`q44:09 City Council Staff Report
February 25, 2025
Agenda Item No. 6
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Andy Tran, Principal Civil Engineer - 949-644-3315,
atran@newportbeachca.gov
TITLE: Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot (Project
No. 15T09) — Notice of Completion for Contract No. 8020-6
h\ 33 d:7±Tip 6
On November 29, 2022, the City Council awarded Contract No. 8020-6 for the Superior
Avenue Pedestrian/Bicycle Bridge and Sunset View Park Parking Lot project to
Reyes Construction, Inc. The project involved construction of a new pedestrian/bicycle
bridge across Superior Avenue, expansion of Sunset View Park, and construction of a
larger parking lot at the intersection of Superior Avenue and Pacific Coast Highway
(PCH). The work is now complete and staff requests City Council acceptance and close
out of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded Contract
Final Total Contract
Total Contract
Percent Contract
Amount
Amount
Change Amount
Cost Change
$10,518,759.00
$11,431,428.94
$912,669.94
8.7%
Allowed Contract Time +
422
Actual Time Used (Days)
422
Approved Extensions (Days) _
This project included the construction of a new pedestrian/bicycle bridge across
Superior Avenue, expansion of Sunset View Park with additional landscaping and grass
area, and construction of a larger parking lot at the intersection of Superior Avenue and
PCH.
6-1
Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot —
Notice of Completion for Contract No. 8020-6
February 25, 2025
Page 2
The new pedestrian/bicycle bridge and larger parking lot have improved pedestrian and
cyclist access and safety for visitors to both Sunset Ridge and Sunset View Parks.
The contracted work has been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount:
$
10,518,759.00
Actual Cost of Bid Items Constructed:
$
10,473,726.01
Total Change Orders:
$
957,702.93
Final Contract Cost:
$
11,431,428.94
The final total contract amount was $11,431,428.94, which was approximately 8.7%
higher than the original bid amount. This cost increase was primarily due to unforeseen
poor soil conditions, which required modifications to the retaining wall design and a
significant amount of additional earthwork and foundation work. Several other smaller
change order items were related to excessive groundwater seepage and unforeseen
existing underground utilities.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule
February 27, 2023
Actual Start of Construction Per Notice to Proceed
January 23, 2023
Estimated Completion per Annual Baseline Schedule
November 30, 2024
Substantial Completion Date Inclusive of Extra Work
September 27, 2024
The contract time was extended to account for the additional time needed to complete
change order work. In addition, there was a total of 25 inclement weather days, which
delayed the project completion date.
FISCAL IMPACT:
The Superior Avenue Pedestrian/Bicycle Bridge and Sunset View Park Parking Lot
project was included within the FY 2022-23 Capital Improvement Program Budget. Funds
for the construction contract were expended from the following accounts:
Account Description
Bicycle Corridor Improvement Program
(BCIP) Federal Grant
Transportation and Circulation
Facilities Financing Plan (FFP):
Parks/Community Centers
Account Number Amount
13501-980000-15T09 $ 2,349,600.00
14001-980000-15T09 $ 2,943,600.00
56201-980000-15T09 $ 6,138,228.94
Total: $ 11,431,428.94
The BCIP is a funding program administered by the Orange County Transportation
Authority for bicycle and pedestrian projects that reduce traffic congestion and improve
air quality. The City received Congestion Mitigation and Air Quality federal funds for this
project under the BCIP.
6-2
Superior Avenue Pedestrian/Bicycle Bridge and Parking Lot —
Notice of Completion for Contract No. 8020-6
February 25, 2025
Page 3
Transportation and Circulation funds are fair share revenues collected from developers
for capital improvement projects meeting the circulation element of the City's
General Plan. The FFP, funded by the General Fund and development agreement
contributions, was created to allow for the construction and rehabilitation of City facilities.
ENVIRONMENTAL REVIEW:
On November 29, 2022, the City Council found the requirements for environmental review
under the California Environmental Quality Act (CEQA) was satisfied by the
November 19, 2019 City Council adoption of Resolution No. 2019-102, A Resolution of
the City Council of the City of Newport Beach, California, Adopting Mitigated Negative
Declaration No. ND2019-002 (SCH# 2019099074) for the Superior Avenue Pedestrian
and Bicycle Bridge and Parking Lot Project (PA2019-014), including the Mitigation
Monitoring and Reporting Program, pursuant to CEQA Guidelines and City Council
Policy K-3.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
6-3
ATTACHMENT A
\
\ NEWPORT
SUNSET RIDGE PARK \ CREST
ADDITIONAL
PUBLIC PARKING
VILLA
BALBOA
/-Z
C1 SUNSET I _
PAR
LIDO SUNSET VIEW
SANDS \ PARK EXPANSION
P4C
/F/L, L'�"F HOAG HOSPITAL
As% \ .: LOWER CAMPUS
R w Hwy
\ VILLAGE SHOPPING
O CENTER41
JACK IN
/ 4 THE BOX
SUPERIOR AVENUE PEDESTRIAN/BICYCLE CITY OF NEWPORT BEACH
BRIDGE AND PARKING LOT PUBLIC WORKS DEPARTMENT
ATTACHMENT A - LOCATION MAP C-8020-6 1 2/11/2025