HomeMy WebLinkAboutExhibit 1Exhibit 1
General Plan Annual Progress Report
(Including Housing Element Report)
CITY OF NEWPORT BEACH
GENERAL PLAN ANNUAL PROGRESS REPORT
(Including Housing Element Report)
2007 Calendar Year
California Government Code Section 65400 mandates that each City and County
submit an annual progress report to their legislative body, the Office of Planning
and Research (OPR) and the Department of Housing and Community
Development (HCD) to provide progress on General Plan implementation for the
calendar year. Included in the report is a required report on Housing Element
progress.
Consistent with Government Code Section 65400, the following General Plan
Annual Progress Report follows preparation guidelines set forth by OPR and
provides information for decision makers to assess how the General Plan was
implemented during the 2007 calendar year. The updated Newport Beach
General Plan was adopted in November 2006. On December 12, 2006 City
Council created the General Plan /Local Coastal Program Implementation
Committee for the sole purpose of guiding implementation of the General Plan
and Local Coastal Plan. The Committee created the General Plan
Implementation Task List to implement the General Plan. This report evaluates
and provides the status of each task.
The Housing Element portion can be found following the General Plan
Implementation tasks.
A. GENERAL PLAN IMPLEMENTATION TASKS
T49 �°
grants _...
1.
Interim zoning resolution including
Complete
the ability to require development
agreements.
City Council adopted an interim
(Land Use Element)
zoning resolution on January 9,
2007 which included the ability
to require development
2
agreements through an interim
study. No interim studies
processed under the new
resolution.
2.
Procedures to implement single- and
Complete
two- family design policies.
(Land Use Element)
Ordinance No. 2007 -3 adopted
Residential Design Criteria for
single and two -unit residential
developments.
3.
Zoning Code and Specific Plan
Pending
rewrite.
(Land Use Element)
Staff and consultants are working
on this task.
• Consultants hired April
2007
• Staff and consultants
attended multiple
meetings with the GP/LCP
Committee and Technical
Advisory Group
• First administrative draft
completed October 2007
• Second administrative
draft completed April 2008
• Committee meetings will
occur Summer 2008
followed by Planning
Commission and City
Council hearings
4.
Housing Element certification by
Pending
HCD
(Housing Element)
Consultants and staff continue to
move towards completion of this
task. Revised RHNA approved by
SCAG July 12, 2007.
• City Council approval
of contract with PBSJ
for required update and
certification, December
18, 2007
3
• On March 31, 2008,
two public workshops
were conducted — one
for developers and one
for the general public
• Draft to Planning
Commission and City
Council June 2008
• HCD Submittal
scheduled for June
2008
5.
Park dedication fee update (Quimby
Complete
Act).
(Natural Resources Element)
Fee updated, May 2, 2007:
$26,125 per unit
6.
Economic Development Strategic
Complete
Plan
(Land Use Element)
Staff, Applied Development
Economics Inc. (ADE) and the
Economic Development
Committee (EDC) completed the
strategic plan. In July, 2007, City
Council adopted the Strategic
Plan for Fiscal and Economic
Stability which will assist the City
in implementing the portions of
the General Plan related to
economic development.
7.
Economic Development Strategic
Ongoing
Plan Implementation
(Land Use Element)
Implementation schedule
has been created which
includes objectives from
the plan and a time line
with allocated staff hours
■ Objective 2.2 Facilitate
changes by Newport
Center /Fashion Island,
completed
8.
Fair Share Fee update
Pending
Circulation Element
4
Consultants hired by the City
continue to work towards
completion with the City.
• Staff approval of contract
for nexus study (Revenue
& Cost Specialists, LLC),
October 31, 2007
• Nexus study first draft
reviewed January 16,
2008
• Nexus study completion
February 2008
9.
Airport Area infrastructure study and
Pending
fee (s)
(Land Use Element)
ROMA Design Group and Fair
Share Consultant continue to
work on task.
■ Submitted the first draft for
staff review on January
23, 2008
10.
Inclusionary Housing Ordinance and
Pending
In -lieu fee
(Housing Element)
Consultant along with staff
currently working on this task.
■ In July, 2007 the City
entered into agreement
with Economic & Planning
Systems, Inc., to prepare
a revised in -lieu fee study
• Affordable Housing Task
Force (AHTF) review of
updated fee study,
November 13, 2007
■ The AHTF requested
additional information and
that the study be
distributed to the
development community
■ City received response
from the BIA with
concerns regarding
5
calculation of the fee
• City is currently working
with BIA to alleviate their
concerns
• Draft ordinance and fee
calculation to AHTF
scheduled for Summer
2008
11.
Parking requirements and
On -going
management
(Circulation Element)
Staff and the Economic
Development Committee (EDC)
continue to work on this task.
• Sent out RFP for Parking
Management Study
• Selected and hired Walker
Parking Consultants
• Held kick -off meeting for
first study area - Corona
del Mar
• Conducted parking counts
week of May 12, 2008, in
CdM
• Sent Walker draft parking
sections of zoning code for
first review and comment
12.
Local Coastal Program Land Use
Pending
Plan Amendments - Amend CLUP
for consistency with General Plan
Both staff and consultants
Land Use Element
continue to work on this task.
(Land Use Element)
• Staff and the City's
consultant met with CCC
staff several times
regarding the application
• A tour of the coastal zone
with their staff was
conducted in February
2008
• CCC staff has expressed
to staff several questions
and concerns about
several proposed land use
M
Local Coastal Program Land Use
changes and staff
Plan Amendments (continued)
provided additional
information regarding
these issues and many of
CCC staffs questions
have been resolved
• Several land use changes
remain outstanding that
may result in a
recommendation for
changes to the CLUP and
General Plan
• Staff is continuing to work
with CCC staff to identify
and focus their comments
and will be initiating a
dialog with local
stakeholders in the coming
weeks and months to
develop a strategy to
address CCC staffs
issues in advance of a
hearing with the Coastal
Commission itself
• July hearing in San Luis
Obispo has been
requested as CCC staff
was unable to go to
hearing in May. Alternative
hearing times are August
in Oceanside or October in
LA or Orange County
13.
City Council Ordinance on
Complete
development agreements
(Land Use Element)
Staff completed and City Council
approved ordinance on February
27, 2007. The first development
agreement using the new
ordinance, North Newport Center
Development Agreement, was
adopted December 18, 2008.
14.
Traffic signal synchronization
Pending
(Circulation Element)
The Traffic Signal
7
Communication Master Plan
was completed in December
2007.
• Public Works awarded a
construction contract on
May 27, 2008, for the
Traffic Signal
Modernization Phase 1
project which will
implement CE 1.2.3 and
CE 6.1.1
• Phase 1 project
completion is anticipated
at the end of the year
2008
15.
Planned Community rewrite and
On -going
revisions
(Land Use Element)
Property owners are
responsible for
amendments in the North
Newport Center and
Airport Area
• North Newport Center
Planned Community was
adopted December, 2007
■ Both Koll and Conexant
(Airport Area) have
submitted conceptual
development plans(Koll
Center and Newport Place
Planned Communities)
■ Staff will work on other
planned communities
following the Zoning Code
rewrite
16.
Banning Ranch Pre - Annexation and
Pending
Development Agreement
(Land Use Element)
Staff anticipates a formal
application will be submitted
soon.
17.
Harbor Area Management Plan
Pending
Harbor and Bay Element
i3
Consultants, staff and Harbor
Commission continue towards
completion of task.
■ Completion of plan is
expected Fall 08'
18.
Run -off and Pollution Reduction Plan
On -going
(Natural Resources Element)
The Coastal /Bay Water Quality
Committee and staff continue to
work on this plan.
19.
Land Use database refinements and
On -going
maintenance
(Land Use Element)
Maintenance and updates of
databases is on- going.
20.
Fiscal Impact Model training
Complete
Applied Development
Economics, Inc. (ADE) and staff
completed training on March 29,
2007.
21.
Traffic Phasing Ordinance revision
Complete
regarding NBTAM
(Circulation Element)
Ordinance adopted on July 24,
2007.
22.
Measure S guidelines regarding
Pending
variable FAR
(Land Use Element)
Staff is preparing amendments.
23.
Municipal Code amendments
Pending
regarding property maintenance
standards
On December 11, 2007, the City
(Land Use Element)
adopted the 2006 International
Property Maintenance Code, with
local amendments, for residential
properties.
24.
Building Code amendments
Pending
regarding green buildings
Land Use Element
Resolution 2008 -21 adopted by
M
City Council on April 8, 2008
Building Code amendments
established the Task Force on
regarding green buildings
Green Development.
(continued)
• Task force will be
composed of (1) member
of the City Council, (3)
members of EQAC and
(3) members of the
General Plan /Local
Coastal Program
Implementation
Committee or its
Technical Advisory
Group, appointed by the
Mayor and confirmed by
the City Council
• First meeting was May
28, 2008
25.
Amend City Council Policies on
Pending
historic, archaeo and paleo
resources
Historical Resources Element
26.
Funding and priority program for
Pending
construction of noise barriers along
arterials
(Noise Element)
27.
Annual Review of CIP to determine
Pending
consistency with the General Plan
and Coastal Land Use Plan
On June 7, 2007, staff presented
(Land Use Element)
CIP for fiscal year 2007 -2008 to
the Planning Commission for
review. Planning Commission
provided comment and CIP was
included with the actual CIP
budget presentation to City
Council. See Attachment A for
the table of CIP projects and their
implementation of General Plan
and Coastal Land Use Plan
policies.
28. Emergency Preparedness
(Safety Element)
10
In January of 2007, the City
was officially recognized as a
Storm Ready and Tsunami
Ready community. The City
also completed a Tsunami
Incident Action Plan (IAP),
which specifically addresses
public notifications,
evacuations and sheltering
needs during a tsunami event.
200 residents completed the
Fire Department's Community
Emergency Response Team
(CERT) program. The CERT
program teaches residents life
saving skills that can be used
during a disaster or
emergency.
CITY OF NEWPORT BEACH
GENERAL PLAN ANNUAL PROGRESS REPORT
Housing Element Report
2007 Calendar Year
This portion addresses more specific requirements, as required by Government
Code Sections 65584 and 65583, to demonstrate the City's progress in meeting
its share of regional housing needs and Housing Element goals. As mandated by
Government Code Section 65400, staff used guidelines provided by the
Department of Housing and Community Development (HCD) to prepare this
portion.
The Housing Element report includes the following information: (A) annual
building activity reports for new housing units; (B) regional housing needs
allocation progress; and (C) program implementation status including local efforts
to remove governmental constraints to the maintenance, improvement, and
development of housing.
A. Annual Building Activity Reports for New Housing Units
Using data from the Newport Beach Building Department Building Activity
Report, the following table was created, illustrating the number of permits issued
for new construction of housing units and for demolished housing units in
calendar years 2006 and 2007.
PERMITS ISSUED FOR HOUSING UNITS
2006 -2007
CALENDAR YEAR
NEW UNITS
DEMOLISHED UNITS
NET INCREASE IN UNITS
2006
161
143
18
2007
151
151
0
TOTAL
312
294
18
2
B. REGIONAL HOUSING NEEDS ALLOCATION PROGRESS
The Southern California Association of Governments (SCAG) prepared a
Regional Housing Needs Allocation (RHNA) to identify the housing needs for
each jurisdiction within the SCAG region. SCAG, through the RHNA process,
assigned Newport Beach a share of housing units that should be constructed in
the 2006 -2014 planning period to satisfy housing needs resulting from the
projected growth in the region. To accommodate projected growth in the region,
SCAG determined the City's RHNA to be 1,784 dwelling units.
The City is currently working on a draft Housing Element and anticipates the
submittal to HCD will occur prior to July 1, 2008.
The table below summarizes the need for new housing, distributed by income,
calculated through the RHNA process for the 2006 -2014 Planning Period.
TOTAL RHNA CONSTRUCTION NEED BY INCOME
2006 -2014
VERY LOW
I LOW
MODERATE
ABOVE MODERATE
TOTAL
392
1 322
362
708
1,784
22%
18%
1 20.3%
1 39.7%
1 100%
CITY'S PROGRESS IN MEETING IT'S SHARE OF THE REGIONAL HOUSING NEEDS
ASSESSMENT DURING RHNA PERIOD 2006 -2014
VERY
LOW
MODERATE
ABOVE
TOTAL
On -going
LOW
deterioration of existing
MODERATE
neighborhoods by strictly enforcing
PROJECTED NEED
392
322
362
708
1,784
TOTAL NEW UNITS
0
0
0
18
18
PERMITTED
06-07
REMAINING NEED
392
322
362
1690
1,766
C. PROGRAM IMPLEMENTATION STATUS/ LOCAL EFFORTS
TO REMOVE GOVERNMENTAL CONSTRAINTS
PROGRAM
GOAL
STATUS
1.1.1
Improve housing quality and prevent
On -going
deterioration of existing
neighborhoods by strictly enforcing
A quarterly report on code
building code regulations and abating
enforcement activities is kept
code violations and nuisances.
on file at the City.
3
1.1.2
Participate with the Orange County
On -going
Housing Authority and Housing and
Community Development Division in
City staff attends OCHA's
their administration of rehabilitation
City's Advisory Committee
loans and grants for low- and
meetings to keep up to date
moderate - income homeowners and
on rehabilitation programs
rental property owners to encourage
offered by the County.
preservation of existing City housing
stock.
1.1.3
Require replacement of housing
On -going
demolished within the Coastal Zone
when housing is or has been
The City uses Chapter 20.86
occupied by very-low, low -, and
"Low and Moderate Income
moderate - income households within
Housing within the Coastal
the preceding 12 months. The City
Zone" to implement this
shall prohibit demolition unless a
program:
Coastal Residential Development
Permit has been issued. The specific
■ CRDP required to
provisions implementing replacement
demolish a 54 -unit
unit requirements are contained in
apartment complex on
the Municipal Code.
5515 River Avenue.
• Six rental units
occupied by low -
income and moderate -
income households
were found within
complex
• CRDP approved and
requires applicant to
replace the six rental
units at an off -site
location with
restrictions to maintain
their affordability for a
minimum 30 years
4
PROGRAM
GOAL
STATUS
2.1.1
Maintain rental opportunities by
On -going
restricting conversions of rental units
to condominiums unless the vacancy
A vacancy rate surrey is
rate in Newport Beach for rental
completed every quarter to
housing is an average 5 percent or
monitor consistency with this
higher for four (4) consecutive
policy.
quarters, and unless the property
owner complies with condominium
conversion regulations contained in
Chapter 20.83 of the Newport Beach
Municipal Code.
2.1.2
Take all feasible actions, through
On -going
use of development agreements,
expedited development review, and
Planning staff continually
expedited processing of grading,
evaluates all proposed
building and other development
affordable housing projects for
permits, to ensure expedient
potential incentives, including
construction and occupancy for
expedient processing of
projects approved with low- and
permits.
moderate - income housing
requirements.
The Santa Barbara
Condominium project which
included an Affordable
Housing Agreement with an
Affordable Housing
Implementation Plan (AHIP)
will be provided expedited
permit processing.
The North Newport Center
Planned Community project
which included an Affordable
Housing Agreement with an
Affordable Housing
Implementation Plan (AHIP)
will be provided expedited
permit processing.
2.1.3
Participate with the County of
On -Going
Orange in the issuance of
tax - exempt mortgage revenue bonds
The issuance of tax - exempt
to facilitate and assist in financing,
mortgage revenue bonds is
housing affordable to low and
moderate - income households.
2.1.4 Conduct an annual compliance-
monitoring program for units
required to be occupied by very low -,
low -, and moderate - income
households.
2.2.1
Require a proportion of affordable
housing in new residential
developments or levy an in -lieu fee.
The City's goal over the five -year
planning period is for an average of
15 percent of all new housing units
to be affordable to very low—, low -,
and moderate - income households.
The City shall either (a) require the
payment of an in -lieu fee, or
(b) require the preparation of an
Affordable Housing Implementation
Plan (AHIP) that specifies how the
development will meet the City's
affordable housing goal, depending
on the following criteria for project
size:
1. Projects of 50 or fewer units
shall have the option of preparing an
AHIP or paying the in -lieu fee.
2. Projects where more than 50
units are proposed shall be required
to prepare an AHIP.
Implementation of this program will
occur in conjunction with City
approval of any residential
discretionary permits or Tentative
Tract Maps. To insure compliance
5
typically applies for the bonds.
The City will encourage the
use of such bonds and inform
affordable housing developers
of their availability.
The City retains a consulting
firm that provides an annual
compliance monitoring report
for the City's income qualified
units.
On -going
Staff continues to enforce the
requirements for affordable
housing and /or the payment of
in -lieu fees. Adoption of an
inclusionary housing
ordinance that includes an in-
lieu housing fee is anticipated
midyear 2008.
The recently approved Santa
Barbara Condominium and
North Newport Center
Planned Community projects
include Affordable Housing
Agreements with Affordable
Housing Implementation
Plans (AHIP) that will provide
affordable housing units.
The Santa Barbara
Condominium AHIP requires
the purchase of covenants for
a 12 -unit existing off -site
apartment complex to restrict
income levels and rent for
thirty years.
The North Newport Center
Planned Community AHIP
A
requirements, the City will include
requires that deed restrictions
conditions in the approval of
be recorded to ensure that the
discretionary permits and Tentative
units remain affordable for a
Tract Maps to require ongoing
minimum of 30 years.
monitoring of those projects. (Imp
2.1)
2.2.2
The City shall provide more
On -going
assistance for projects that provide a
higher number of affordable units or
The City will provide financial
a greater level of affordability. At
assistance based on a project
least 15 percent of units shall be
by project analysis, depending
affordable when assistance is
on need and overall project
provided from Community
merits from in -lieu housing
Development Block Grant funds or
fund reserves. The City did
the City's in -lieu housing fund.
not commit any funds in 2007.
A portion of the City's CDBG
funds were committed to pay
a Section 108 loan. For
allocation of the other portion
of the CDBG funds see the
status for Program 5.1.1.
2.2.3
For new developments proposed in
On -going
the Coastal Zone areas of the City,
the City shall follow Government
See status of Program 1.1.3.
Code Section 65590 and Title 20.
2.2.4
All required affordable units shall
On -going
have restrictions to maintain their
affordability for a minimum of 30
Staff continues to include this
years.
affordability restriction as a
standard condition on all
affordable housing projects,
unless an otherwise longer
affordability covenant is
agreed upon.
A comprehensive inclusionary
housing ordinance is currently
being developed which will
clearly specify all conditions
for incentives, including the
minimum affordability period
of 30 years.
2.2.6
Advise existing landowners and
prospective developers of affordable
housing development opportunities
available within the Banning Ranch,
Airport Area, Newport Center,
Mariners' Mile, West Newport
Highway, and Balboa Peninsula
areas.
Periodically contact known local
developers and landowners to solicit
new affordable housing construction
2.2.7 Participate in other housing
assistance programs that assist
production of housing.
7
City staff continues to provide
prospective developers with
information on the City's
available land and its
incentive program.
Development of a plan
outlining incentives that
implement General Plan
goals is also part of the City's
General Plan Implementation
Program.
The City Manager's Office and
Community and Economic
Development periodically
discuss the construction of
new affordable housing with
local developers and
landowners.
City staff also introduces the
idea of constructing affordable
housing to developers who
propose large residential
projects and discuss density
bonuses to assist in the
construction of affordable
housing.
City staff attends OCHA
Cities Advisory Committee
meetings to keep up -to -date
with programs that assist in
the production of housing.
Staff informs developers of
programs that are available to
assist in the production of
i3
housing for all income levels.
2.2.8
New developments which provide
On -going
Provide a streamlined "fast- track"
housing for lower income
development review process for
households that help meet regional
The City has provided a copy
proposed affordable housing
needs shall have priority for the
of the Housing Element to
developments.
provision of available and future
water and sewer service
resources or services, including
providers. Pursuant to state
water and sewer supply and
law, water and sewer
services.
providers must grant priority to
Condominium and North
developments that include
Newport Center Planned
housing units affordable to
lower income households.
2.3.1
Study housing impacts of proposed
On -going
major commercial /industrial projects
during the development review
Staff is monitoring legal
process. Prior to project approval, a
challenges to inclusionary
housing impact assessment shall be
housing requirements, and will
developed by the City with the active
consider developing housing
involvement of the developer. Such
impact fees for all new
assessment shall indicate the
commercial and industrial
magnitude of jobs to be created by
developments as an additional
the project, where housing
or alternative resource for
opportunities are expected to be
providing affordable housing.
available, and what measures
(public and private) are requisite, if
Staff monitors all new
any, to ensure an adequate supply
planning applications for
of housing for the projected labor
applicability.
force of the project and for any
restrictions on development due to
the "Charter Section 423" initiative.
PROGRAM
GOAL
STATUS
3.1.1
Provide a streamlined "fast- track"
On -going
development review process for
proposed affordable housing
The City considers "fast track"
developments.
development review
incentives on a project -by-
project basis.
The Santa Barbara
Condominium and North
Newport Center Planned
3.1.2
3.1.3
3.2.1
When a residential developer
agrees to construct housing for
persons and families of very low,
low and moderate income above
mandated requirements, the City
shall either (1) grant a density
bonus as required by state law, or
(2) provide other incentives of
equivalent financial value.
Review and consider in accordance
with state law, the waiver of
planning and park fees, and
modification of development
standards, (e.g., setbacks, lot
coverage, etc.) at the discretion of
City Council and Planning
Commission for developments
containing very low, low- and
moderate - income housing in
proportion to the number of low- and
moderate - income units in each
iaentity the tollowmg sites as
adequate, which will be made
available through appropriate
zoning and development standards
and with public services and
facilities needed to facilitate and
encourage development of a variety
of housing types to meet City
housing goals as identified pursuant
to Government Code
Section 65583(b): Banning Ranch,
Airport Area, Newport Center,
Mariners' Mile, and the Balboa
Peninsula areas.
0
a streamlined development
review process for their
Affordable Housing
Agreements and Affordable
Housing Implementation
Plans.
The City considers density
bonuses and other incentives
on a project by project basis.
On -going
Waivers and incentives are
considered by the Planning
Commission and City Council
on a project -by- project basis.
The City is currently rewriting
the Zone Code which will
reflect changes to facilitate the
development of the identified
sites. The North Newport
Center project has been
approved and talks continue
with the property owner of the
Airport Area regarding
development plans.
10
3.2.2
Update Zoning Code to reflect
Pending
GOAL
housing opportunities provided in
4.1.1
Periodically contact owners of affordable
the Land Use Element.
■ Consultants hired April
units for those developments listed in
2007
Table H12 to obtain information regarding
Staff is currently
• Staff and consultants
their plans for continuing affordability on
updating the contact list
attended multiple
their properties.
for affordable units in
meetings with the
conjunction with the
GP /LCP Committee and
Technical Advisory
Group
• First administrative draft
completed October
2007
• Second administrative
draft completed April
2008
• Committee meetings
will occur Summer 2008
followed by Planning
Commission and City
Council hearings
3.2.3
When requested by property
On -going
owners, the City shall approve
rezoning of developed or vacant
The City continually monitors
property from non - residential to
requests for zone changes of
residential uses when appropriate.
vacant and developed
These rezoned properties shall be
properties from non -
added to the list of sites for
residential to residential and
residential development.
approves when determined to
be compatible and feasible.
When approved, these sites
are mapped for residential
uses on both the zoning
district map and General Plan
Land Use Map.
PROGRAM
GOAL
STATUS
4.1.1
Periodically contact owners of affordable
On -going
units for those developments listed in
Table H12 to obtain information regarding
Staff is currently
their plans for continuing affordability on
updating the contact list
their properties.
for affordable units in
conjunction with the
11
2008 Housing Element
Update.
4.1.2
Consult with the property owners regarding
Pending
utilizing CDBG funds and in -lieu housing
funds to maintain affordable housing
Will be discussed during
opportunities in those developments listed
the AHTF meetings in
in Table H12.
conjunction with
Program 2.2.7.
4.1.3
Prepare written communication for tenants
On -going
and other interested parties about Orange
County Housing Authority Section 8
Pamphlets informing
opportunities to assist tenants and
prospective tenants and
prospective tenants to acquire additional
landlords about the
understanding of housing law and related
OCHA Section 8
policy issues.
program have been
made available in the
public lobby and
information is posted on
the City website.
4.1.4
Investigate availability of federal, state,
On -going
and local programs (including in -lieu funds)
and pursue these programs if found
The City investigates
feasible, for the preservation of existing
available programs and
low- income housing, especially for
evaluates the feasibility
preservation of low- income housing that
of participating in such
may increase to market rates during the
programs.
next ten years. A list of these programs,
including sources and funding amounts,
will be identified as part of this program
and maintained on an on -going basis.
4.2.1
Investigate the use of federal funds to
On -going
provide technical and financial assistance,
if necessary, to all eligible homeowners
The City investigates
and residential rental property owners to
available programs and
rehabilitate existing dwelling units through
evaluates the feasibility
low- interest loans or potential loans, or
of participating in such
grants to very low —, low- and moderate-
programs.
income, owner - occupants of residential
properties to rehabilitate existing units.
4.2.2
In accordance with Government Code
On -going
Section 65863.7, require a relocation
12
impact report as a prerequisite for the
Consistent with state
closure or conversion of an existing mobile
law, a detailed
home park.
relocation impact report
is a requirement for the
permit for proposed
closures or conversions.
4.2.3
Should need arise, consider using a
On -going
portion of its Community Development
Block Grant funds for establishment and
A need for this program
implementation of an emergency home
has not been
repair program. Energy efficient products
demonstrated.
shall be required whenever appropriate.
4.2.4
Participate as a member of the Orange
On -going
County Housing Authority Advisory
Committee and work in cooperation with
Staff regularly attends
the Orange County Housing Authority to
the quarterly meetings
provide Section 8 Rental Housing
of the OCHA Cities
Assistance to residents of the community.
Advisory Committee.
The City shall, in cooperation with the
Housing Authority, recommend and
Staff continually works
request use of modified fair market rent
in cooperation with the
limits to increase number of housing units
County to provide
within the City that will be eligible to
Section 8 rental housing
participate in the program. The Newport
assistance to residents.
Beach Planning Department shall prepare
and implement a publicity program to
A link to the Orange
educate and encourage landlords within
County Housing
the City to rent their units to Section 8
Authority website has
Certificate holders and to make very low-
been placed on the City
income households aware of availability of
website to provide
the Section 8 Rental Housing Assistance
information on the
Program.
Section 8 program.
4.2.5
Participate in a Joint Powers Authority of
Discontinued
Orange County jurisdictions for the
Indefinitely
purpose of financing and administering a
lease purchase program for first -time
Due to potential legal
homebuyers.
conflicts, the lease
purchase program has
been discontinued
indefinitely.
13
PROGRAM
GOAL
STATUS
5.1.1
Apply for United States Department
On -going
of Urban Development Community
Development Block Grant funds and
The Action Plan for Fiscal
allocate a portion of such funds to
year 2007 -2008 has been
sub - recipients who provide shelter
i approved and the City will
and other services for the homeless.
provide funding to the
following organizations to
preserve the supply of
emergency and transitional
housing: Human Options,
Emergency Transitional
Shelter (Orange Coast
Interfaith Shelter), Serving
People In Need (SPIN), and
Fair Housing Council of
Orange County.
The following organization
has been funded to assist
homeless battered women
and children: Human
Options.
5.1.2
Cooperate with the Orange County
Pending
Housing Authority to pursue
establishment of a Senior /Disabled or
The City will conduct an
Limited Income Repair Loan and
analysis of different
Grant Program to underwrite all or
programs and the financial
part of the cost of necessary housing
feasibility or participating in
modifications and repairs.
such programs.
Cooperation with the Orange County
Housing Authority will include
continuing City of Newport Beach
participation in the Orange County
Continuum of Care and continuing to
provide CDBG funding. (imp 14.3)
5.1.3
Permit, where appropriate,
On -going
development of "granny" units in
single - family areas of the City.
One permit was approved on
July 26, 2007 to establish a
granny unit in conjunction
with an existing single-family
14
home. The applicant has until
July 2009 to obtain building
permits for the structure.
5.1.4
Consistent with development
On -going
standards in residential and
commercial areas, permit emergency
Emergency shelters and
shelters and transitional housing
transitional housing are
under group housing provisions in its
monitored for compliance
Zoning Code.
with the development
standards regulations
contained in the Zoning
Code.
5.1.5
Work with the City of Santa Ana to
On -going
provide recommendations for the
allocation of HUD Housing
As the most populous city in
Opportunities for Persons with AIDS
Orange County, the City of
( HOPWA) funds within Orange
Santa Ana receives HOPWA
County)
funding from HUD on behalf
of the entire County.
Authorized uses of these
funds include: acquisition,
rehabilitation, conversion, or
lease of facilities to provide
short-term shelter,
permanent housing, new
construction for housing,
project or tenant based rental
assistance, short term rent,
utility payments, and
supportive services.
Should the City wish to
partner in the acquisition,
development, or
rehabilitation of affordable
housing for persons with
HIV /AIDS, the City may
request funding at future
HOPWA Strategy meetings
which are held once a year.
15
5.1.6 Maintain a list of `Public and Private Pending
Resources Available for Housing and
Community Development Activities." City staff will work to develop and
maintain a list of resources that
are available for housing and
PROGRAM
GOAL
STATUS
6.1.1
Contract with an appropriate fair
On -going
housing service agency for the
provision of fair housing services for
The City contracts with the
Newport Beach residents. The City
OC Fair Housing Authority
will also work with the fair housing
annually.
service agency to assist with the
periodic update of the Analysis of
The Regional Fair Housing
Impediments to Fair Housing
Impediments Analysis was
document required by HUD. The City
completed in 2000. The next
will continue to provide pamphlets
analysis is due in 2009.
containing information related to fair
housing at the Planning Department
Pamphlets containing
counter.
information of Fair Housing
and Dispute Resolution
Services are available at the
public counter.
6.1.2
Support fair housing opportunities by
On -going
using Community Development Block
Grant funds whenever necessary to
For the 2007 -2008 Fiscal
enact federal, state, and City fair
Year, Newport Beach
housing policies.
allocated $12,960 in CDBG
funding to the Fair Housing
Council of Orange County to
assist the City in furthering
fair housing through
education, landlord/tenant
counseling, and legal action
when necessary.
16
The City's 2006 General Plan Update provided an implementation program to
identify a principal set of actions and procedures necessary to carry out the goals
and policies of the General Plan including implementation programs aimed at
facilitating the production of a variety of housing types for all income levels. In
December 2006 the General Plan /Local Coastal Program Implementation
Committee was established by the City Council with the sole purpose of guiding
implementation of the General Plan and Local Coastal Plan. The Committee has
created the General Plan Implementation Task List which includes tasks to
implement the programs aimed at housing.
The tasks include the updated Housing Element for the 2008 -2014 planning
period that will include 2006 -2014 RHNA allocation numbers.
Identifying areas of the City where additional housing could be located in order to
accommodate the City's fair share of regional population growth continues to be
a main focus of General Plan Implementation. Opportunities for residential
development were created in a number of areas of the City including Newport
Center and the Airport Area. The City is in the process of updating its zoning
code to reflect these changes in the General Plan. Rezoning of these areas will
facilitate the infusion of new housing into these areas, consistent with the goals
of the General Plan.
PROGRAM
GOAL
STATUS
7.1.1
As part of its annual General Plan
On -going
Review, the City shall report on the
status of all housing programs. The
The City prepares an Annual
portion of the Annual Report
Housing Element Progress
discussing Housing Programs is to be
Report for submission to
distributed to the California
HCD.
Department of Housing and
Community Development in
accordance with California State Law.
The City's 2006 General Plan Update provided an implementation program to
identify a principal set of actions and procedures necessary to carry out the goals
and policies of the General Plan including implementation programs aimed at
facilitating the production of a variety of housing types for all income levels. In
December 2006 the General Plan /Local Coastal Program Implementation
Committee was established by the City Council with the sole purpose of guiding
implementation of the General Plan and Local Coastal Plan. The Committee has
created the General Plan Implementation Task List which includes tasks to
implement the programs aimed at housing.
The tasks include the updated Housing Element for the 2008 -2014 planning
period that will include 2006 -2014 RHNA allocation numbers.
Identifying areas of the City where additional housing could be located in order to
accommodate the City's fair share of regional population growth continues to be
a main focus of General Plan Implementation. Opportunities for residential
development were created in a number of areas of the City including Newport
Center and the Airport Area. The City is in the process of updating its zoning
code to reflect these changes in the General Plan. Rezoning of these areas will
facilitate the infusion of new housing into these areas, consistent with the goals
of the General Plan.
Attachment A
CIP Project Table
CIP Review
June 7, 2007
Page 2
maintenance of existing improvements and facilities. Otherwise, these projects are not
directly applicable to planning policies. Such projects will not be analyzed unless they
present an apparent inconsistency with the City's planning policy documents. Projects
involving new construction or the expansion or removal of existing improvements will be
analyzed in terms of their consistency or inconsistency with the General Plan, Coastal
Land Use Plan, and other planning policy documents.
CIP Pg.*
Project Title
Planning Document
Comments
Coastal Land Use Plan
Both the General Plan and the LCP call for
12
Little Corona Restroom Facility
Recreation Element
providing adequate support facilities,
including restrooms.
Policy CE 7.1.5 calls for the City to
23
Avon Street and Tustin Avenue Parking Lot
Circulation Element
consider relocation of the Avon Street
Slurry Seal
municipal lot to better serve commercial
uses in Mariners' Mile.
Policy LU 5.2.3 calls for improving and
24
Balboa Village Alley Replacement
Land Use Element
enhancing the aesthetic quality of alleys
without impacting service access.
Policy S 4.2 supports and encourages the
seismic retrofitting and strengthening of
27
Bridge Seismic Retrofit Construction
Safety Element
essential facilities such as hospitals and
schools to minimize damage in the event of
seismic or geologic hazards.
28
Coast Highway Sidewalk — Morning Canyon
Circulation Element
Improvements and dimensions are
consistent with the classifications of this
Road to Seaward Road
primary road.
The medians are currently watered
manually. The project includes an irrigation
system connected to the City's automated
32
Dover Drive Medians Renovation
Natural Resources
system. This is consistent with Policy NR
Elemem
1.1, which calls for the use of water —
efficient landscaping and irrigation. Water -
efficient shrubs and groundcover should be
used.
Improvements and dimensions are
33
Dover Drive Sidewalk
Circulation Element
consistent with the classification of this
primary/major road.
Irvine Avenue Realignment— University to
Improvements and dimensions are
3g
Bristol
Circulation Element
consistent with the classification of this
primary road.
40
Irvine Terrace Landscape Improvements
Natural Resources
Pursuant to Policy NR 1. 1, water — efficient
Element
landscaping and irrigation should be used.
CIP Review
June 7, 2007
Page 3
CIP Pg.#
Project Title
Planning Document
Comments
Improvements and dimensions are
42
Jamboree Road Bridge Widening
Circulation Element
consistent with the classification of this
major road.
The medians are currently watered
manually. The project includes an irrigation
system connected to the City's automated
53
Westdiff Drive Medians Renovation
Natural Resources
system. This is consistent with Policy NR
Element
1. 1, which calls for the use of water —
efficient landscaping and irrigation. Water -
efficient shrubs and groundcover should be
used.
Bayside Waterfront Walkway to Balboa Island
Harbor and Bay Element
This project is consistent with policies
54
Bridge
Recreation Element
calling for expanding public access to and
Coastal Land Use Plan
along the shoreline.
56
Directional, Wayfinding, and Monument
Circulation Element
Policy CE 1.2.1 and CLUP Policies 2.9.3 -3,
3.1.1.3, and 3.2.2 -6 call for wayfinding
Signage
Coastal Land Use Plan
signs.
Policy CE 5.1.12 calls for improved
57
Flashing Crosswalk — Newport Boulevard at
Circulation Element
Pedestrian crossings in key high volume
23 Street
areas, including those on the Balboa
Peninsula.
Policy CE 5.1.12 calls for improved
58
Iris Avenue and Coast Highway Traffic Signal
Circulation Element
pedestrian crossings in key high volume
areas, including those in Corona del Mar.
Neighborhood Traffic Management
Pursuant to Policy CE 2.2.5, traffic calming
59
Improvements
Circulation Element
improvements will need to balance safety,
quality of life, and efficiency.
Harbor and Bay Element
This project is consistent with policies
60
Pedestrian Coastal Access Improvements
Recreation Element
calling for enhancing public access to the
Coastal Land Use Plan
shoreline.
Policy CE 2.3.4 calls for monitoring of traffic
61
Traffic Signal Modernization: Phase 1 Newport
Circulation Element
conditions, considering additional
improvements in areas with operations
Center Area
issues, such as intersections with heavy
turn volumes.
Policy CE 2.3.4 calls for monitoring of traffic
Traffic Signal Modernization: Phase 2
conditions, considering additional
62
Jamboree Road
Circulation Element
improvements in areas with operations
issues, such as intersections with heavy
turn volumes.
Policy CE 2.3.4 calls for monitoring of traffic
63
Traffic Signal Modernization: Phase 3 Airport
Circulation Element
conditions, considering additional
improvements in areas with operations
Area
issues, such as intersections with heavy
turn volumes.
Policy CE 2.2.6 calls for efficient and safe
64
Traffic Signal Preemption System
Circulation Element
access for emergency vehicles in all
residential, commercial, and industrial
areas.
Policy LU 6.17.2 calls for streetscape
improvements to enhance West Newport's
67
West Coast Highway Vision Plan
Land Use Element
character and image as a gateway to
Newport Beach and develop a stronger
pedestrian environment at the commercial
nodes.
CIP Review
June 7, 2007
Page 4
CIP Pg.#
Project Title
Planning Document
Comments
Back Bay View Park Replenishment and
The project is consistent with Policy 4.4.1.2,
Enhancement
Coastal Land Use Plan
which requires landscaping to minimize
impacts to public coastal views.
CLUP Policy 2.8.2 -6 and Policy S 1.3 call
for continuing the Surfside- SunseUWest
72
Beach Sand Study and Replenishment
Coastal Land Use Plan
Newport Beach Replenishment program.
Program
Safety Element
CLUP Policy 2.8.6 -2 and Policy S 3.1 call
for monitoring beach width and elevations.
CLUP Policy 2.8.6 -3 and Policy HB 116
call for a comprehensive beach
replenishment program to assist in
Coastal Land Use Plan
maintaining beach width and elevations.
76
Coastal Sand Replenishment Cooperative
Harbor and Bay Element
Project
Natural Resources
CLUP Policy 4.2.4 -2 and Policy NR 15.1
Element
call for monitoring dredging projects within
the region to identify opportunities to reduce
disposal costs and utilize dredge spoils for
beach nourishment.
CLUP Policies 4.2.5 -2 and 4.2.54 and
Coastal Land Use Plan
Policy NR 11.5 allow eelgrass restoration
77
Eelgrass Mitigation Bank
Natural Resources
sites to serve as mitigation sites for
Element
eelgrass removal resulting from dock and
channel dredging projects.
Coastal Land Use Plan
CLUP Policy 3.3.2 -7 and Policies HB 6.3,
79
Mooring Layout Design
Harbor and Bay Element
HB 6.4, and Policy R 8.3 encourage the
Recreation Element
provision and expansion of moorings.
80
Newport Center Park
Recreation Element
Policy R 1.9 calls for developing Newport
Center Park as a passive park.
CLUP Policy 3.3.2 -7 calls for expanding
83
Public Docks Access Improvements
Coastal Land Use Plan
and enhancing facilities for dinghy docks,
where feasible.
84
Rhine Channel Wharf Public Doric
None
No policies are directly applicable.
Policy R 1.9 calls for developing Sunset
87
Sunset Ridge Park
Recreation Element
Ridge Park as an active park with
playfiekls, picnic areas, a playground, and
other facilities.
CLUP Policy 4.1.2 -2 calls for special
90
Areas of Special Biological Significance
Coastal Land Use Plan
protection to marine resource areas and
Assessment
species of special biological or economic
significance.
CIP Review
June 7, 2007
Page 5
CIP Pg.#
Project Title
Planning Document
Comments
CLUP Policy 4.1.2 -2 calls for special
91
Areas of Special Biological Significance
Coastal Land Use Plan
protection to marine resource areas and
Implementation
species of special biological or economic
significance.
Policy NR 16.2 calls for coordinating the Big
Canyon Creek Restoration Project so that
92
Big Canyon Creek Restoration
Natural Resources
its outcomes are consistent with goals for
Element
Upper Newport Bay established by Orange
County and the Department of Fish and
Game.
CLUP Policy 4.1.3 -3 and Policy NR 10.8
call for the preparation of natural habitat
protection regulations for Buck Gully for the
Coastal Land Use Plan
purpose of providing standards to ensure
93
Buck Gully Maintenance Road and Wetland
Natural Resources
both the protection of the natural habitats in
Project
Element
these areas and of private property rights.
Include standards for the placement of
structures, native vegetation/fuel
modification buffers, and erosion and
sedimentation control structures.
CLUP Policy 4.3.2 -24 calls for the use of
94
Irrigation — Citywide Central Computer System
Coastal Land Use Plan
weather- and moisture-based irrigation
controls to reduce runoff, direct and
encourage water conservation.
CLUP Policy 4.3.2 -24 calls for the use of
95
Irrigation — Newport Coast Central Computer
Coastal Land Use Plan
weather- and moisture-based irrigation
System
controls to reduce runoff, direct and
encourage water conservation.
CLUP Policy 4.3.2 -24 calls for the use of
96
Irrigation — Smart Controller Program
Coastal Land Use Plan
weather- and moisture-based irrigation
controls to reduce runoff, direct and
encourage water conservation.
CLUP Policy 4.3.2 -3 and Policies HB 8.6
Coastal Land Use Plan
and NR 3.6 call for participation in
97
Newport Coast Runoff Reduction Program
Harbor and Bay Element
watershed-based runoff reduction efforts
Natural Resources
with the Regional Board Water Quality
Element
Control Board, the County of Orange, and
upstream cities.
Coastal Land Use Plan
The project is consistent with the water
98
Newport Coast Watershed Program
Harbor and Bay Element
quality control policies of the CLUP and the
Natural Resources
General Plan.
Element
The methane gas associated with an
99
Newport Terrace Landfill Gas Remediation
Safety Element
abandoned landfill and mitigation measures
to reduce the hazard is referenced in the
General Plan, there are no specific policies.
CIP Review
June 7, 2007
Page 6
CIP Pg.#
Project Title
Planning Document
Comments
Both the CLUP and the General Plan
identify the Semeniuk Slough as an
Coastal Land Use Plan
environmental study area (ESA). Policy NR
100
Semeniuk Slough Dredging Project
Natural Resources
10.3 requires a site - specific survey and
Element
analysis prepared by a qualified biologist
where development would occur within or
contiguous to areas identified as an ESA.
Both the CLUP and the General Plan call
Coastal Land Use Plan
for the preparation of a Harbor Area
101
Upper Bay and Harbor Area Management
Harbor and Bay Element
Management Plan (RAMP) that will provide
Plan
Natural Resources
a comprehensive approach to the
Element
management of the resources of Newport
Bay.
The following projects are not budgeted in the Preliminary Fiscal Year 2007 -2008 CIP:
• Shoreline Management Plan. CLUP Policy 2.8.3 -3 and Safety Element Policy S
2.2 call for the development and implementation of shoreline management plans
for shoreline areas subject to wave hazards and erosion.
■ Uniform Signing Program. CLOP Policies 2.9.2 -3, 3.1.1 -3, and 3.2.2 -6 and
General Plan Policies CE 5.1.1.10 and R 9.3 call for developing and
implementing a signing program to assist the public in locating, recognizing, and
utilizing coastal access points, public bikeways and trails, parking areas,
restrooms, and other support facilities.
■ Parking Management Programs. CLUP Policies 2.9.3 -14 and 3.2.2 -4 call for
developing parking management programs for coastal areas. Land Use Element
Policy LU 6.8.4 encourages the development of shared parking facilities and
management programs on the Balboa Peninsula.
■ Long Range Plan for Public Trails and Walkways. Harbor and Bay Element
Policy 6.2 and Circulation Element CE 5.1.1 -4 call for the development and
implementation of a long -range plan for public trails and walkways to access all
appropriate commercial areas of the harbor, as determined to be physically and
economically feasible.
The fact that these projects were not included in the Preliminary Fiscal Year 2007 -2008
CIP does not indicate inconsistencies with planning policies. Some of these programs are
still in their preliminary stages and do not involve public improvements at this time. These
projects, or components of these special projects, may appear in future capital
improvement programs.