HomeMy WebLinkAboutW_5210_S• 1201122 GENERAL CITY OF NEWPORT BEACH -BUILDING DEPARTMENT GENERAL GRADING SPECIFICATIONS 1. ALL WORK SHALL CONFORM TO CHAPIER 15 OF THE NEWPORT BEACH MUNICIPAL CODE (NBMC), THE PROJECT SOILS REPORT AND SPECIAL REQUIREMENTS OF THE PERMIT. 2. DUST SHALL BE CONTROLLED BY WATERING AND/OR DUST PALLIATIVE. 3. SANITARY FACILITIES SHAIL BE MAINT~D ON THE SITE DURING THE CONSTRUCTION PERIOD. 4. WORK HOURS ARE LIMITED FROM 7:00 AM TO 6:30 PM MONDAY THROUGH FRIDAY;8:00AMT06:00PMSATURDAYS;AND IJO W=. Ol,l SUNDAYS AND HOUDA YS PER SECTION 10-28 OF THE NBMC. 5, NOISE, EXCAVATION, DELIVERY AND REMOVAL SHALL BE CONTROLLED PER SECTION 10-28 OF THE NBMC. 6. THE STAMPED SET OF APPROVED PLANS SHALL BE ON THE JOB SITE AT ALL TIMES. 7. PERMITIEE AND CONTRACTOR ARE RESPONSIBLE FOR LOCATING AND ' PROTECTING UTILl11ES. 8. APPROVED DRAINAGE PROVISIONS AND PROTECTIVE MEASURES MUST BE USED TO PROTECT ADJOINING PROPERTIES DURING THE GRADING OPERATION. 9. CESSPOOLS AND SEPTIC TANKS SHALL BE ABANDONED IN COMPLIANCE WITH THE UNIFORM PLUMBING CODE AND APPROVED BY THE BUILDING OFFICIAL 10. HAUL ROUTES FOR IMPORT OR EXPORT OF MATERIALS SHALL BE APPROVED BY THE CITY TRAFFIC ENGINEER AND PROCEDURES SHALL CONFORM WITH CHAPTER 15 OF THE NBMC. 11. POSITIVE DRAINAGE SHALL BE MAINTAINED AWAY FROM ALL BUILD!l/G AND SLOPE AREAS. 12. FAILURE TO REQUEST INSPECTIONS AND/OR HA VE REMOVABLE EROSION CONTROL DEVICES ON-SITE AT THE APPROPRIATE TIMES SHALL RESULT IN FORFEITURE OF THE CONSTRUCTION SITE CLEANUP DEPOSIT. 13. ALL PLASTIC DRAINAGE PIPE SHALL CONSIST OF PVC OR ABS PLASTIC AND EI1HER ASTM 2751, ASTM D1S27, ASTM D3034 OR ASTM D1785. EROSION CONIROL 1. TEMPORARY EROSION CONTROL PLANS ARE REQUIRED FROM OCTOBER 15 TO MAY 15. 2. EROSION CONTROL DEVICES SHALL BE AVAILABLE ON-SITE BETWEEN OCTOBER 15 AND MAY 15. 3. BETWEEN OCTOBER 15 AND MAY IS, EROSION CONTROL MEASURES SHALL BE IN PLACE AT THE END OF EACH WORKING DAY WHENEVER THE FIVE- DAY PROBABILITY OF RAIN EXCEEDS 30 PERCENT. DURING THE REMAINDER OF THE YEAR, TilEY SHALL BE IN PLACE AT THE END OF THE WORKING DAY WHENEVER TilE DAILY RAINFALL PROBABILITY EXCEEDS SO PERCENT. 4. LANDSCAPING PLANS SHALL BE SUBMITTED FOR APPROVAL, WORK COMPLETED AND A CERTIFICATE OF CONFORMANCE RECEIVED BY THE CITY GRADING ENGINEER PRIOR TO CLOSURE OF PERMIT, UNLESS WAIVED BY THE CITY GRADING ENGINEER. 5. TEMPORARY DESILTING BASINS, WHEN REQUIRED, SHALL BE INSTALLED AND MAINTAINED FOR TilE DURATION OF THE PROJECT, REQUIRED INSPECTIONS !. A PRE-GRADING MEETING SHALL BE SCHEDULED 48 HOURS PRIOR TO START OF GRADING WITH THE FOLLOWING PEOPLE PRESENT: OWNER, GRADING CONTRACTOR, DESIGN CIVIL ENGINEER, SOILS ENGINEER, GEOLOGIST. CITY GRADING ENGINEER OR THEIR REPRESENTATIVES. REQUIRED FIELD INSPECTIONS WILL BE OUJLINED AT THE MEETING. 2. APRE-PAVINGMEETINGSHALLBESCHEDULED48HOURSTOSTARTOFTHE SUB-GRADEPREPARATIONFOR THE PA YING WITHTHEFOLLOWING PEOPLE PRESENT: OWNER, PA YING CONTRACTOR, DESIGN CIVIL ENGINEER, SOILS ENGINEER, CITY GRADING ENGINEER OR THEJR REPRESENTATIVES. REQUIRED FIELD INSPECTIONS WILL BE OUJLINED AT TilE MEETING. GRADING FIUS/ClITS I. GRADED SLOPES SHALL BE NO STEEPER TilAN 2 HORIZONTAL TO 1 VERTICAL 2. FILL SLOPES SHALL BE COMPACTED TO NO LESS TilAN 90 PERCENT RELATIVE COMPACTION OUT TO THE FINISHED SURFACE. 3. ALL FILLS SHALL BE COMPACTED THROUGHOUT TO A MINIMUM OF 90 PERCENTREIATIVECOMPACTIONASDETERMINEDBYASTMTESTMETilOD 15S7, AND APPROVED BY TilE SOILS ENGINEER. COMPACTION TESTS SHALL BE PERFORMED APPROXIMATELY EVERY TWO FEET IN VERTICAL HEIGHT ANDORSUFFIC!ENTQUANTITYTOATTESTTOTHEOVERALLCOMPACTION EFFORT APPLIED TO THE FILL AREAS. 4. AREAS TO RECEIVE FILL SHALL BE CLEARED OF ALL VEGETATION AND DEBRIS, SCARIFIED AND APPROVED BY THE SOILS ENGINEER PRIOR TO PLACING OF THE FILL 5, FILLS SHALL BE KEYED OR BENCHED INTO COMPETENT MATERIAL 6. ALL EXISTING FIILS SHALL BE APPROVED BY THE SOILS ENGINEER OR • REMOVED BEFORE ANY ADDffiONAL FIILS ARE ADDED. 7. ANY EXISTING IRRIGATION LINES AND □STERNS SHALL BE REMOVED, OR CRUSHED IN PIACE AND BACKFILLED, AND APPROVED BY THE SOILS ENGINEER. 8. THE ENGINEERING GEOLOGIST AND SOILS ENGINEER SHALL, AFTER CLEARING AND PRIOR TO THE PLACEMENT OF FILL IN CANYONS, INSPECT EACH CANYON FOR AREAS OF ADVERSE STABILITY AND DETERMINE THE PRESENCE OF, OR POSSIBILITY OF FUTURE ACCUMULATION OF, SUBSURFACE WATER OR SPRING FLOW. IF NEEDED, DRAINS WILL BE DESIGNEDANDCONSTRUCTEDPRIORTOTilEPLACEMENTOFFILLINEACH RESPECTIVE CANYON. 9. TilE EXACT LOCATION OF THE SUBDRAINS SHALL BE SURVEYED IN THE FIELD FOR LINE AND GRADE. 10. ALL TRENCH BACKFILLS SHALL BE COMPACTED TilROUGHOUT TO A MINIMUM OF 90 PERCENT RELATIVE COMPACTION, AND APPROVED BY THE SOILS ENGINEER. TilE BUILDING DEPARTMENT MAY REQUIRE CORING OF CONCRETE FIAT WORK PIACED OVER UNTESTED BACKFILLS TO FACILIT,\TE TESTING. JOB ADDRESS CITY OF NEWPORT BEACH UTILITIES DEPARTMENT .. "-411 AVOCADO ST. NEWPORT BEACH, CALIF. LEGAL DESCRIPTION: LOT "I 18'!, TRACT # 2813 NEWPOR I BEACH OWNER/DEVELOPER BYERLY RESIDENCE 411 AVOCADO ST. NEWPORT BEACH, CALIF. (114-) G,j"::,-.,1~ APPROVED 3111" R.C.E. NO. SOILS ENGINEER ~-F-lf<M. 60 I GL.a.\%~ '7-r- lJ,.G.\}l,.\,1>,... ~,b,.C\J., ~ "l'l.~1'7 ~ .... -. ~ \..-/>,.~~ (114) ~4-1-Z l'Z 11. THESTOCKPILINGOFEXCESSMATERIALSHALLBEAPPROVEDBYTilEOTY GRADING ENGINEER. 12. LANDSCAPING OF ALL SLOPES AND PADS SHALL BE IN ACCORDANCE WITH CHAPIER 15 OF THE NBMC. 13. ALL CUT SLOPES SHALL BE INVFSllGATED BOTH DURING AND AFTER GRADING BY AN ENGINEERING GEOLOGIST TO DETERMINE IF ANY STABILITY PROBLEM EXISTS. SHOULD EXCAVATION DISCLOSE ANY GEOLOGICAL HAZARDS OR POTENTIAL GEOLOGICAL HAZARDS, TilE ENGINEERING GEOLOGIST SHALL RECOMMEND AND SUBMIT NECESSARY TREATMENT TO THE OTY GRADING ENGINEER FOR APPROVAL 14. WHERE SUPPORT OR BUTIRESSING OF CUT AND NATURAL SLOPES JS DETERMINED TO BE NECESSARY BY THE ENGINEERING GEOLOGIST AND SOILS ENGINEER, TilESOILS ENGINEER WILL OBTAJN APPROVAL OF DESIGN, LOCATIONANDCALCULATIONSFROMTilECITYGRADINGENGINEERPRIOR TO CONSTRUCTION. 15. THE ENGINEERING GEOLOGIST AND SOILS ENGINEER SHALL INSPECT AND TEST THE CONSTRUCTION OF ALL BUTTRESS FILLS AND ATTEST TO THE STABILITYOFTHE SLOPEANDADJACENTSTRUCTURESUPONCOMPLETION. 16. WHEN CUT PADS ARE BROUGIIT TO NEAR GRADE THE ENGINEERING GEOLOGIST SHALL DETERMINE IF THE BEDROCK JS EXTENSIVELY FRACTURED OR FAULTED AND WILL READILY TRANSMIT WATER. IF CONSIDERED NECESSARY BY TilE ENGINEERING GEOLOGIST AND SOILS ENGINEER, A COMPACTED FILL BLANKET WILL BE PLACED. 17. THE ENGINEERING GEOLOGIST SHALL PERFORM PERIODIC INSPECTIONS DURING GRADING. 18. NOTIFICATION OF NONCOMPLIANCE: IF, IN THE COURSE OF FULFILLING THEIR RESPONSIBILITY, THE □VIL ENGINEER, THE SOILS ENGINEER, TilE ENGINEERING GEOLOGIST OR THE TESTING AGENCY FINDS THAT TilE WORK IS NOT BEING DONE IN CONFORMANCE WITH THE APPROVED GRADING PLANS, THE DISCREPANOES SHALL BE REPORTED IMMEDIATELY IN WRITING TO THE PERSON IN CHARGE OF THE GRADING WORK AND TO THE OTY GRADING ENGINEER. RECOMMENDATIONS FOR CORRECTIVE MEASURES IF NECESSARY, SHALL BE SUBMITTED TO THE CITY GRADING ENGINEER FOR APPROVAL POCUMENJ'ATION 1. ANAS-BUILTGRADINGPLANSHALLBEPREPAREDBYTHECIVILENGINEER INCLUDING ORIGINAL GROUND SURFACE ELEVATIONS, AS-GRADED GROUND SURFACE ELEVATIONS, LOT DRAINAGE PATTERNS AND LOCATIONS, AND ELEVATIONS OF ALL SURFACE AND SUB-SURFACE DRAINAGE FACJLmES. HE SHALL PROVIDE WRITTEN APPROVAL THATTilE WORK WAS DONE IN ACCORDANCE WITH THE FINAL APPROVED GRADING PLAN AND STATE THE NUMBER OF YARDS OF CUT AND/OR FILL MOVED DURING THE OPERATION. 2. ASOILS GRADING REPORTPREPAREDBYTHESOILS ENGINEER, INCLUDING LOCATIONS AND ELEVATION OF FIELD DENSITY TESTS, SUMMARIES OF FIELDANDLABORATORYRESULTSANDOTHERSUBSTANTIATEDDATAAND COMMENTSONANYCHANGESMADEDURINGGRADINGANDTHEIREFFECT ON THE RECOMMENDATIONS MADE IN THE SOILS ENGINEERING INVFSllGATION REPORT. HE SHALL PROVIDE WRITTEN APPROVAL AS TO THE ADEQUACY OF THE SITE FOR THE INTENDED USE AND COMPLETION OF WORK IN ACCORDANCE WITH TilE NBMC. 3. A GEOLOGIC GRADING REPORT PREPARED BY THE ENGINEERING GEOLOGIST, INCLUDING A FINAL DESCRIPTION OF THE GEOLOGY OF THE SITE, INCLUDING ANY NEW INFORMATION DISCLOSED DURING THE GRADING AND THE EFFECT OF SAME ON RECOMMENDATIONS INCORPORATED IN TilE APPROVED GRADING PLAN. HE SHALL PROVIDE WRITTEN APPROVAL AS TO THE ADEQUACY OF THE SITE FOR THE INTENDED USE AS AFFECTED BY GEOLOGIC FACTORS. EROSION CONTROL SPEOFICATIONS 1. ALL WORK SHALL BE IN ACCORDANCE WITH THE GRADING CODE OF THE CITYOFNEWPORTBEACH,THERECOMMENDATIONSOFTHEPROJECTSOILS REPORT AND ANY SPECIAL REQUIREMENTS OF THE PERMIT, 2. TEMPORARY EROSION CONTROL PLANS ARE REQUIRED FROM OCTOBER 15 TO MAY 15. 3. BETWEEN OCTOBER 15 AND MAY IS, EROSION CONTROL MEASURES SHALL BE IN PLACE AT THE END OF EACH WORKING DAY WHENEVER THE FIVE- DAY PROBABILITY OF RAIN EXCEEDS 30%. DURING THE REMAINDER OF THE YEAR, THEY SHALL BE IN PIACE AT THE END OF THE WORKING DAY WHENEVER TilE DAILY RAINFALL PROBABILITY EXCEEDS 50%. 4. A STAND-BY CREW FOR EMERGENCY WORK SHALL BE AVAILABLE AT ALL TIMES DURING TilE RAINY SEASON. NECESSARY MATERIALS SHALL BE AVAILABLE ON-SITE AND STOCKPILED AT CONVENIENT LOCATIONS TO FAOLITATE RAPID CONSTRUCTION OF TEMPORARY DEVICES WHEN RAIN IS IMMINENT. 5. DEVICESSHALLNOTBEMOVED ORMODIFIEDWITHOUTTHEAPPROVALOF THE BUILDING DEPARTMENT. 6. ALL DESILTING BASINS SHALL BE CLEARED OF SILT, AS NEEDED, TO PROVIDETHENECESSARYVOLUMETRICCAPAOTY,ANDSTANDINGWATER, TURBID-FREE OF SILT, SHALL BE PUMPED OUT OF THE BASINS TO ASSIST IN KEEPING THE VOLUMETRIC CAPACITY AND ASSISTING IN SILT REMOVAL 7. ALLSLOPESATTHETRACTPERIMETERSHALLDRAINAWAYFROMTHETOP OF SLOPE AT TilE CONCLUSION OF EACH WORKING DAY. 8. A GUARD WILL BE POSTED AND/OR AN ENCLOSURE ESTABLISHED WHENEVER THE DEPTil OF WATER IN ANY DEVICE EXCEEDS TWO FEET. 9. PLACEMENT OF DEVICES TO REDUCEEROSIONDAMAGEWITHINTHETRACT IS LEFT TO THE DISCRETION OF TilE ENGINEER THESE DEVICES, IF ANY, MUST SHOW ON THE PLAN BECAUSE THEIR PRESENCE WILL AFFECT TilE REQUIRED CAPACITY OF TilE DESILTING BASIN . 10. OUTLET CONDffiONS ARE NOT TO EXCEED DOWNSTREAM LIMITATIONS, WITilEXCEPTIONOFOVERFLOWWHICHISTOPROVIDECAPACITYOFl.SQ. 11. IF EROSION CONTROL PROBLEMS OCCUR THEDEVELOPERSHALLCORRECT THE CONDmON IMMEDIATELY PRIOR TO RECEIVING A CORRECTION NOTICE FROM THE CITY GRADING ENGINEER, BUT IF A NOTICE IS ISSUED AND THE EROSION PROBLEM IS NOT CORRECTED THE DEBRIS DEPOSIT SHALL BE FORFEITED AND ALL CONSTRUCTION WORK SHALL BE STOPPED UNTIL THE PROBLEM IS CORRECTED AND A NEW DEPOSIT IS RECEIVED BY THE CITY. 12. THE DEVELOPER AND THE □VIL ENGINEER SHALL REVIEW AND COORDINATE OIANGES IN THE EROSION CONTROL SYSTEM AS THE TOPOGRAPHY DICTATES DURINO THE GRADING PHASE. 13. THE STANDARDS TO BE USED IN DESIGNING THE VOLUMETRIC CAPACITY OF DESILTING BASINS CONSISTS OF: !. UNIVERSAL SOIL LOSS EQUATION FOR SILT LOAD. 2. RATIONAL FORMULA FOR WATER LOAD. 3. 25-YEAR STORM. 4, OVERFLOW DESIGNED FOR 1.5 MAXIMUM Q. • PROJECT VICINITY MAP N.T.S. '-........ ' ( : I ' I 179 180 183 BAYSIDE 184 PROJECT SITE LOCATION MAP TPP e,= Citti.19 {T.'9.) ei,.e.11, PP: ru-u N.T.S. DlfA\IJ Plflt / ...:. ... . -~~' i·, ... ;,r. . ,)a .;."' '• :, .. s ..... • 7:.-" ;,,w.· .'1 ·--.,, ~-,-. =~ ·--1===-·- • .. ' .. . . ' -· .:. ,.., "'"; ' 7 47 ,.. ,.. / / ,.. / 185 ------ 11,1.111/E' """L-e.r-CIQ<IU... Ill <;I:> ~ C'<OM~OIJ • 14. IN CASE OF EMERGENCY, CALL t./1~ ~'r°OC>t:l!:IZ. ("IJl.)'-11;,#"llec (Re.1ponsible PersonJ (24 Hour Phone No.) JS. THE UNDERSIGNED □VIL ENGINEER WILL ~~ EROSION CONTROL WORK AND VERIFY THAT WORK IS IN ACCORDANCE WITH THE APPROVED PLANS. Atl.EA. ~w e,e\MIJ6:ii OE j.J\.u ... M.T.'J7. (s?.,~fJJ£¥ (Date) BENCH MARK O.C.S. BENCH MARK DESIGNATION NB4·4I-82 LEVELED ON I982j ELEV, =9.896. FROM THE INTERSECTION OF BAYSIDE DR. ANt.1 THE ENTRANCE ROAD TO THE HARBOR DEPT. AND US. COAST GUARD GROUNDS GO APPROXIMATELY 0.2 Ml'r,ES SE'LY ALONG BAYSIDE DR. TO HOUSE ~2137· 17.2 FT. SW LY OF THE CENTER-LINE OF BAYSIDE pR.; 48.B FT. SE'LY OF STREET LIGHT POLE #61; 24.0 FT, SE LY OF THE CENTERLINE OF THE CONCRETE DRIVEWAY TO HOUSE ~ 2137; SET IN THE NE CORNER OF THE TOP OF A 7.4 FT. X 3.3 FT. CONCRETE CATCH BASIN. UNDERGROUND STRUCTURES ALL UNDERGROUND UTILITIES OR BTRUCTU"U REl'ORTED D'I' THE OWNU! 011 OTHrt• AND THOSlli: SHOWN ON Tl-Iii: RECO"DS EX.O.MINEO ARE INDICATED WITH THEIR A-RO)UMATE LOCATIOl4 "HO EXT'ENT THE OWNER 11'1' ACCEPTING THESE PLANS OR PR0CE£01N0 WITH IMPRO\/EloOENTS PURo;:UAN'I' 'l'Ml:RE'l'O ACR[Ui TO ASSUME LTAIIILl'l''I' AND '1'0 HOLD UNDER· lllGHEO '"'"RM1-ESS FCR ,.,. .. """'"CEii RESV1-TING F"ROM THE EXISTENCI. or UNOERGROUNO UTr1-ITlli:S OR STRUCTURES NOT Rli"ORTl:0 TO '!'HE UNDERSIGNED NOT ll'IOIC.0.TED ON 'T'HE l'Ulll IC RECORDS El(,.MIN£D LOCATED AT 1/ARl,.NCI: WITH TMAT Rli:l'ORTED OR SHOWN 011 R£COROS CXAMINEC THE CONT"A,-.TOR IS RUlU1Rt;g TO T,.KE DUI: l'RECAU'l'lONARY ,.£.SUll:ES TO PROTECT THE UTIUTIES 0~ STRUCTURES ISHOWN ,.,-g .0.HY OTHER UTJLITlll:15 011: ST .. UCTVRES FOUND AT THE SITE IT SMAL1-11£ '!'HE CON'l'RACTOR'■ IIUPONSl■ILl'TY TO NOTrFY THC ow,.ER9 OF" nu UTIUTJES OR ISTRUCTUR[S CONCERNED ■11:F"ORII: ■TA'ITING WORK NOTICE TO CONTRACTOR Con11truction contractor agree.<1 that m accordance with generally acrepted construction practices, construction contr11c1or will be required to assume sole and complete responsibility for Job site conditions dunng the course of constructmn of the project. 1nclud1ng .<1afety of all per!IOns and property; that this requirement shall be made to apply contmuously and not be bm1tcd to normal workmg hours, and construction contractor further agrees to defend. indemnify and hold design professional harmless from any and all liability, real or alleged, in connection with the performance o[ work on this proJect, excepting liability ansmg from the sole negligence of design professional. ~ "Bei4,'WilliamCJ-tt,st ®c51lssociates PROFESSIONAL ENGINEERS, PLANNERS& SURVEYORS PO BOX19739 • 14725ALTONPAAKWAY.IAVINE,CALIF0RNIA92718 (114)472,JSOS R.C.E. ~27'1187 I • </ ~'::i"'TlMA\'i;P ~~t{~ ~\~\¢<:;. FIL.L- S c.-<. -Ji. ,..D'1A,\..';, Po ~ ~ N:".,.-~ f'r:f!: ":,l-\~\l\(,6(1,\e AW "blJS"!>l~lct. 1'~- \\.f.' ,-_e, "f.G.. re.. it -rw u <!,. f.u. f'::> 1\--IV. f.f. \?AD Lege!l"lld .-Of" of swre lllGI-\ POIP,- "(Of' Or e,el"-1/1 -rep or c,,Rr->.'11=: 10P Or C.Ui2£:::> FL.OW LINE; TOP Or WAU... C,,\V,.Dl:c e,~eAI'- f'IN 1<ol-\ f'INl'bl.\ \t-lve;Rr u1<Aoe 'bllf<?f'Ac.ec OP Ol'Z.A\N tl!!o,-AINIIJ(!, WAU... FIN \<bl-I FLO= e~e.\/l(f\ON ("AO 1':\£\/,'.f\O\J F\.O'N 1-1 >-i e ~€, ,:»-~~a-.-r PRECISE GRADING PLAN LOT NO. 184 TRACT NO. 2813 SHEET I CITY OF NEWPORT BEACH OF 3 SHTS. J.N. 26757 f ~ " " C C -C ' ,c C 1( I , ~ c, '2 ~ a 0 ' z C !': f:i " 0 ~ ,, > c z ~ C ~ 2 OJ C' ~ m ~ JJ ~ g z l> s ~ z 0 \Jo r ~ □ I JJ " 2 D ~ ~ "l ~ c □ c:, 2; z ' 6 ~ GJ z i z \ C "' ~ ::;: < ~ z rn [jJ " m > :0 'a D c:, z " ~.------, l z ~ < z 0 r. ~ c ~ 0 JJ B < z G'J z C < OJ m JJ z ►L..-----' 0 JJ ~ z G) z C ~ OJ m • r I I I ! I : I ( : I I I I l I 'L • I J ~ ""E;l7 ~* a,,,,.. -\ 1'7i-:!~:!:!"~.::r+zD-'l'IJ1, ,., 1.,,f'. -z.e'!> \.., f. "2.-ZO 1-. F ' ' w;u, ___ IS l'U,\,\ 4 \lf't"RF. P.,}e,. -""""'ft.Ill c.,ec(,0\-l f?,e, ··-~-:::.~-::=:::-._:::,~, ! i I ~CJJei11,,CWilliam'Ti"ost ®cfllssociates PROFESSIONAL ENGINEERS, PLANNERS & SURVEYORS PO BOX197S9 • 14725ALTONPARKWAY,IRVINE,CALIFORNIA92718 (714) '172-3505 tJ:r:~. --- 4. !'ef<!'c p.,J.,,. f"l!:R WA.L • .L l'l.NJ,e, •r· ~----L. ,..., ---\""'> .. ~' ,(1<{1 -~-- .PAg_,- • \,..01' 4' ffi~ p...J.c,. !/IAv 6e> CC!J~~"r'W 't'O -i.::>c.lt> 4' r-./.r;, @ 'ffil'o l.ocAilO/J. ~~ ~~ "'~ "' j ,,. ;,, CJ 4'---._ ill \ ~ \_ -------/1a:, tJ § Pt.ANTE~~--/- N,A IZ.E>L E S/DE-WAl.,!<; " e,;. t...f' ® o.i::,. " --- v;; I<'.: (:!' ts-;~) $-Xr F.&.ocv o.k., t..JJ,9-. \Jill.,.lTlE~ 1'E'l!'r. J • ~TA""~l2-"r S'/t 1~ l • ---- t -. .,,,, 'i-<¥;¢; f"\ft'~W OIJ ~ :!> 9''-(V. ~ fl,/,\L a,,11,\. 1°'t7 A!'~P f'l,J-C• VJAV. ,e,,_ """""" --- , .. .mr:- ---0 IG, ft.AN \...t?1"' \54~ ""f"~ACT' Mg. U\~ ~Of( r fe"-C-\.\" CA SHEET 2 Of 3 SHTS • ~ ' ., z I ~ 0 ' CJ ' c n ~ 0 CJ ~ " ~ ~ c ~ 'I c; 3 C z u C z ~ -~ C f'l C " 0 ~ C ;-;.! ~ C ~ a z (Iii /TI n > C ~ D ~ z > \) ' ~ N I vi 0 ::0 ~ z GJ z C <, OJ m ::0 0 ::0 ~ z GJ z C <'. [I] m JJ 0 JJ ~ z GJ z C ~ OJ !Il u DOWEL (TTP I ..-n ""' r, =F-1 STE~-........_ II i II . ' . PLAN • a:NTI:R SU'PatT FOR YJLTlPLE GRATES iO DOWEL DETAIL AMERICAN PUBLIC WORKS ASSOCIATION-STANDAROPLAN 302-0 STRUCTURAL DATA WALL AM:) SU!! OIW:NSIONS AB, RB~FORCEIEIIT REOUREMENTS ~ i-~-~--:1....,.,,,r """"" -----t----,.U' I I \~ PPE OR I I K!NOLITHIC CATO! '-'-' "---~"~•---~~! BASIN CONNECTION SECTION A-A JWTES· ,_, , .. , .. •-· •·• , .. ,. ,. ,. "'' • • " ,,. .. ' .. " • • ' " .. • ,,. • " • • .. " • ' • .. • ,o• -""' WA!.LS AH0 SU.SS HOT ltE0Ulll!D REQUIRED NOT REQURfD "'"""' HOT REQUIRED """""' 1. WHERE THE BASIN IS TO BE CONSTRUCTED WITHIN THE LIMITS OF EXISTING OR PROPOSED SIDEWALK OR I~ CONTIGUOUS TO SUCH SIDEWALK, THE TOP SLAB OF THE BASIN MAY BE POURED EITHER MONOLITHIC WITH THC:: SIDEWALK OR SEPARATELY, USING THE SAME CLASS OF CONCRETE AS IN THE BASIN·WHEN POURED MONOLITHICALLY. THE SIDEWALK SHALL BE PROVIDED WITH A WEAKENED PLANE OR A 1•INCH DEEP SAWCUT CONTINUOUSLY AROUND THE EXTERNAL PERIMETER OF THE CATCH BASIN WALLS, INCLUDING ACROSS THE FULL WIDTH OF THE SIDEWALK. SURFACE OF ALL EXPOSED CONCRETE SHALL CONFORM IN SLOPE, GRADE, COLOR, FINISH, ANO SCORING TO EXISTING OR PROPOSED CURB AND WALK ADJACENT TO THE BASIN. 2 All CURVED CONCRETE SURFACES SHALL BE FOAMED BY CURVED FORMS, AND SHALL NOT BE SHAPED BY PLASTERING 3. ONE Gi=IATlr-lG IS REQUIRED UNLESS OTHERWISE SHOWN ON THE PROJECT PLAN. 4 FLOOR OF BASIN SHALL BE GIVEN A STEEL TROWEL FINISH AND SHALL HAVE A LONGITUDINAL AND LATERAL SLOPE OF 1 :12 MINJMUM AND 1 ·3 MAXIMUM, EXCEPT WHERE THE GllTTER GRACE EXCEEDS 8 PERCENT, IN WHICH CASE THE LONGITUDINAL SLOPE OF THE FLOOR SHAU BE THE SAME AS THE GUTTER GRADE SLOPE FLOOR FROM ALL DIRECTIONS TO THE OUTLET. 5. DIMENSIONS· V -THE DIFFERENCE IN ELEVATION FROM THE TOP OF THE CURB AND THE INVERT OF THE CATCH BASIN AT THE OUTLET " 4 S FEET. Vu "'THE DIFFERENCE IN ELEVATION BETWEEN THE TOP OF THE CURB ANO THE INVERT AT THE UPSTREAM END O"F THE BASIN, ANO SHALL BE DETERMINED BY THE REQUIREMENTS OF NOTE 4, BUT SHALL NOT BE LESS THAN CURB FACE PLUS 12 INCHES. V, = THE DIFFERENCE IN ELEVATION BETWEEN THE TOP OF THE CURB ANO THE INVERT OF THE INLET. NOTED ON THE PROJECT PLANS. H "' NOTED ON THE PROJECT PLANS. W -= 2 FEET 11·3,B INCHES FOR ONE GRATING, ADO 3 FEET 5-318 INCHES FOR EACH AoomONAL GRATING A = THE ANGLE. IN DEGREES, INTERCEPTED BY 'rHE CENTERLINE OF THE CONNECTOR PIPE ANO THE CATCH BASIN WALL TO WHICH THE CONNECTOR PIPE IS ATTACHED. 6 PLACE CONNECTOR PIPES AS INDICATED ON THE PROJECT PLANS. UNLESS OTHERWISE SPECIFIED. THE CONNECTOR PIPE SHALL BE LOCATED AT THE DOWNSTREAM END OF THE BASIN WHERE THE CONNECTOR PIPE IS SHOWN AT A CORNER, THE CENTERLINE OF THE PIPE SHALL INTERSECT THE INSIDE CORNER OF THE BASIN THE PIPE MAY BE CUT AND TRIMMED AT A SKEW NECESSARY TO INSURE MINIMUM 3-INCH PIPE EMBEDMENT, ALL AROUND, WITHIN THE CATCH BASIN WALL ANO 3-INCH RADIUS OF ROUNDING OF STRUCTURE CONCRETE, ALL AROUND, ADJACENT TO PIPE ENDS. A MONOLITHIC CATCH BASIN CONNECTION SHALL BE USED TO JOIN THE CONNECTOR PIPE TO THE CATCH BASIN WHENEVER ANGLE "A' IS LESS THAN 70 DEGREES OR GREATER THAN i ,o DEGREES, OR WHENEVER THE CONNECTOR PIPE IS LOCATED IN A CORNER. THE OPTIONAL USE OF A MONOLITHIC CATCH BASIN CONNECTION IN ANY CASE IS PERMITTED, MONOLITHIC CATCH BASIN CONNECTIONS MAY BE CONSTRUCTED TO AVOID CUTTING STANDARD LENGTHS OF PIPE. 7. STEPS SHALL BE LOCATED AS SHOWN. !F THE CONNECTOR PIPE INTERFERES WITH THE STEPS, THEY SHALL BE LOCATED ON THE FRONT WALL AT THE CENTERLINE OF THE DOWNSTREAM GRAT-ING. STEPS SHALL BE SPACED 12 INCHES APART. THE TOP STEP SHALL BE 7 INCHES BELOW THE TOP OF THE GRATING AND PROJECT 2·1i'2 INCHES ALL OTHER STEPS SHALL PROJECTS INCHES. 8 DOWELS ARE REQUIRED AT EACH CORNER AND AT 7 FEET ON CENTER (MI\XIMUM) ALONG THE BACKWALL 9. THE FOLLOWING A. P.W A.. STANDARD PLANS ARE !NCO.RPORATED HEREIN: 308 MONOLITHIC CATCH BASIN CONNECTION 311 FRAME ANO.GRATING FOR CATCH BASINS 309 CATCH BASIN REINFORCEMENT 635 STEEL STEP 310 CATCH BASIN FACE PL.ATE ASSEMBLY ANO PROTECTION BAR ~ - - - ~.,_____,,r - ~i"'E""'~~ 1+,o ~4 Con ~w• _ o, -· I 3'-0"(Max.J Retainin5 Walls tJ'-0' Max. i Max, Slope\ 2 /.-'--'--:,,4\l.,.,F Clr. ,H----... 32" ~ Grade: Sloping or Level '----9" Cone. Blk. I --.._ ~ r. l Cu. Ft. of Coarse --.... Grave 1 Cont. I #4 Cont-__ "-. ... _·r--•• f,i¢'.;~ Onu.t Head "'--"''-! jj ~· Jo,.l.nt as Show,,n,-..-1 -.......__ ~ v;, I I ...., ,;_ ; ~=-~--·~--::-,~ i:; \\1~1i§!Hi T 2•• ---r-==-=l'--'.=· =-"' 12" 1 T 3'-0" (Max.) I_ 2'2" L 'l •9" i 3" Max. Slope (Slopinq Backfill} (Level Backfil ) 1 2 #4 Cont. ______ ~ r---..,' --2" "~ Clr. r----.,..._J<t---¼4@32" ·--., ... _ B" Blk. i ~--.. -, ~ (..,•✓ ,; Grade; Slop2.ng or Level 1 #4 Cont.---k. $-1::ff f\__-' .. Omit Head Joint i ,-• as Shown ! "'-!--:i°J l ._, .. / 12"Clr. ,,,_,, = Cu. Ft. of Co3rse Gravel (Cont.) l. 2. f2" NOTES .11. (Min. ) ---,.4 Cont.--.. {L r This is a guide line and (Typ. l applies to normal conditions. A Professional Engineer should '--1~,~"~C~lr-.-----''\. be consulted where unusual conditions exist. Walls over 3'-0" in he1.gi'lt require Engineer's calculetions and building permit. GENERAL NOTES -t-4-'.-f," jSlopinq Backf1.rll l'-10" (Level Backfil J 1. CONCRETE BLOCK. Grade N. Per ASTM C90. 2. CONCRETE. 3. GROUT. 4. MORTAR. 5. STEEL BARS.~ 6. EXPi'\NSION JOINTS. 7. BLOCK PATI'ERN. 8. FOOTINGS- 9. SOIL. 2000 PSI_ Ratio: 1 cement, 2! sand, 3½ crushed reek, 7¼ gals. water. 2000 PSI. Ratios: I cement, 2 pea gravel, 3 sand. Grout all 'cells. Type Mor S. Ratios; 1 cement. ¼ lime, 4½ sand. Grade 40 per ASTM A615. Every 30' o.c. Lay all block in RUNNING BOARD pattern. Bottom of footings r.rust be level. Use stepped footing in sloped lots. Footings must be placed only in natural undisturbed or properly compacted soil with~ minimum bearing value of 1000 psi, 1 12" 1 ~4@32" -, ,Z..-+?,O MATERIALS: i ffi Ci) ® ® FEMALE COUPLING WITH I.P. THREAD ON SERVICE LINE. 6 @ TAIL PIECE AND HETER INSTALLED BY CITY AFTER HETER BOX IS IN PLACE. ANGLE HETER STOP, JAMES JONES J1524 DR l«JELLER H1425D. FDR C{)IPRESSIDN CONNECTION USE JAMES JONES J4201 OR MUELLER H14253. TYPE "K" COPPER TUBING. -COUPLING, JAMES JONES J152B, J1529, OR MUELLER H15400, H15403. FOR C{)IPRESSJON CONNECTION, USE JAMES JONES J2609 OR MUELLER H15403. CORPORATION STOP, JAMES JONES Jl500 OR MUELLER H15000. FOR COMPRESSION CONNECTION USE JAMES JONES J3401 OR l«JELLER H1500B. DOUBLE BRONZE SERVICE CLAMP WITH C.S. THREAD, JAMES JONES J979, MUELLER lolOS. CONCRETE HETER BOX, BROOKS #37 OR H & C 1437 00 l ( R * 41/1. i,CXES SUBJECT TO TI\Al'f\C \,llO.Oll{G REQUIRE C.1 TUfFIC COIEl!S. NOTES: 1 2 3 4 5 COUPLINGS WILL NOT BE PERMITTED WHEN SERVICE LINE IS LESS THAN 60' IN LENGTH, ALL TUBING AND FITTINGS BElWEEN HAIN AND HETER SIW.L BE 1" WHEN INSTALLING A 3/4" METER USE A BRONZE liATER HETER BUSHING, JAMES JONES J128H, l«JELLER H-108B9. TUBING SHALL BE BENT WITH AN APPROVED BENDER. DISTORTION OF 0.0. SHALL NOT EXCEED \\I 0~ ITi Ol!i-11••' °"""'"•· SEE STD-516-L FOR SPACING OF 111/LTIPLE CONNECTIONS. SEE STD-505-L FDR SERVICE TAP TO LINED AND COATED STEEL HAIN. C;i.Lc.. c.JJ.I). (.,T11.1TIE5" t>r::Pf". J .S-n&.NE.AP.T s{1[11 CJ@bet1CJJci11fWilliam'Prost ®d:lJ_ssociates PROFESSIONAL ENGINEERS, PLANNERS& SURVEYORS P.O BOX1 9739 • 147'25ALTON PARKWAY,IRVINE,CALIFORNJA.92718 {7'14)'17'2•3505 ~ ' ---- _- I----- --- ·' -, -~ ,15• ">C:-.::::. ~ j '. ~ .t.A~JL. d&:""n-oN ~ MJT£.S: _,, ~T0-406·£ • T l Fl:'R .sl'.t>OE U:.S.S 7,/A/V l/4-" Pe"R 1='7; A d" ll::WV£l:',DV $/u;L/.. 8£ t/.S'EO, MIN JJUJPe • U,"' ~R FT. .z. -"Zif' ,SEHl.f;,11' t:'L~WUr -@ A/ SIDE"'4i.k, v.s'e" ~-'CS' RTVOVCr.s .,eu-,'i'8 ,-At:1 l·R{t:,:;!K'..eET6 a:JVeR) MARKEO ~H'-,:;;e v,-"1'_ M"-l·R. S MW.ER lr.5/W!JIJT .S,,,,,,.,. IAL'LWE A .ST~R aER .R.trl!!'A!S ✓N n;,e SIDL'!WA(.k USE .w.,.r4:>V c-=v .-,a,e,7.!:' ,rs.s. sr~R 4. -SEHIER C',<e,,~ P.I.At'EO ✓,VALLE~ a'<' &l<:'IVEN,'Y.S' U3E ,e;;,,:;,:;,-;s A<'oa.<>r ...,_ ~rr eK." o/r~ -<e>. 4T -~Ke,::, .Jl:we;,c_ ,:,, -~ C~VT -.... V$E flpe ~ 7'He ,$,4171; 0/AMe'TER MID AJ4T£".E"/~ useo AV TNE A&Vd/lV/J.1$ S,E"Hle'll /.,.IA/£. 6. ~ 1;41///.Y HE.r✓IJEN:'E:S Si""/../.. BE 4.-Cli!AVITY .Sl:WE,<!;S. AU 07/.leR S SJ,l,t/l.L aE 4""~ SHEET 3 -- OF 3 SHTS. ,, I I 1: I I \ er-------, ~ z !;' ~ r·, Cc g g ~ ~ s 5 z c z n > C C " 0 JJ ~ z GJ L C <' OJ rn JJ ,. ______ ~ 0 :0 ~ < z GJ z C s OJ rn :0 GJ JJ ~ z GJ z C < OJ m ~