`q44:09 City Council Staff Report
March 11, 2025
Agenda Item No. 8
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
PREPARED BY: Tom Sandefur, Assistant City Engineer - 949-644-3321,
tandefur@newportbeachca.gov
TITLE: Newport Beach Police Station Video Surveillance System
Replacement (Project No. 24F02) - Notice of Completion for Contract
No. 9500-1
ABSTRACT -
On July 9, 2024, the City Council awarded Contract No. 9500-1 for the Newport Beach
Police Station Video Surveillance System Replacement project to Vector Resources Inc.,
DBA Vector USA (Vector). The project included removing and replacing the existing video
surveillance system and providing new computers and monitors in the jail and Watch
Commander's office. The work is now complete and staff requests City Council
acceptance and close out of the contract.
RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion
for the project.
DISCUSSION:
Overall Contract Cost/Time Summary
Awarded Contract
Final Total Contract
Total Contract
Percent Contract
Amount
Amount
Change Amount
Cost Change
$318,370.44
$321,905.44
$3,535.00
1.1 %
Allowed Contract Time +
Approved Extensions (Days) -
60
Actual Time Used (Days)
57
This project included providing submittals; completing employee background verification;
removing and replacing the existing video surveillance system; providing new computers
and monitors in the jail and Watch Commander's office; installing a new server rack;
providing video management software (VMS) and software licenses; putting in new wiring
and completing close out documents.
8-1
Newport Beach Police Station Video Surveillance System Replacement —
Notice of Completion for Contract No. 9500-14
March 11, 2025
Page 2
The contracted work has been completed to the satisfaction of the Public Works
Department. A summary of the construction cost is as follows:
Original Bid Amount:
$
318,370.44
Actual Cost of Bid Items Constructed:
$
318,370.44
Total Change Orders:
$
3,535.00
Final contract cost:
$
321,905.44
The final total contract amount was $321,905.44, which was approximately 1.1 % higher
than the original bid amount. A single change order was issued totaling $3,535.00 that
included providing additional cameras and cabling in the jail and property storage areas.
A summary of the project schedule milestones is as follows:
Estimated Start of Construction per Annual Baseline Schedule
October 10, 2024
Actual Start of Construction Per Notice to Proceed
November 4, 2024
Estimated Completion per Annual Baseline Schedule
December 6, 2024
Substantial Completion Date Inclusive of Extra Work
January 28, 2025
FISCAL IMPACT:
The Police Station Video Surveillance System Replacement project was expensed from
Fiscal Years 2022-23 and 2023-24 Police Department salary savings. Funds for the
construction contract were expended from the following account:
Account Description Account Number
Police Department Staff Savings 0103522-911024-PDCAM
Total:
ENVIRONMENTAL REVIEW:
Amount
$ 321,905.44
$ 321,905.44
On July 9, 2024, the City Council found this project exempt from the California
Environmental Quality Act (CEQA) pursuant to Class 1 Section 15301(a) (interior or exterior
renovations involving such things as interior partitions, plumbing, and electrical conveyances)
of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it
has no potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
ATTACHMENT:
Attachment A — Location Map
8-2
ATTACHMENT A
Newport Beach Police Station
Video Surveillance System
Replacement
a
NOT TO SCALE
. =FZZZA00 OZ19A
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
LOCATION MAP
C-9500-1 3/11/2025