HomeMy WebLinkAbout06 - Water Well Rehabilitation - Tamura Deep Well (Project No. 24W15) - Award of Contract No. 9328-1Q �EwPpRT
CITY OF
s NEWPORT BEACH
`q44:09 City Council Staff Report
September 12, 2023
Agenda Item No. 6
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Andy Tran, Senior Civil Engineer, atran@newportbeachca.gov
PHONE: 949-644-3315
TITLE: Water Well Rehabilitation — Tamura Deep Well (Project No. 24W15)
— Award of Contract No. 9328-1
City of Newport Beach (City) staff received construction bids for the Tamura Deep Water
Well Rehabilitation project and requests City Council approval to award the construction
contract to General Pump Company, Inc. of San Dimas, CA. This project will rehabilitate
the Tamura Deep water well with mechanical and chemical treatment, and will install a
stainless -steel liner to restore and maintain water production.
RECOMMENDATIONS:
a) Find this project exempt from the California Environmental Quality Act (CEQA)
pursuant to Section 15302(c), Class 2 (reconstruction of existing facility involving
negligible or no expansion of capacity) of the CEQA Guidelines, because this project
has no potential to have a significant effect on the environment;
b) Approve the project plans and specifications;
c) Award Contract No 9328-1 to General Pump Company, Inc. for the total bid price of
$817,024 for the Tamura Deep Water Well Rehabilitation project, and authorize the
Mayor and City Clerk to execute the contract; and
d) Establish a contingency of $81,000 (approximately 10 percent of total bid) to cover the
cost of unforeseen work not included in the original contract.
DISCUSSION:
The Tamura Deep Water Well is one of four City water wells and is an integral part of the
City's water supply system. This well's pumping capacity has significantly declined over
the past year due to new holes in the well casing, which are allowing sand to enter the
pump. Installation of a new stainless -steel liner will prevent sand from entering the pump
and extend the life of the well.
6-1
Water Well Rehabilitation — Tamura Deep Well (Project No. 24W15) —
Award of Contract No. 9328-1
September 12, 2023
Page 2
At 10 a.m. on August 15, 2023, the City Clerk opened and read the following bids for this
project:
BIDDER
TOTAL BID AMOUNT
Low
I General Pump Company, Inc.
1 $ 817,024.00
The City received one bid for this project. The low bidder, General Pump Company, Inc.,
possesses a California State Contractor's License Classification "C-57" (Well Drilling
Contractor), as required by the project specifications. A review of references for General
Pump Company, Inc. shows satisfactory completion of similar contracts for the City and
other municipalities.
Although the City only received one bid, the bid is balanced and below the Engineer's
Estimate. General Pump Company is very familiar with the City's water wells as the
company has successfully completed many water well rehabilitation projects for the City
in the past 20 years. Well rehabilitation projects require a highly specialized contractor's
license classification (C-57). There are only a few contractors in Southern California that
are qualified to bid on this type of work. The City typically only receives a few bids for well
rehabilitation projects. Bidders were required to attend one of two mandatory pre -bid
meetings. A total of five potential bidders attended the mandatory meetings.
The low bid was 25.7 percent below the Engineer's Estimate of $1,100,000. The
difference between the low bid and the Engineer's Estimate was primarily attributed to
the lower bid prices for the new well liner and the rebuild and reinstallation of the City's
pump. The contractor's familiarity with the City's water wells may also have contributed
to the favorable bid prices.
The proposed project includes removing the existing motor and pump, conducting down
well video surveys, wire brushing, chemical treatment, mechanical treatment, installing a
new stainless -steel liner, installing the rebuilt permanent pump, and performing test
pumping.
Pursuant to the Contract Specifications, the contractor will have 80 consecutive working
days to complete the work. Work is scheduled to start in November 2023 during low water
demand months.
The project plans and specifications will be available for review at the September 12 City
Council meeting or upon request.
FISCAL IMPACT:
The adopted Capital Improvement Program (CIP) budget includes sufficient funding for
the award of this contract. The CIP budget for this project included in the FY 2023-24
Budget is $900,000. The following funds will be expended from the Water Capital Fund:
Account Description
Water Capital Fund - Water Well
Rehabilitation Project
Account Number Amount
70201933-980000-24W15 $ 900,000
Total: $ 900,000
6-2
Water Well Rehabilitation — Tamura Deep Well (Project No. 24W15) —
Award of Contract No. 9328-1
September 12, 2023
Page 3
Proposed fund uses are as follows:
\/Pnrinr
General Pump Company, Inc
General Pump Company, Inc
Various
Purpose
Construction Contract
Construction Contingency
Printing & Incidentals
Total:
Amount
$
817,024
$
81,000
$
1,976
$
900,000
Staff recommends establishing $81,000 (approximately 10 percent of total bid) for
contingency purposes and unforeseen conditions associated with construction.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15302(c), Class 2 (reconstruction
of existing facility involving negligible or no expansion of capacity) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because this project has
no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map