Grading Plan Check Corrections
Corrections shall be made on the tracings and three(3) new sets of plans shall be submitted. If you make changes to the
plan other than or in addition to what Plan Check has requested, yellow highlight the changes on one set of the re-submitted
plans.
Return the original check print with corrected plans. Payment of a new plan check deposit may be required for all plans
on which no action is taken by the applicant for a period of 180 days. Applications for which no permit is issued within
180 days following the date of submittal shall expire by limitation, and shall be discarded.
Project Number:GB050096
Submittal Date:Aug 03, 2005
CBC Edition: 2000
Plan Check Date: 8/9/2005 4:08 PM
Description:precise for sfd
and attached garage
Job Address
23 AVALON VISTA
NEWPORT COAST, CA
Owner Address
William Schulte
6 Anondale
Newport Beach CA92660
Current - 1st Plan Check
Plan Checked By
Michael Fisher
Michael.Fisher@pdsd.ocgov.com
714-834-6156
Page 1 of 5
GB050096
GENERAL INFORMATION
Please provide 24-hour notice to your plan checker, prior to obtaining the grading Permit.Return the original check
print with corrected plans. Payment of a new plan check deposit may be required for all plans on which the applicant
takes no action for a period of 180 days. Applications for which no permit is issued within 180 days following
date of submittal shall expire by limitation, and shall be discarded.
SUBMITTALS, FEES, BOND, INSURANCE AND ISSUANCE
Provide three (3) complete sets of corrected plans. Provide minimum 40-scale plan for precise grading. The maximum
size shall be 36" x 42". All sheets shall be uniform size. Plans will not be rechecked at the counter. Allow
one week for recheck.
Plan check and inspection deposit amounts will be calculated by the plan checker based on earthwork quantities
or drainage improvements, whichever is greater. The engineer shall provide this information.
Surety is required in the amount of $ _________. Surety may be posted in one of the following forms:
Bond
Certificate of Deposit
Letter of Credit
Cash or Cashier s Check
Personal/Company checks cannot be accepted. County approved forms for the various types of surety are available
upon request at the Grading Counter, Station 4, Room 122. Please note all signatures must be notarized.
Provide verification of contractor's coverage for Workman's Compensation insurance. If owner is doing work and
will not employ other workers, owner must sign exemption statement.
Owner or authorized agent and/or contractor must sign the permit at the time of issuance.
Authorized agent must have a notarized statement from the owner authorizing the agent to act on behalf of the owner.
The permittee and the entity providing the surety must be the same i.e., owner, developer or contractor.
Page 2 of 5 8/9/2005 4:08 PM
GB050096
Grading Plan Check Corrections
Sheet Comments
General
1 A) Show Assigned project address on title sheet of plan.
2 B) Show site acreage and earthwork quantities on plans:
2.1 Site Acreage_______ Acres
3 C) Each sheet of all plan sets must be stamped and signed by the Civil Engineer
or Architect of Record for the project.
4 E) Submit an itemized summary of the unit and total cost of all drainage devices,
grading, paving, and erosion control.
5 F) Show on Plans:
5.1 Grading Legend
5.2 Grading Limits and Off-Site Grading Limits
5.3 Permit Limits
5.4 Property Lines (labeled with P.L. symbols)
6 G) A notarized letter of permission from adjacent property owner(s) is required
for slope encroachment or other off-site grading or work . Include off-site legal
description and Assessor´s Parcel Number. (See soils report for caissons).
7 H) Show location of retaining walls on grading plan plus top of wall elevations,
adjacent finished surface elevations, top of footing elevations, provide a cross
section detail showing subdrain design, indicate drainage outlet for all retaining
walls. Retaining walls are not a part of the grading permit. Submit for separate
building permits; show connection of subdrain to storm drain. Note on plans.
8 J) Show existing and proposed elevations using contours and/or spot elevations.
9 N) Show all easements, (i.e. drainage, utilities, etc.).
10 O) Extend existing contours or spot elevations to reflect off-site areas and identify
drainage patterns.
11 Q) Approved erosion control measures are to be installed and functional during
the rainy season from October 15 to April 15. Justify design with hydrology and
hydraulic calculations. Submit three (3) copies of an erosion control plan and a
Page 3 of 5 8/9/2005 4:08 PM = Indicates line item not Cleared.
GB050096
Grading Plan Check Corrections
Sheet Comments
cost summary of erosion control facilities. If proposed grading will take place
after April 15, continue to show erosion control plans. Grading may extend into
the next rainy season. Use proper BMPs; show location & details on plans.
12 R) Show detail on plan how finished grades meet adjoining property.
13 S) Show on title sheet of plans name, address, and telephone number of:
13.1 Soil Engineer
13.2 Engineering Geologist
14 T) Show benchmark and basis of bearing (reference based on Orange County Surveyor
vertical datum and recorded map or survey, respectively).
15 U) Show percent grade of all driveways (first 18 ft).
16 W) Additional comments may be made after field verification that the plans and
soils report accurately reflects existing conditions.
17 Y) The grading concept proposed appears to require a separate Site Development
Permit. Verify with Current Planning at Station 1, Room 122. If not required,
please provide name of Planner at Station 1, who made the determination and date
of determination.
18 Z) Show location of sump pump on the grading plan. (Provide Brochure). An electrical
and plumbing permit must be obtained from the Building Permits Division.
Drainage Instructions
19 B) Submit a hydrology study and/or hydraulic calculations for this project.
20 I) Minimum, acceptable gradients:
20.1 Earth 1.00%
21 J) Show plan and section details of typical lot drainage. Minimum 2%, maximum
21% away from a building pad to a swale is required.
22 M) Show limits of roof gutters and location of downspouts (if discharged onto
A.C. paving or onto a finished grade, a P.C.C. splash block is required).
23 Q) Show the approved non-erosive device where concentrated drainage exceeds 4%
gradient. Use concrete, gunite, or other approved materials.
Page 4 of 5 8/9/2005 4:08 PM = Indicates line item not Cleared.
GB050096
Grading Plan Check Corrections
Sheet Comments
24 T) Show detail and locations of extra depth footings.
25 V) Show flow line elevations of all swales and other drainage devices.
26 W) Show retaining wall subdrain details with disposal points, flow line elevations
and pipe material.
27 X) Show typical section of driveway and pavement section. Include type of surfacing
material.
28 Y) Show typical section of hardscape. Include type of surfacing material.
Slopes
29 H) Show top and toe of cut and fill slopes (as applicable).
Geotechnical
30 A) Obtain approval of soils and geology report by County Geotechnical staff.
Reports have been forwarded for their review.