value of 1,500 pounds
per square foot. This value is for dead plus live load and may be increased 1/3 for total including
seismic and wind loads where allowed by code.
It is recommended that all footings be reinforced with a minimum of four # 5 bars (two top and
two bottom). The structural engineer's reinforcing requirements should be followed if more
stringent.
A representative of COAST GEOTECHNICAL, Inc. shall observe foundation excavations to
verify that they comply with project geotechnical recommendations. Some mitigation of footing
bottoms (deepening or compaction) should be anticipated.
LATERAL DESIGN
Lateral restraint at the base of footings and on slabs may be assumed to be the product of the
dead load and a coefficient of friction of 0.30. Passive pressure on the face of footings may also
be used to resist lateral forces. A passive pressure of zero increasing at the rate of 300 pounds per
square foot of depth to a maximum value of 3000 pounds per square foot may be used for
compacted fill and native soil at this site. If passive pressure and friction are combined when
evaluating the lateral resistance, the value of the passive pressure should be limited to 2/3 of the
values given above.
RETAINING WALLS
Walls retaining drained earth under static loading may be designed for the following:
The code requires that retaining walls supporting more than six feet of backfill be designed for
earthquake ground motions. A supplemental report will be needed if final plans show this condition
to exist. The client is advised that seismic loads will be high due to high ground motion and current
City policy.
The point of resultant force under static loading is at H/3 above the base of the retaining wall.
Footing excavations require the observation and approval by COAST GEOTECHNICAL, Inc.
and the City grading inspector.
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 4 W.O. 544317-03
Roush Grade Compaction Report July 1, 2019
WATERPROOFING
There is an inherent risk associated with moisture -induced problems when constructing earth
retaining structures. The client, the design consultant of the waterproofing system, and the
contractor responsible for installation, assumes this risk. The geotecbnical consultant is only
responsible for identification of adverse moisture conditions, which could impact below grade
rooms. Site basement walls and floors shall be waterproofed to the degree desired by the client.
Waterproofing design is not within the expertise or work scope of the soils engineer.
SUBDRAINS
Subdrain systems shall be installed behind retaining walls and at a minimum they shall consist of
four -inch diameter SCH 40 or SDR 35 perforated pipe surrounded with one cubic foot, per lineal
pipe foot, of 3/4 -inch gravel. The gravel shall be wrapped in filter fabric. Outlet pipes shall be
solid pipe of similar material.
Subdrain systems shall be independent of area surface drains and roof drains.
Subdrain placement requires observation and approval by COAST GEOTECHNICAL, Inc.
RETAINING WALL BACKFILL
Retaining wall backfills shall consist of onsite granular import earth materials, gravels, or where
allowed and or designed for onsite earth materials.
The project soils engineer shall be consulted prior to the import of any select backfill to verify
that the import material complies with our recommendations for select material. At a minimum
the material shall have an expansion index of zero and a minimum phi angle of 30 degrees.
Materials typically utilized are pea gravels, 3/4 -inch gravels, and clean sand. Where gravel is
utilized, the gravel shall be separated from soil by filter cloth.
The upper two to three feet of backfill shall be with a cohesive onsite or import soil to reduce
infiltration of surface water.
Prior to placement of any backfills the area shall be cleaned of loose soils and construction
debris. COAST GEOTECHNICAL, Inc. shall observe and approve the area as acceptable prior
to any backfill placement.
Retaining wall backfill shall be placed in six to eight inch loose; moisture conditioned lifts and
mechanically compacted to a minimum of 90% relative compaction. Backfills require testing at
two -foot vertical intervals during placement.
Compaction of backfills requires observation and approval by COAST GEOTECHNICAL, Inc.
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 5 W.O. 544317-03
Rough Grade Compaction Report July 1 2019
SETBACK
Foundations shall maintain a setback as measured horizontally from the bottom outside footing
edge to a descending slope face of H/3 where H is the slope height. Based on a slope height of
about twenty-three feet, a minimum eight -foot setback is recommended.
DECK & PLANTER WALLS
Foundations on or at the top of slope, may consist of a pile and grade beam foundation system
that maintains at least an eight -foot foundation setback from the slope face. Where piles are
necessary they shall be at least 18 inches in diameter and shall extend at least five feet into
compacted fill or native soil below the creep zone.
Piles may be designed using a skin friction value of 400 psf per foot of intercept with compacted
fill or native soil with a point of fixity taken at five feet. Piles shall be interconnected with grade
beams. The weight of the pile and grade beams may be neglected in considering dead loads.
Structural design shall determine actual depth requirements based on loading. This value is for
dead plus live load and may be increased 1/3 for total including seismic and wind loads where
allowed by code.
Foundation excavations shall be observed by a representative of COAST GEOTECHNICAL,
INC. prior to placement of steel and/or concrete to verify compliance with geotechnical
recommendations. If unacceptable conditions are exposed mitigation will be required.
CREEP LOAD
Creep loads may impact proposed site improvements near the descending slope. Proposed
foundations and site improvements located within ten feet of this top of slope or located on this
slope shall incorporate a creep value of 1,000 pounds per foot of depth for the upper three feet of
earth material. Passive pressures shall be ignored in the creep zone.
SEISMIC DESIGN
Based on the 2016 CBC the following seismic design parameters are provided. These seismic
design values were determined utilizing latitude 33.62468 and longitude -117.8976 and
calculations from the USGS Seismic Tool Application. A conservative site class D was assigned to
site earth materials. A printout of the USGS Seismic Tool output is attached in Appendix B.
• Site Class = D
• Seismic Design Category = D
• Mapped 0.2 Second Spectral Response Acceleration, Ss = 1.697g
• Mapped One Second Spectral Response Acceleration St = 0.624g
• Site Coefficient from Table 1613A.3.3(1), Fa =1.0
• Site Coefficient from Table 1613A.3.3(2). Fv = 1.5
• Maximum Design Spectral Response Acceleration for short period, Sm, = 1.697g
• Maximum Design Spectral Response Acceleration for one -second period, SMl = 0.936g
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 6 W.O. 544317-03
Roush Grade Compaction Report July 1. 2019
• 5% Design Spectral Response Acceleration for short period, SDs = 1.132g
• 5% Design Spectral Response Acceleration for one -second period, SDI= 0.624g
SETTLEMENT
For a structure supported by foundations placed into approved earth materials the maximum total
post -construction settlement is anticipated to be on the order of one-half inch. Differential
settlements are expected to be less than 3/4 inch, measured between adjacent structural elements
over a horizontal distance of forty feet.
EXPANSIVE SOILS
Results of expansion tests indicate that the near surface soils have a medium expansion potential.
SUBSIDENCE & SHRINKAGE
Subsidence over the site is anticipated to be negligible. Shrinkage of reworked materials should be
in the range of 5 to 10 percent.
SOLUBLE SULFATES
A chemical analysis of typical near surface earth materials for soluble sulfates showed a sulfate
content of 75 ppm. Based on the current CBC and Table 4.3.1 of ACI 318-05 this is a negligible
exposure to sulfate corrosion. Type II cement may be utilized. Structural requirements may
dictate a higher strength concrete.
FLOOR SLABS
Proposed interior slabs shall derive support from compacted fill.
Site materials are expansive in nature. Guidelines in the current CBC shall be utilized in the
design of slabs.
For design of slab on grade a computed effective plasticity index of 18 may be utilized.
Minimum geotechnical recommendations for on grade slab design are five inch actual thickness
with #4 bars at twelve inches on center each way. Structural design may require additional
reinforcement and slab thickness.
If the soils at grade become disturbed during construction, they should be brought to 34% over
optimum moisture content and recompacted to a minimum of 90% relative compaction. Prior to
placement of the capillary break and or vapor barrier COAST GEOTECHNICAL, Inc., shall test
the slab subgrade soils for moisture content and compaction.
The capillary break -material- shallcomply-with-the requirements -of thelocaljurisdiction and -
shall be a minimum of four inches in thickness and consist of gravel (1/2 -inch or larger clean
aggregate). A heavy filter fabric should be placed over the gravels prior to placement of the
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 7 W.O. 544317-03
Roueh Grade Compaction Report July 1, 2019
recommended vapor retarder to minimize puncturing of the vapor retarder. Additionally, a
vibratory plate should be used over the gravels prior to placement of the filter fabric to smooth
out any sharp protuberances and consolidate the gravels/sands.
Slab areas should be underlain by a vapor retarder consisting of an engineered plastic film (as
described by ASTM:E-1745). In areas where a moisture sensitive floor covering will be used
and/or where moisture infiltration is not desirable, a vapor barrier with a permeance of less than
0.01perms (consistent with ACI 302.2R-06) such as 15 mil. Stego Wrap Vapor Barrier, or
equivalent should be considered. The vapor barrier should be underlain by the above described
capillary break material and filter cloth. The capillary break materials should be compacted to a
uniform condition prior to placement of the recommended filter cloth and vapor barrier. The
vapor barrier should be properly lapped and sealed and in contact with the slab bottom.
TEMPORARY CUTS
Temporary construction cuts, based on preliminary plans, are anticipated for the grading
Temporary cuts in site earth materials are anticipated to expose existing fill soil and shall be sloped
at a 1:1(H:V) angle.
No cuts shall be allowed which would remove significant runs of lateral support from adjacent
properties, structures, or public right of ways. Typically construction cuts where these conditions
exist shall be restricted to a 1:1 downward projection to the excavation bottom. Alternate
construction methods may need to be used along the return property line walls of the toe of slope
retaining wall.
The project geologist shall observe all cuts at the time of excavation. If adverse conditions are
exposed, remedial measures will be recommended and implemented.
OSHA guidelines shall be followed where workers are to enter confined spaces, trench work, or
excavations.
UTILITY LINE BACKFILLS
All utility line backfills, both interior and exterior, shall be compacted to a minimum of
90% relative compaction and shall require testing at a maximum of two -foot vertical intervals.
Utility lines shall be placed at appropriate depths. Shallow pipes can be damaged by the forces
imposed by compacting backfill soils. If shallow pipes are not capable of withstanding the forces
of backfill compaction, slurry backfill will be recommended.
COAST GEOTECHNICAL, INC. shall be present during backfill placement and compaction to
verify_compliars .
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 8 W.O. 544317-03
Rough Grade Compaction Report July 1, 2019
HARDSCAPE AND SLABS
Hardscape and slab subgrade areas shall exhibit a minimum of 90% relative compaction to a depth
of at least two feet. Deeper removal and recompaction may be required if unacceptable conditions
are encountered. These areas require testing just prior to placing concrete. Hardscape shall be at
least four inches thick and reinforced with 94 bars on 18 inch centers both ways.
DRAINAGE
Positive drainage should be planned for the site. Drainage should be directed away from
structures via non -erodible conduits to suitable disposal areas. The structure should utilize roof
gutters and down spouts tied directly to yard drainage. Drainage shall not be directed onto or
over slopes.
Unlined flowerbeds, planters, and lawns should not be constructed against the perimeter of the
structure. If such landscaping (against the perimeter of a structure) is planned, it should be
properly drained and lined or provided with an underground moisture barrier. Irrigation should
be kept to a minimum.
While current CBC recommends 5% slope away from structures for landscape areas, 2% slope is
allowable where justified. Our justification is the use roof drains tied into area drains, the use of
area drains, and site grading which will mitigate the potential for moisture problems beneath a slab
on grade. Hardscape areas shall be sloped a minimum of 2% where within ten feet of the residence
unless allowed otherwise by the building official.
We do not recommend the use of bottomless trench drains to conform with infiltration best
management practice (BMP) such as infiltration trenches, infiltration basins, dry wells, permeable
pavements or similar systems designed primarily to percolate water into the subsurface soils within
ten feet of foundations or near slopes. Due to the physical characteristics of the site earth materials,
infiltration of waters into the subsurface earth materials has a risk of adversely affecting below
grade structures, building foundations and slabs, hardscape improvements and slope stability. From
a geotechnical viewpoint surface drainage should be directed to the street.
The WQMP requirement shall be addressed by the Civil Engineer.
POST -GRADING SERVICES
During construction of the residence, it is recommended, and at times required by the regulatory
agency, the following be observed and/or tested by the geotechnical engineer:
Foundation excavations for all structures
• Drainage and rock placement behind retaining walls
• Backfill compaction behind retaining walls
___Exterior_andinteriorslab_subgrade_compaction testing and moisture_ conditioning_ prior_ to_placement---
of
placement—of the capillary break or waste slab
• Compaction of exterior and interior utility trenches
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker 9 W.O. 544317-03
Rough Grade Compaction Report July 1, 2019
Hardscape subgrade
It is the responsibility of the developer to schedule the required observations and testing.
REGULATORY COMPLLANCE
I hereby certify that the subject grading was observed by a representative from this office, and
the work was done in full compliance with the Grading Ordinance of the City of Newport Beach
and in accordance with the best accepted practices of the applicable chapter of the California
Building Code.
All cuts, fills or processing of original ground under the purview of this report have been
completed under the observation of and with selective testing by COAST GEOTECHNICAL,
INC. and found to be in compliance with the Grading Code of the City of Newport Beach. The
completed work has been observed by COAST GEOTECHNICAL, INC. and is considered
adequate for the development. Our findings were made and recommendations prepared in
accordance with generally accepted professional engineering practices, and no further warranty
is implied nor made.
This report is subject to review by the controlling authorities for this project. We appreciate this
opportunity to be of service to you.
Respectfully submitted:
COAST GEOTECHNICAL, INC.
Ming-Tamg Chen
RCE 54011 `r c" �\
lI No b40 -1I_ ` ,r, z;auly
,, N
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker to W.O. 544317-03
Rough Grade Compaction Report July 1. 2019
COMPACTION TEST RESULTS
TABLE 1
1
Pad Area
3.54.0
11.6
113.5
I
90.8
6/18/19
2
Pad Area
3.54.0
10.1
113.8
I
91.0
6/18/19
3
Pad Area
2.53.0
12.1
113.3
1
90.6
6/18/19
4
Pad Area
2.53.0
9.9
113.9
I
91.1
6/18/19
5
Pad Area
1.01.5
11.2
113.5
I
90.8
6/19/19
6
Pad Area
4.04.5
8.9
114.0
I
91.2
6/19/19
7
Pad Area
4.04.5
8.4
114.6
I
91.7
6/19/19
8
Rear Deck
Footing Area
6.06.5
15.1
100.5
rV
91.4
6/19/19
9
Pad Area
0.51.0
9.0
117.4
I
93.9
6/19/19
10
Pad Area
3.03.5
12.5
117.0
1
93.6
6/19/19
11
Rear Slope
Area
5.05.5
15.4
107.1
II
90.8
6/20/19
12
Rear Slope
Area
4.55.0
16.2
108.3
II
91.8
6/20/19
13
Rear Slope
Area
4.55.0
15.9
107.9
II
91.4
6/20/19
14
Pad Area
3.03.5
16.9
108.2
II
91.7
6/20/19
15
Pad Area
2.53.0
10.1
115.6
I
92.8
6/20/19
16
Pad Area
2.02.5
15.2
109.4
H
92.7
6/21/19
17
Pad Area
4.04.5
10.5
113.9
I
91.1
6/24/19
18
Pad Area
2.53.0
10.0
113.5
1
90.8
6/24/19
19
Pad Area
1.52.0
9.8
114.9
I
91.9
6/24/19
COAST GEOTECHNICAL, INC.
Mr. Gary Uecker ] 1 W.O. 544317-03
Rough Grade Compaction Report July 1, 2019
20
Pad Area
F.G.
10.3
115.7
III
91.1
6/26/19
21
Pad Area
F.G.
12.5
115.4
III
90.9
6/26/19
22
Pad Area
F.G.
10.0
117.7
III
92.7
6/26/19
F.G.: Finish Grade
COMPACTION TEST LOCATIONS
'ridII�LL�
7
Pescador Drive
3.20
�9
"o w Sao
v ,
WO N L
QV
�18 it 4Mrm
3z`4? 0. r
z
7 *22
Rough Grade Compaction Report
Scale: V'= 20'
Compaction
Fest Location
of
1
Work Order 544317-03
C 'f Plate No. 1
wport Beach, ali orma
COAST GEOTECHNICAL, INC.