RESIDENTIAL
FIRE SPRINKLER NFPA 13D SYSTEM
FINAL CHECKLIST
FAIL
PASS
1.
Fire sprinkler system installed per the approved plans
❑
2.
Proper sprinkler head spacing
❑
I
3.
All construction covers removed from sprinkler heads
❑
e,
4.
All tape and paint removed from sprinkler heads
❑
5.
Finish trim installed around sprinkler heads
11
6.
Proper type of sprinkler heads installed at each location.
❑
7.
Proper signage posted at all required locations
❑
8.
Alarms tested���.}'p��
9.
Location of inspector's testing valve in approved location
SYSTEMS
10.
Clearances around sprinkler heads and riser - no obstructions
❑
C
11.
Fire alarm (bell) installed at proper locations
❑
[�
12.
Proper clearance around sprinkler heads at acoustical panels
❑
L
13.
Operating pressure gauge installed and pressure verified
14.
Back flow preventer installed
❑
I'
15.
System installed per manufacturers specifications
❑
NOTES:
—
--
FIRE SPRINKLER FINAL APPROVED:
/ PERMIT#:y35
BY: DATE: _ �`Z6 -13 ---
Forms\ Fire Sprinkler NFPA 13D System -FINAL Checklist RESIDENTIAL S-12
CITY OF NEWPORT BEACH
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING DIVISION
3300 Newport Boulevard I P.O. Box 1768 1 Newport Beach, CA 92658
www.newportbeachca.gov 1 (949) 644-3275
FIRE SPRINKLER NFPA 13D SYSTEM
ROUGH INSPECTION CHECKLIST
FAIL
PASS
1. Riser Construction and Location Approval
a. Drain valve
❑
b. Backflow device (single check)
❑
c. Alarm activation device
❑
d. Inspector's test valve
❑
C"
2. Pressure Test
hours
U
a. System tested at operating pressure for 2
b. Pressure gauge installed
❑
r'
3. Sprinkler Heads (Installed per plans)
a. Correct head type installed
❑
b. Installation and spacing of sprinkler heads
❑
lzr�
c. Field changes to approved plans
❑
d. Field changes require review and new calculations
❑
4. Pi in
a. Material installed per plan
❑
[4--
b. Hangers per codes/prevent upward movement
❑
ra'�
c. All CPVC piping shall be installed by persons who have been
❑
certified by the manufacturer for installation of CPVC piping
d. Piping protected from damage
❑
e. Water meter proper size
����
C
I..�
5. Alarms
a. Wiring installed per code
❑
b. Boxes installed at proper locations
❑
NOTE: CPVC plastic pipe in the garage shall not be exposed unless it is installed above
a smooth, flat,
horizontal ceiling. Sprinklers that are listed as "Quick Response" or "Residential"
must be used.
CORRECTIONS AND NOTES:
FIRE SPRINK GH INSPECTION APPROVED: _
PERMIT #: rZn2 '"D 3S
By. DATE: ���7 2