`q44:09 City Council Staff Report
April 23, 2024
Agenda Item No. 7
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Andy Tran, Senior Civil Engineer - 949-644-3315,
atran@newportbeachca.gov
TITLE: Concrete Replacement Program FY 2023-24 (Project No. 24R06) —
Notice of Completion for Contract No. 9378-1
On September 26, 2023, the City Council awarded Contract No. 9378-1 for the Concrete
Replacement Program Fiscal Year 2023-24 project to Grigolla & Sons Construction
Company, Inc. of San Dimas. The project replaced deteriorated concrete sidewalks,
driveways, curbs and gutters, and access ramps in the Mariners and Dover Shores
neighborhoods. The work is now complete and staff requests City Council acceptance
and close out of the contract.
RECOMMENDATIONS:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project;
b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the
Notice of Completion has been recorded in accordance with applicable portions of
Civil Code; and
c) Release Faithful Performance Bond one year after acceptance by the City Council.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded Contract
Final Total Contract
Total Contract
Percent Contract
Amount
Amount
Change Amount
Cost Change
$989,250
$1,189,244
$199,994
20.2%
Allowed Contract Time + Approved
85
Actual Time Used (Days)
73
Extensions (Days) _
7-1
Concrete Replacement Program FY 2023-24 (Project No. 24R06) —
Notice of Completion for Contract No. 9378-1 April 23, 2024
Page 2
This project included replacing deteriorated concrete sidewalks, driveways, curbs and
gutters, and access ramps in the Mariners and Drover Shores neighborhoods. Final
concrete pavement restoration work related to the Balboa Boulevard Utility
Undergrounding project (UUD-22 Phase 2) was included with this contract.
The work has been completed to the satisfaction of the Public Works Department.
A summary of the construction cost is as follows:
Original Bid Amount:
$
989,250
Actual Cost of Bid Items Constructed:
$
939,850
Total Change Orders:
$
249,394
Final Contract Cost:
$
1,189,244
The final total contract amount was $1,189,244, which was approximately 20.2% higher
than the original bid amount. This cost increase was primarily due to additional concrete
work needed on the Balboa Boulevard Utility Undergrounding project, which was paid for
by the utility companies involved. Staff also added some concrete replacement work to
improve the condition of the public walkways within the Mariners and Dover Shores
neighborhoods.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule October 16, 2023
Actual Start of Construction Per Notice to Proceed November 13, 2023
Extended Contract Completion Date Inclusive of Extra Work April 16, 2024
Actual Substantial Construction Completion Date March 29, 2024
The contractor was able to complete all the proposed improvements, including the change
order work, ahead of schedule despite multiple rain events throughout winter and spring.
FISCAL IMPACT:
The Concrete Replacement Program FY 2023-24 was included within the FY 2023-24
Capital Improvement Program Budget. Funds for the construction contract were
expended from the following accounts:
Account Description
General Fund
General Fund
Utilities Contribution Fund
Water Capital Fund
Account Number
01201927-980000-24R06
01201927-980000-23R06
13501-980000-21 A11
70201-980000-24R09
Total:
Amount
$
1,045,551
$
8,244
$
124,199
$
11,250
$ 1,189,244
The Water Capital Fund is generated from water rate charges and was used to replace
water valve boxes and meter boxes for the Balboa Boulevard Utility Undergrounding
work.
7-2
Concrete Replacement Program FY 2023-24 (Project No. 24R06) —
Notice of Completion for Contract No. 9378-1 April 23, 2024
Page 3
ENVIRONMENTAL REVIEW:
On September 26, 2023, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Section 15301(c), Class 1 (maintenance
of existing public facilities involving negligible or no expansion of use) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
7-3
ATTACHMENT A
JOHN WAYNE
AIRPORT
NOT TO SCALE
CONCRETE REPLACEMENT PROGRAM
FY 2023-24
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C-9378-1 1 4/23/2024