Loading...
HomeMy WebLinkAbout94-37 - Mitigation Monitoring Program for Hoag Hospital Master PlanRESOLUTION NO. 9437 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NEWPORT BEACH ADOPTING A MITIGATION MONITORING PROGRAM FOR THE HOAG HOSPITAL MASTER PLAN • WHEREAS, the City of Newport Beach has approved a planned Community Development Plan and Development Agreement for Hoag Memorial Hospital Presbyterian; and WHEREAS, the project has also been approved by the California Coastal Commission; and WHEREAS, the Development Agreement and the Conditions of Approval of the California Coastal Commission requires the formal adoption of the mitigation monitoring program. NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Newport Beach, that the mitigation monitoring program attached as "Exhibit A" is approved. ADOPTED this 13th day of June, 1994. ATTEST: MAYOR HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING PLAN May 1994 f Project: APPLICABILITY OF MITIGATION MEASURES Date: APPLIES AMR N/A APPLIES AMR N/A "1 • APPLIES AMR N/A APPLIES AMR N/A 45 69 46 70 47 71 48 72 49 73 50 74 51 75 52 76 53 77 54 78 55 79 56 80 57 81 58 82 59 83 60 84 61 85 62 86 63 87 64 88 65 89 66 90 67 91 68 92 C APPLIES AMR N/A APPLIES AMR N/A 93 117 94 118 95 119 96 120 97 121 98 122 99 123 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 2 • HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project. . Mitigation Measure: 1 Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: Prior to the issuance of a grading permit, the project sponsor shall document to the Citv of Newnort Beach Building Department that grading and development of the site shall be conducted in accordance with the City of Newport Beach Grading Ordinance and with plans prepared by a registered civil engineer. These plans shall incorporate the recommendations of a soil engineer and an engineering geologist, subsequent Building Department by the project sponsor. Standard For Compliance: Shown on approved grading 121ans; permanent reproducible copies to be provided at project completion Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 7 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 2 • Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: that all cut slopes shall be monitored for potential instabilities by the project geotechnical engineer during all site rg ading and construction activities and strictly monitor the slopes in accordance with the documentation. Standard For Compliance: Shown on approved rg ading plans: documented in contractor/ subcontractor supplemental general conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ FO J4 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 3 Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: Prior to the issuance of a grading permit the project sponsor shall provide to the City of Newport Beach a comprehensive soil and geologic investigation and minimize disturbance to adjacent residents This report shall determine if there are any faults on site which could render all or a portion of the property unsafe for construction All recommendations contained in this investigation and report shall be incorporated into project construction and design plans This report shall be submitted to the City for review and approval. Standard For Compliance: Approved soil and geologic report Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 0 c HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 4 • Timing For Completion: Prior to Issuance of Each Building Permit Text of Mitigation Measure: related structures and as specified in the then current City adopted version of the Uniform Standard For Compliance: Shown on approved building plans Compliance: _ f City of Newport Beach Verification Approved on: Approved by: Signature: _ /d HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 5 Timing For Completion: Prior to the Issuance of Each Grading and /or Building Permit_ Text of Mitigation Measure: Prior to the issuance of grading or building permits for each phase of development, the Building Department shall ensure that geotechnical recommendations included in "Report of Geotechnical Evaluation for Preparation of Master Plan and Environmental Impact Report, Hoag Memorial Hospital Presbyterian Campus, 301 Newport Boulevard, Newport. California" as prepared by LeRoy Crandall Associates, June. 1989, and in the report prepared pursuant to Mitigation Measure 3, are followed. Standard For Compliance: Shown on approved grading 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 6 • Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: Prior to the issuance of a grading permit. the project sponsor shall conduct a soil corrosivity evaluation. This evaluation shall be conducted by an expert type should be evaluated. Appropriate personnel protection shall be worn by field personnel during the field evaluation. In the event soils are found to be corrosive, the source and extent of the corrosive soils shall be determined, and all buildings and infrastructure shall be designed to control the potential impact of corrosive soils over time. Standard For Compliance: Approved soil corrosivity report Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /2 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 7 Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: Based on the corrosion assessment and source determination. a soils and construction material compatibility evaluation shall also be undertaken, concluding with the appropriate mitigation measures and design criteria. Corrosion resistant construction materials are commonly available and shall be used where the evaluation /assessment concludes the corrosive soils conditions could adversely impact normal construction materials or the materials used for the mitigation of subsurface gas conditions. For example there are many elastomers and plastics like PVC, which are resistant to corrosion by up to 70 percent sulfuric acid at 140 degrees Fahrenheit. Standard For Compliance: Approved soils and construction material compatibility evaluation Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 13 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 8 • Timing For Completion: Prior to the Issuance of a Building Permit Text of Mitigation Measure: Should the soil be identified as hazardous due to the severeness of their corrosives (i.e., a PH less than 2.5), on -site remediation by neutralization shall be undertaken prior to construction. Appropriate regulatory agency approvals and permits shall also be obtained. Standard For Compliance: Obtain approvals /permits, if remediation is required, subsequent remediation Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /N HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 9 Timing For Completion. Prior to the Issuance of Each Grading Permit plan completion): Ongoing During Grading (plan implementation) Text of Mitigation Measure: Prior to issuance of rg adi g permits. the project sponsor shall pollutants These procedures may include: the replanting of exposed slopes within 30 days shall strictly adhere to the approved construction erosion control plan and compliance shall be monitored on an on-going basis by the Newport Beach Building Department. Standard For Compliance: Shown (construction erosion control plan ) on approved grading plans, in contractor /subcontractor supplemental general conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ J5 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 10 is Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: Prior to the issuance of grading permits, the project sponsor shall submit a landscape plan which includes a maintenance program to control the use of fertilizers and pesticides, and an irrigation system designed to minimize surface runoff and overwatering. This plan shall be reviewed by the Department of Parks. Beaches and Recreation and approved by the City of Newport Beach Planning Department. The project sponsor shall install landscaping in strict compliance with the approved plan. Standard For Compliance: Approved landscape plan Compliance: I- City of Newport Beach Verification Approved on: Approved by: Signature: _ !6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: . Mitigation Measure: 11 Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: The Project Sponsor shall continue the current practice of routine vacuuming of all existing parking lots and structures and shall also routinely vacuum all future parking lots and structures at current frequencies. Upon implementation of the County of Orange Storm Water Master Plan, routine vacuuming shall be done in accordance with the requirements specified in the plan. Standard For Compliance: Documented as part of Development Agreement annual review_ Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 0 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 12 • Timing For Completion: Prior to Issuance of Each Grading Permit Text of Mitigation Measure: Upon completion of final building construction plans, and prior are adequate. The applicant shall submit a report to the City of Newport Beach Building shall be forwarded to the California Regional Water Quality Control Board, Santa Ana Region. Standard For Compliance: Approved site hydrological analysis: submit report to RWQCB Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ K HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 13 Timing For Completion: Prior to Issuance of Each Building Permit ermit Text of Mitigation Measure: Prior to the completion of final construction plans. the Project determine the necessity for a construction dewatering program and subdrain system. Standard For Compliance: Approved geotechnical/hydrolo is study Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ Iq HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 14 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: to the Regional Water Quality Control Board for an NPDES permit if a construction dewatering or subdrain program is determined necessary by the Building Department based submit it to the California Regional Water Quality Control Board Santa Ana Region. The results of this testing will assist in determining the he specifications for the NPDES permit. The project sponsor shall strictly ply with all conditions of any NPDES Permit. Standard For Compliance: Obtain NPDES permit. if required: perform groundwater sampling and analysis, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ ,20 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 15 Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: Project Sponsor shall strictly comply with its Hazardous regulations enacted between now and completion of the proposed Master Plan development. Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 2i HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 16 • Timing For Completion: Prior to the Issuance of a Grading Permit Effecting the Wetlands Text of Mitigation Measure: The federal wetland regulations and requirements shall be reviewed by the City and the project sponsor at the time the proposed work is undertaken Coastal Commission If this review results in a finding by the Resources Agencies involved in the permit processes that mitigation is required for impacts to the 1.07 acres of wetlands dominated byl2amnpas grass such mitigation will be accomplished as part of the mitigation Standard For Compliance: Obtain Section 404 Permit, Section 1603 Streambed Alteration Agreement and Coastal Development Permit Compliance: l` City of Newport Beach Verification Approved Approved Signature: on: by: 1Z Project: HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING • Mitigation Measure: 17 Timing For Completion: Prior to the Issuance of a Grading Permit Effecting the Wetlands Text of Mitigation Measure: City of Newport Beach. Standard For Compliance: Approved wetlands mitigation plan Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ .)-3 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 18 • Timing For Completion: Prior to the Issuance of a Grading and /or Building Permit Effecting the Wetlands Text of Mitigation Measure: The resulting final mitigation plan shall be approved as part development in any areas affecting wetlands. Standard For Compliance: Obtain Section 404 Permit, Section 1603 Streambed Alteration Agreement and Coastal Development Permit Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ ..,y HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 19 Timing For Completion: Prior to the Issuance of a Grading Permit Effecting the Wetlands Text of Mitigation Measure: The plan will be consistent with the following= provisions: The amount of new wetlands created under the mitigation plan shall be at least of equal size to the area of sensitive wetland communities impacted by the project; the wildlife habitat values in the newly created wetlands shall not be less than those lost as the result of removal of sensitive wetland communities impacted by the project: the wetlands created shall not decrease the habitat values of any area important to maintenance of sensitive plant or wildlife populations: the wetland mitigation planning effort will take into consideration creation of 0.2 acre of salt grass habitat suitable for use by wandering skipper, such constitute an agreement between the applicant and the resource agencies involved. The plan shall be written so as to guarantee wetland restoration in accordance with stated management objectives within a specified time frame. The plan shall describe the applicant's responsibilities for making any unforeseen repairs or modifications to the restoration plan in order to meet the stated objectives of the plan. Standard For Compliance; Approved wetlands mitigation plan Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 2—S HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 20 • Timing For Completion: Prior to the Issuance of Grading Permit Effecting the Wetlands Text of Mitigation Measure: The following detailed information will be provided by the project sponsor in the final mitigation plan: diagrams drawn to scale showing any alterations to natural landforms: a list of plant species to be used: the method of plant introduction (i.e., seeding, natural succession, vegetative transplanting etc.): and details of the short -term and long -term monitoring plans, including financing of the monitoring 121ans. Standard For Compliance: Approved wetlands mitigation plan Compliance• City of Newport Beach Verification Approved on: Approved by: Signature: _ ab HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Prgject: • Mitigation Measure: 21 Timing For Completion: Prior to the Issuance of Each Grading Permit ermit Text of Mitigation Measure: Prior to the issuance of a grading permit, an Orange Countv certified archaeologist shall be retained to, and shall, monitor the rp ading across the project area. The archaeologist shall be present at the pre - grading conference, at which time monitoring procedures acceptable to and approved by City shall be established, including procedures for halting or redirecting work to permit the assessment, and possible salvage, of unearthed cultural material. Standard For Compliance: Submittal of letter of authorization for certified archaeologist_ Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ z1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 22 • Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: Prior to the issuance of grading permits, an Orange Counri certified paleontologist shall be retained to and shall monitor the grading activities. The paleontologist shall be present at the pregrading conference, at which time procedures acceptable to and approved by the City for monitoring shall be established. including the temporary halting or redirecting of work to permit the evaluation, and possible salvage, of any exposed fossils All fossils and their contextual stratigraohic data shall go to an Orange County institution with an educational and /or research interest in the materials. Standard For Compliance: Submittal of letter of authorization for certified paleontologist Compliance: L City of Newport Beach Verification Approved on: Approved by: Signature: _ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: 0 Mitigation Measure: 23 Timing For Completion: Not Specified Text of Mitigation Measure: The Project Sponsor shall construct, if feasible and by mutual agreement. and maintain a fence along the common property line west of the Upper Campus. The proposed design of the fence shall be reviewed and approved by the Citv Engineering eering Department. Standard For Compliance: A¢reement for common property line fence construction and maintenance Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ ;L-1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 24 • Timing For Completion: Prior to the Issuance of Each Grading and Building Permit Text of Mitigation Measure: (LCP). Those requirements that are superseded by the PCDP and District Regulations are not considered applicable. The following discretionary approvals are required by the City of Newport Beach: EIR certification, adoption of the Master Plan, adoption of the Planned building permits for some facilities. The California Coastal Commission has the discretionary responsibility to issue a Coastal Development Permit for the Lower Campus and a Local Coastal Program Amendment for the Lower Campus. Standard For Compliance: Incorporated into approved grading plans/building 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 30 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 25 Timing For Completion: Prior to Issuance of Phase II Building Permits Text of Mitigation Measure: Subsequent to completion of Phase I of the project. the Project Sponsor shall conduct a Traffic Phasing Ordinance (TPO ) analysis for Phase II and III Master Plan development. The analysis shall identify potential intersection impacts the proposed project traffic volume contributions at these impacted intersections and the schedule for any intersection improvements identified as necessaEy by the study to insure a satisfactory level of service as defined by the TPO This report shall be approved by the City prior to commencement of Phase II or III construction Standard For Compliance: Approved TPO anal sis Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 31 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 26 is Timing For Completion: Prior to Issuance of Each Building Permit for Phase I Text of Mitigation Measure: Prior to issuance of building permits for Phase 1 of the projem generated by existing plus Phase 1 development will not exceed 1.338 PM peak hour traffic the mix of land uses will be altered to reduce the PM peak hour trips to at or below 1.338. Standard For Compliance: Approved trip generation study (note: Development Agreement specifies that this study required only "if Hoag proposes a land use other than specified in the approved Traffic Studv''1 Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 32 Project: HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING • Mitigation Measure: 27 Timing For Completion: Prior to the Issuance of Phase II Grading or Building Permits _ Text of Mitigation Measure: Subsequent to completion of Phase I Master Plan development, generated by the subsequent phases of development (Phases II and III) will exceed 1.856 or building permits for Phase II or III development. Standard For Compliance: Approved trip generation stud Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 33 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 28 • Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: The Project Sponsor shall continue to comply with all applicable regulations adopted by the Southern California Air Quality Management District that pertain to trip reductions such as Regulation 15. Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 3q HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 29 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: The project shall comply with the City of Newport Beach Transportation Demand Management Ordinance approved by the City Council pursuant to the County's Congestion Management Plan. Standard For Compliance: Shown on approved buildine plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: 35 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 30 Timing For Completion: Not Specified Text of Mitigation Measure: In order to ensure accessibility to the available transit services for employees, visitors and patrons of the Hospital the following transit amenities shall be incorporated into the Master Plan project Bus turnouts shall be installed if, and as required, by the City Traffic Engineer at all current bus stop locations adjacent to the Standard For Compliance: Provision of bus turnouts, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 36 • HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 31 Timing For Completion: Prior to Issuance of a Grading Permit Program Completion): Ongoing During Project Operation (Program Implementation) Text of Mitigation Measure: Prior to issuance of a rg ading permit for any of the proposed service roads during non - working hours. Such controls may include requesting that the Physicians, patients and visitors during non - working hours and other methods by which to routine deliveries. The results of this grogram shall be submitted to the City for review prior to issuance of the grading permit. If the results indicate that such controls do not significantly impact the operations of the hospital, and provided that requests for specified vendor delivery times is consistent with future Air Quality Management Plan procedures, the service road impacts to the adjacent residential units. Standard For Compliance: Documented as part of Development Agreement annual review Note: pilot program implemented in 1992 Compliance: City of Newport Beach Verification Approved on Approved by: 31 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 32 • Timing For Completion: Prior to Issuance of Phase II and Phase III Grading and /or Buildine Text of Mitigation Measure: review and approval a study that identifies the appropriate parking generation rates. The findings of this study shall be based on empirical or survey data for the proposed parking Standard For Compliance: Approved parkingg eneration rates study Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ ow HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 33 Timing For Completion: Prior to the Issuance of Each Grading Permit (plan preparation): Prior to the Issuance of Each Building Permit ,site plan incorporation of measures_ Text of Mitigation Measure: Prior to the issuance of precise rg adingl2ermits for the phase of Master Plan development that includes new, or modifications to existing, internal Standard For Compliance: Approved internal circulation plan rading12ermit): Shown on approved building plans site plan measures) Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 31 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 34 Timing For Completion: Not Specified Text of Mitigation Measure: Depending on actual site buildout, intersection improvements improvements shall be assessed during subsequent traffic studies to be conducted in association with Mitigation Measure 25. Standard For Compliance: Determined as part of approved TPO analysis (see Mitigation Measure #25) Compliance: L City of Newport Beach Verification Approved on: Approved by: Signature: _ 11Z HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 35 Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: As each phase of the Master Plan is constructed. the Project employees shall be included in the yearly update of the trip reduction plan for Hoae Hospital, as required by Regulation XV. Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newuort Beach Verification Approved on: Approved by: Signature: _ q1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 36 0 Timing For Completion: Prior to the Issuance of Each Grading or Building Permit Text of Mitigation Measure: Prior to issuance of grading and building permits for each phase of development, the project sponsor shall provide evidence for verification by the Planning Department that the necessary permits have been obtained from the SCAQMD for regulated commercial equipment incorporated within each phase. An air quality analysis shall be conducted prior to each phase of development for the proposed mechanical when added to existing project emissions could resulting impacts not 4reviouslyconsidered or significantly change the land use impact. appropriate CEQA documentation shall be prepared prior to issuance of any hermits for that phase of development. Each subsequent air quality analysis shall be reviewed and approved by the SCAQMD. Standard For Compliance: Obtain AOMD permits applications and submit air quality analysis, if required (Note: permit applications only will be submitted prior to issuance of each grading_ or building permit, as SCAQMD does not issue actual permits until after equipment is installed) Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ y2. Project: HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING • Mitigation Measure: 37 Timing For Completion: Prior to the Issuance of Each Grading and Buildin P� ermit Text of Mitigation Measure: Prior to the issuance of -grading and building permits for each desien Standard For Compliance: Shown on approved building-plans Compliance: City of Newnort Beach Verification Approved on: Approved by: Signature: _ y3 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 38 Timing For Completion: Prior to the Issuance of Each Grading and Building_ Permit Text of Mitigation Measure: Prior to issuance of grading and building_ permits for each is of five Percent of the provided narking at new facilities shall be reserved for carpools. These parking places shall be located near the employee entrance or at other preferential locations; (2) A minimum of two bicycle lockers per 100 employees shall be provided. Additional lockers shall be provided at such time as demand warrants: (3) A minimum of one shower and two lockers shall be provided; (4) Information of transportation alternatives access and parking of vanpool vehicles-, and (7) Bus stop improvements shall be required for developments located along arterials where public transit exists or is anticipated to exist within five years The exact number of each of the above facilities within each phase of the Master Plan shall be determined by the City during review of grading and building permit complete by the Planning Department. Standard For Compliance: Incorporate TDM site development requirements in approved gradin /bg uilding plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ qY HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 39 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: If noise levels in on -site outdoor noise sensitive use areas exceed 65 CNEI, the project sponsor shall develop measures that will attenuate the noise to acceptable levels for proposed hospital facilities Mitigation through the design and construction of a noise barrier (wall berm or combination wall/berm) is the most common way of alleviating traffic noise impacts Standard For Compliance: Approved acoustical study: noise attenuation measures shown on approved building 121ans, as required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ u5 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Proiject: Mitigation Measure: 40 . Timing For Completion: Prior to the Issuance of Certificate of Occupancy Text of Mitigation Measure: If levels exceed 45 CNEL. mitigation such as window modifications shall be implemented to reduce noise to acceptable levels. Standard For Compliance: ADnroyed acoustical study: incorporate noise attenuation measures, as required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: 4 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 41 Timing For Completion: Prior to the Issuance of a Grading and Building Permit Text of Mitigation Measure: Standard For Compliance: Completed acoustical study for on -site exhaust fan: incorporate recommended mitigation measures (Note: exhaust fan relocated and noise baffles installed in October 1)91) Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 41 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 42 • Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: The City of Newport Beach shall send a letter to each emergency vehicle company that delivers patients to Hoag Hospital requesting that, hat upon entrance to either the Upper or Lower Campus, emergency vehicles turn off their sirens to help minimize noise impacts to adjacent residents Hoag Hospital will provide the City with a list of all emergency vehicle companies that deliver patients to Hoag Hospital Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ ,/B HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 43 Timing For Completion: Prior to the Issuance of Each Grading and Building Permit Text of Mitigation Measure: Prior to issuance of grading and building permits, the project sponsor shall ensure that a landscape and irrigation _plan is prepared for each buildingLimprovement within the overall Master Plan. This plan shall be prepared by a licensed landscape architect. The landscaae--plan shall inteygrate and phase the installation of landscaping with the proposed construction schedule. The plan shall be subject to review by the Parks. Beaches and Recreation Department and approval by the Planning Department and Public Works Department. Standard For Compliance: Approved landscape and irrigation plan Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ Y9 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 44 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of a building permit, the project sponsor shall side of the Upper Campus. The systems shall be designed and maintained in such a manner as to conceal light sources and to minimize light spillage and glare to the adjacent residential Standard For Compliance: Shown on approved building 121ans: documented in electrical engineer's letter Compliance: City of Newaort Beach Verification Approved on: Approved by: Signature: _ %1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 45 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of building permit, the project sponsor shall submit plans to the City Planning Department which illustrate that all mechanical equil2ment and trash areas will be screened from public streets, alleys and adjoining propgrties. Standard For Compliance: Shown on approved buildin&T ans Compliance: City of Ne "ort Beach Verification Approved on: Approved by: Signature: _ 61 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 46 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of building permits the project sponsor shall submit plans which illustrate that major mechanical equipment will not be located on the building height criteria, and shall be concealed and screened to blend into the building roof using materials compatible with building materials. Standard For Compliance: Shown on approved building plans Compliance: City of Newaort Beach Verification Approved on: Approved by: Signature: _ 5.z HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 47 Timing For Completion: Prior to the Issuance of a Grading or Building Permit Text of Mitigation Measure: Prior to issuance of building or grading permits, the project sponsor shall make an irrevocable offer to dedicate and grade the proposed linear and Standard For Compliance: Submit Offer of Dedication Compliance: City of Newuort Beach Verification Approved on: Approved by: Signature: _ 53 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 48 Timing For Completion: Prior to the Issuance of Each Building_ Permit Text of Mitigation Measure: Regulations, to ensure that the visual impacts identified in the EIR are consistent with actual Master Plan development. This analysis shall be submitted to and approved by the Citv Planning Department. Standard For Compliance: Approved view impact analysis in conformance with PCDP and District Regulations Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 0 • HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 49 Timing For Completion. Ongoing During Site Preparation and Construction` Text of Mitigation Measure: In the event that hazardous waste is discovered during site preparation or construction, the project sponsor shall ensure that the identified hazardous waste and /or hazardous materials are handles and disposed in the manner specified by the State of California Hazardous Substances Control Law (Health and Safety Code Division 20, Chapter 6.5), standards established by the California Department of Health Services. Standard For Compliance: Documented in contractor /subcontractor supplemental general conditions and subsequent handling and nd disposal of any identified hazardous wastes /materials in accordance with regulations, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 55 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: SO • Timing For Completion: Prior to the Issuance of a Building Permit for Structures Located Near Wilshire Oil Well Text of Mitigation Measure: Prior to construction of structures over or near the Wilshire oil well Project Sponsor shall ensure that the Wilshire oil well, or any abandoned, unrecorded well or pressure relief well is re- abandoned to the current standards. Abandonment plans reabandonment was carried out according to DOG procedures. Standard For Compliance: Obtain DOG approval for well abandonment Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ y6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 51 Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: To further determine the source of the gas on the Lower Campus site, prior to issuance of a rg ading permit on the Lower Campus Project Sponsor shall collect gas samples from the nearest fire flooding wells and at Newport Beach Standard For Compliance: Approved report documenting ag s samples results Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 57 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 52 • Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: intervals within the removal zone, and at a deRh below the depth of actual disturbance. (The individual(s) performing this initial study may be at risk of exposure to significant - and possibly lethal - does of hydrogen sulfide, and shall be appropriately protected as Standard For Compliance: Approved soil ¢as sampling and monitoring_reportlprogram_ Compliance: L City of Newport Beach Verification Approved on: Approved by: Signature: _ ON HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 53 Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: A site safety plan shall be developed that addresses the risks associated with exposures to methane and hydrogen sulfide Each individual taking12art in by CFR 2910.120. Standard For Compliance: Approved site safes nlan Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 5`1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 54 • Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: If the analysis of the initial soil gas samples show unacceptable levels of hazardous constituents that have the potential to pose a health risk durin¢ construction activities, additional gas collection wells shall be drilled to contain and collect the gas. Standard For Compliance: Approved gas collection well report, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ M HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 55 Timing For Completion: Ongoing During Site Preparation and Construction Text of Mitigation Measure: Continuous monitoring for methane and hydrogen sulfide shall be conducted during the disturbance of the soils and during any construction activities that may result in an increase in the seepage of the gases The project sponsor shall maintain a_ continuous monitor in the immediate vicinitv of the excavation and a personal monitor, with an alarm, shall be worn by each worker with a potential for exposure Standard For Compliance: Documented in contractor /subcontractor supplemental eg neral Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ �1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 56 • Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: A study of other hazardous constituents that may be present in quantities that pose a health risk to exposed individuals shall be--Drepared and evaluated prior to the initiation of the project. The constituents studied shall include compounds that are directly related to petroleum, such as benzene and toluene. Standard For Compliance: Approved hazardous constituents study Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 6'�- HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 57 Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: A study shall be conducted that characterizes the wells, the influent ,gas, and the effluent of the flare. This study shall characterize the gas over a period of time, to allow for potential fluctuations in concentration and rate. Standard For Compliance: Approved gas characterization study Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 58 • Timing For Completion: Not Specified Text of Mitigation Measure: A scrubber system shall be required to reduce the concentration of hydrogen sulfide in the influent as. Standard For Compliance: Approved scrubber installation plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ &LI HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 59 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: In the event additional ,gases are to be collected from newly constructed collection wells as part of a measure to reduce exposures during construction, an evaluation of the capacity and efficiency of the present flare system shall be conducted prior to connecting any new sources. Standard For Compliance: Approved flare canacity(efficiency stud, . if f required Compliance: Ci of Newport Beach Verification Approved on: Approved by. Signature: _ b6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 60 • Timing For Completion: Not Specified Text of Mitigation Measure: An automatic re -light system shall be installed on the flare manned 24 hours per day. Standard For Compliance: Shown on approved flare relocation plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ b6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 61 Timing For Completion: Prior to Approval of Flare Relocation Plans Text of Mitigation Measure: Standard For Compliance: Shown on droved flare relocation plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 0 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 62 • Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: A study of the concentration of potential hazardous constituents shall be conducted prior to initiation of the project to characterize the wastewater and any risks it may pose to human health prior to development. A stormwater 1ollution prevention plan shall be developed to reduce the risk of the transport of hazardous constituents from the site. The Hospital shall apply for coverage under the State Water Resources Control Board's General Permit for Storm Water Discharges Associated with Construction Activity and shall comply with all the provisions of the permit, including, but not limited to, the development of the SWPPP, the development and implementation of Best Management Practices, implementation of erosion control measures, the monitoring_ program requirements, and post construction monitoring of the system. Standard For Compliance: Submit NOI to State Water Resources Control Board: prepare/ implementSWPPP Compliance: City of Newport Beach Verification Approved Approved Signature: on: by: ,i HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: isMitigation Measure: 63 Timing For Completion: Prior to the Issuance of a Grading Permit Teat of Mitigation Measure: Soil samples shall be collected from appropriate locations at the site and analyzed for BTEX and priority pollutants: if the soils are found to contain contamination, and a remedial action plan shall be completed and approved by the for Phase I construction activities. Standard For Compliance: Approved soil sample report: submit remedial action plan, if Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ bq HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 64 • Timing For Completion: Prior to the Issuance of Each Grading or Building Permit Text of Mitigation Measure: data to the City Building and Fire Departments. the State Department of Conservation. Division of Oil and Gas. and the Southern California Air Quality Management District for comment. Additional, any proposed new passive vents shall be evaluated by these agencies in a manner acceptable to these agencies. Standard For Compliance: Approved evaluation of all existing vent systems Compliance: I City of Newport Beach Verification Approved on: Approved by: Signature: _ 7p HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 65 Timing For Completion: Not Specified Text of Mitigation Measure: If required by the Southern California Air Quality Management District, an air dispersion model shall be required in order to predict the cumulative effects NemTort Beach Building Department. Standard For Compliance: Approved air dispersion model, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ -71 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 66 • Timing For Completion: Prior to the Issuance of Each Building ,g ermit Text of Mitigation Measure: Before the issuance of building permits, the project sponsor shall submit plans to the Building_ Department, City of Newport Beach, demonstrating that continuous hydrogen sulfide monitoring eciuiament with alarms to a manned remote location have been provided in building designs. This monitoring equipment must be the best available monitoring system, and the plans must include a _preventative maintenance program for the equipment and a calibration plan and schedule. Standard For Compliance: Shown on approved buildinj -p ans Compliance: City of Newport Beach Verification Approved on: Approved by Signature: _ 12, HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 67 Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: Prior to issuance of a rl ading permit, the Project Sponsor shall additional gas collection wells will be drilled to collect and contain the gas. Standard For Compliance: Approved inferred fault study; drill additional gas collection wells, if recluired Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 73 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 68 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of building permits. Project Sponsor shall recommendations of a Qeotechnical engineer. Standard For Compliance: Shown on approved building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 7q HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 69 Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: amount of gas is detected, a directionally drilled well will be permanently completed and put into the existing as collections tem. Standard For Compliance: Approved gas test study implement recommendations, as required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 75 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 70 • Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: Riser tvoe vents will be attached to light standards and buildings high points. Additionally. design such systems. Standard For Compliance: Shown on approved grading and building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ �6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 71 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of building, permits, Project Sponsor shall submit plans to the Building Department City of Newport Beach demonstrating that all buildings on the Lower Campus are sealed from gas migration. Such sealing may be for compatibility with the existing environmental conditions of the soils and /or potential gases. Standard For Compliance: Shown on approved building 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ i� HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 72 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of building permits. Project Sponsor shall rooms. Sensors can monitor on a continuous basis and can be tied into fire alarm aystems for 24 hour surveillance. Standard For Compliance: Shown on approved building 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 6, HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 73 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: To avoid possible accumulation of Las in utility or other seldom used service or storage rooms Project Sponsor shall submit plans to the City of Newport Beach Building Department prior to issuance of building permits indicating that such rooms are serviced by the buildings' central air conditioning system or an otherwise positive ventilation system that circulates and replaces the air in such rooms on a continuous basis). Standard For Compliance: Shown on approved building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ -7y HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 74 • Timing For Completion: Ongoing Daring Site Preparation and Construction Text of Mitigation Measure: During construction. Project Sponsor shall ensure that an dosimeter is used to monitor methane levels and percentage range. Additionally, construction contractors shall be required to have a health and safety plan that includes procedures for worker /site safety for methane. If dangerous levels of methane are discovered, construction in the vicinity shall stop. the City of Newport Beach Fire Department shall be notified and appropriate procedures followed in order to contain the methane to acceptable and safe levels. Standard For Compliance: Documented in contractor /subcontractor supplemental general Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ iW HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 75 Timing For Completion: Not Specified Text of Mitigation Measure: The Project Sponsor may remove the flare system, contain the gas and utilize the gas for Lower Campus facilities. During the containment process and removal of the flare the Project Sponsor shall ensure that methane levels are monitored throughout the project area to ensure that this transition does not create an upset in methane levels or create odors or risk of explosion, Standard For Compliance: Approved flare removal lan /process Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 9 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 76 Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: a scrubber system to remove hydrogen sulfide from the influent gas to the flare. The design and construction of the system should be in accordance with the Best Available Control Standard For Compliance: Approved flare scrubber system Mans: obtain AQMD permit, as required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ i • HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 77 Timing For Completion: Prior to Relocation of the Flare Text of Mitigation Measure: As required by the District, the project sponsor shall develop Standard For Compliance: Submit sampling and analysis protocol, if required by SCAQMD Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 78 • Timing For Completion: Prior to Approval of Flare Relocation Plans Text of Mitigation Measure: The plans for the design of the new system will include a calibration and maintenance plan for all equipment, and if required by the District as a permit condition, automatic shutdown devices, sensors and charts for continuous recording of monitoring, and flame arresters. The project sponsor shall evaluate enclosing or placing new equipment underground. Standard For Compliance: Shown on approved flare relocation plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ M HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 79 Timing For Completion: Prior to August, 1 96 Text of Mitigation Measure: The project sponsor shall submit plans to the City of Newport Beach Building Department that demonstrate that the flare operation will be shut down within four years of August. 1992. The project sponsor must .prepare and obtain approval from the SCAOMD to implement a sampling and analysis protocol for evaluation of the if engineering design allows, as a supplemental source of fuel for the Hospital's boilers. If the gas is not usable, the flare shall be relocated. Standard For Compliance: Approved flare shut down plans. submit sampling and analysis protocol to SCA MD if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ ED HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 80 Timing For Completion: Prior to Relocation of Flare Text of Mitigation Measure: The plans for the design of the new system will include a calibration and maintenance plan for all equipment, and if required by the District as a permit condition, automatic shutdown devices, sensors and charts for continuous recording of monitoring, and flame arrestors. The project sponsor shall evaluate enclosing or placing new equipment underground. Standard For Compliance: Shown on flare relocation plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ t/ . HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 81 Timing For Completion: Prior to Installation of Scrubbers on Flare Text of Mitigation Measure: Prior to installation of the scrubber system, the project sponsor shall develop a protocol for a study to evaluate the integrity of the control equipment and pining, The roject sponsor must obtain agreement from the District on the protocol prior to initiating the study. Standard For Compliance: Submit control equipment and piping study to SCAOMD, if required Compliance: Citv--of Newport Beach Verification Approved on: Approved by: Signature: _ i HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 79 • Timing For Completion: Prior to August. 1996 Text of Mitigation Measure: The project sponsor shall submit Mans to the City of Newport Beach Building; Department that demonstrate that the flare operation will be shut down existing emissions from the flare after scrubbing (Mitigation Measures 75 & 76). and the effect of flare shutdown on ambient air quality. The methane gas source should be used. Standard For Compliance: Approved flare shut down plans: submit sampling and analy protocol to SCAOMD, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ M HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 80 Timing For Completion: Prior to Relocation of Flare Text of Mitigation Measure: The plans for the design of the new system will include a calibration and maintenance plan for all equipment, and if required by the District as a permit condition, automatic shutdown devices, sensors and charts for continuous recording of monitoring, and flame arrestors. The project sponsor shall evaluate enclosing or placing new equipment underground. Standard For Compliance: Shown on flare relocation plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ IN HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 81 • Timing For Completion: Prior to Installation of Scrubbers on Flare Text of Mitigation Measure: Prior to installation of the scrubber system, the project sponsor to initiating the study_ Standard For Compliance: Submit control equipment and piping study to SCAOMD, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ Gail HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 82 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Before the issuance of building permits, the Project Sponsor 403, Fugitive Dust. Standard For Compliance: Shown on aMroved building 121ans: documented in contractor/ subcontractor supplemental ,general conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ q1 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 83 • Timing For Completion: Prior to the Issuance of Each Building_ Permit Text of Mitigation Measure: Before the issuance of building permits, the project sponsor must submit plans to the City of Newport Beach demonstrating that its Hazardous Materials and Waste Management Plan and its Infectious Control Manual have been modified to include procedures to minimize the potential impacts of emissions from the handling, storage, hauling and destruction of these materials, and that the project sponsor has submitted the modified plans to the City of Newport Beach, Fire Prevention Delartment, and the Orange County Health Care A envy, as required by the Infections Waste Act and Standard For Compliance: Approved revised Hazardous Materials and Waste Management Plan and Infectious Control Manual, if required Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ q2 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: isMitigation Measure: 84 Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: Project Sponsor shall continue compliance with its Hazardous Material and Waste Management Program and its Infectious Control Manual for all new activities associated with the proposed Master Plan, as well as comply with all new regulations enacted between now and completion of the proposed Master Plan._ Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ q3 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 85 . Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: To the satisfaction of the City building official, the Project Sponsor shall expand existing hazardous infectious, radiological disposal facilities to add additional storage areas as necessary to accommodate the additional waste to be generated by the expanded facilities. Standard For Compliance: Shown on approved building 121ans, if required Compliance: City-of Newport Beach Verification Approved on: Approved by: Signature: _ qY HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 86 Timing For Completion: Ongoing During Site Preparation and Construction of Mitigation being carried out. Standard For Compliance: Obtain annual permit from the SCAQMD for re_ ulg ated commercial equipment (see Mitigation Measure No. 36). as required. The above air toxic rules are addressed through the SCAQMD permit process for regulated commercial equipment Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 95 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 87 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: The project sponsor shall submit plans to the City Building Standard For Compliance: Shown on approved building 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 0- HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 88 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: The project sponsor shall submit plans to the City Building Department prior to the issuance of a building_ permit for each phase of development, verifying that energy efficiency will be achieved by incorporating appropriate technologies water heaters. efficient glazing Vstems• appropriate off -hour heatin /cg oolin i hting controls. time clocks and photovoltaic cells for lighting controls: efficient insulation systems; light colored roof and building exteriors: PL lighting and fluorescent lighting systems: motion detector lighting controls: natural interior lighting (skylights, clerestories): and solar orientation, earth berming and landscaping. Standard For Compliance: Shown on approved building-plans Compliance: City of Newport Beach Verification Approved on: Approved by Signature: _ q7 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 89 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: The project sponsor shall demonstrate to the City Building Department that methods and materials which minimize VOC emissions have been employed where practical, available and where value engineering allows it to be feasible.` Standard For Compliance: Shown on approved buildingplans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ i HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 90 Timing For Completion: Prior to Approval of Street Improvement Plans Text of Mitigation Measure: In conjunction with the Critical Care Surgery addition, the Project Sponsor will place the overhead power lines located west of the Upper Campus underground if feasible. Standard For Compliance: Shown on approved street improvement plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ IN HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 91 • Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: Prior to the issuance of grading= permits, emergency fire access to the site shall be approved by the City Public Works and Fire Departments. Standard For Compliance: Shown on approved rg ading plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ X00 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 92 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to the issuance of building permits, the project sponsor sponsor will also comply with any other City adopted water conservation policies. Standard For Compliance: Shown on approved building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ to/ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 93 • Timing For Completion: Prior to Issuance of Each Grading Permit Text of Mitigation Measure: Prior to issuance of Uading permits, a master plan of water and sewer facilities shall be prepared for the site. The Project Sponsor sahll verify the adequacy of existing water and sewer facilities and construct any modifications or facilities necessitated by proposed project development. Standard For Compliance: Approved master plan of water and sewer facilities Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /oz HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 94 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to the issuance of building permits, the project sponsor shall demonstrate, to the satisfaction of the City Fire Department, that all buildings shall be equipped with fire suppression systems. Standard For Compliance: Shown on approved building-plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 103 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 95 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of building permits the project sponsor shall demonstrate to the City Fire Department that all existing and new access roads surrounding Departments. Parallel parking on one side may be permitted if the road is a minimum 32 feet in width. Standard For Compliance: Shown a1212roved building 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /dq HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 96 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of a building permit the project sponsor shall demonstrate to the Citv that the thermal integrity of new buildings are improved with automated time clocks or occupant sensors to reduce the thermal load Standard For Compliance: Shown on approved building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 05 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 97 • Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: Prior to issuance of a building permit, the project sponsor shall demonstrate to the City that window glazing, wall insulation, and efficient ventilation methods have been incorporated into building designs. Standard For Compliance: Shown on approved building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ X06 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 98 Timing For Completion: Prior to the Issuance of Each Building_ Permit Text of Mitigation Measure: Prior to issuance of a building permit, the project sponsor shall demonstrate that building designs incorporate efficient heating units and other appliances, such as water heater, cooking equipment, refrigerators, furnaces and boiler units. Standard For Compliance: Shown on approved building 121ans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 10 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 99 • Timing For Completion: Prior to Issuance of Each Building Permit Text of Mitigation Measure: Standard For Compliance: Shown on approved building plans Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ LI, HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 100 Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: The project sponsor shall ensure that all cut material is development cleared landfill with adequate capad-vL. Standard For Compliance: Approved disposal location Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 10q HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project. Mitigation Measure: 101 • Timing For Completion: Prior to the Issuance of Each Grading Permit Text of Mitigation Measure: In conjunction with the application for a grading permit, the project sponsor shall submit a construction phasing and traffic control plan for each phase of development. This plan would identify the estimated number of truck trips and measures to assist truck trips and truck movement in and out of the local street system i.e., flagmen, signage, etc.). This-plan shall consider scheduling operations affecting traffic during off-yeak hours, extending the construction period and reducing the number of pieces of equipment used simultaneously. The plan will be reviewed and approved by the City Traffic Engineer 12rior to issuance of the grading permit. Standard For Compliance: Approved construction phasing and traffic control plan Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: /1a HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 102 Timing For Completion: Prior to Issuance of Each Grading Permit Text of Mitigation Measure: The Project Sponsor shall ensure that all haul routes for included in the above construction traffic plan. Standard For Compliance: Approved haul routes Compliance. City of Newport Beach Verification Approved on: Approved by: Signature: _ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 103 • Timing For Completion: Ongoing During Site Preparation and Construction Text of Mitigation Measure: The project sponsor shall provide advance written notice of temporary traffic disruptions to affected areas businesses and the public This notice shall be provided at least two weeks prior to disruptions. Standard For Compliance: Documented in contractor /subcontractor supplemental general conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ IIZ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 104 Timing For Completion: Ongoing During Site Preparation and Construction Text of Mitigation Measure: The Project Sponsor shall ensure that construction activities requiring more than 16 truck (i.e multiple axle vehicle) trips per hour, such as excavation and concrete pours, shall be limited between June 1 and September 1 to avoid traffic conflicts with beach and tourist traffic. At all other times, such activities shall be limited to 25 truck (i.e., multiple axle vehicle) trips per hour unless otherwise approved by the City Standard For Compliance: Documented in contractor /subcontractor supplemental general Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 113 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 105 • Timing For Completion: Ongoing During Site Preparation and Construction Text of Mitigation Measure: The Project Sponsor shall ensure that all trucks used for hauling material shall be covered to minimize material loss during transit. Standard For Compliance: Documented in contractor /subcontractor supplemental general conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /�7 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 106 Timing For Completion: Prior to the Issuance of Each Grading Permit: Ongoing During Site Preparation and Grading Text of Mitigation Measure: Standard For Compliance: Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 115 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 107 • Timing For Completion: Prior to the Issuance of Each Grading Permit ermit Text of Mitigation Measure: morning and evening prior to or after earth moving operations. To further reduce dust generation, grading should not occur when wind speeds exceed 25 miles per hour (MPH), and soil binders on SCAOMD approved chemical stabilizers should be spread on construction sites or unpaved areas. Additional measures to control fugitive dust include street sweeping of roads used by construction vehicles, reduction of speeds on all unpaved roads to 15 miles per hours, suspension of operations during first and second stage smog alerts, and wheel washing before construction vehicles leave the site. Standard For Compliance: Documented in contractor /subcontractor supplemental general conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ �/6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 108 Timing For Completion: Prior to the Issuance of Each Grading and Building Permit Text of Mitigation Measure: Prior to issuance of any grading and building permit the project sponsor shall submit a Trip Reduction Plan for construction crew members This plan shall identify measures, such as ride - sharing and transit incentives to reduce vehicle miles traveled by construction crews. The plan shall be reviewed and approved by the City Traffic Standard For Compliance: Approved trip reduction plan Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ r�7 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 109 • Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: Prior to issuance of a grading permit for each phase of construction the project sponsor shall submit an analysis to the City Building Department that documents the criteria emissions factors for all stationary equipment to be used durine that phase of construction The analysis shall utilize emission factors contained in the applicable SCAQMD Handbook The analysis shall also be submitted to the City of Newport Beach Planning Department for review and approval. Standard For Compliance: Approved criteria emission factors based on SCAQMD Handbook Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /1S HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 110 Timing For Completion: Prior to the Issuance of Each Grading and Building Permit Text of Mitigation Measure: The project sponsor shall ensure that low emission mobile and stationary equipment is utilized during construction, and low sulfur fuel is utilized in Standard For Compliance: Documented in contractor /subcontractor supplemental eg neral conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 10 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 111 • Timing For Completion: Ongoing During Site Preparation and Construction Text of Mitigation Measure: The project sponsor shall ensure that all internal combustion engines associated with construction activities shall be fitted with properly maintained mufflers and kept in proper tune. Standard For Compliance: Documented in contractor /subcontractor supplemental general Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /ZD HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 112 Timing For Completion: Ongoing During Site Preparation and Construction Text of Mitigation Measure: The project sponsor shall ensure that construction activities are conducted in accordance with Newoort Beach Municioal Code, which limits the hours of construction and excavation work to 7:00 a.m. to 6:00 p.m. on weekdays, and 8:00 a.m. to 6:0012.m. on Saturdays. No person shall, while engaged in construction, remodeling, digging, grading, demolition, painting, plastering or any other related building g ctivity, operate any too], equipment or machine in a manner that produces loud noise that disturbs, or could disturb, a persons of normal sensitivity who works or resides in the vicini , , on any Sunday or any holiday_ Standard For Compliance: Documented in contractor /subcontractor supplemental eg neral conditions Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 1.2-I HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 113 • Timing For Completion: Subsequent to the Approval of the Development Agreement by the Coastal Commission and the Expiration of Any Statute of Limitation for Filing a Legal Challenge to the Development Agreement. the Master Plan, or the EIR Text of Mitigation Measure: Subsequent to the approval of this Agreement by the Coastal Commission and the expiration of any statute of limitation for filing a legal challenge to this Agreement the Master Plan, or the EIR. Hoag shall deposit Two Hundred and Fifty to access the funds in the event but only to the extent that. Hoag constructs or installs the construction of a sidewalk and installation of landscaping in the CalTrans right -of -way along the west side of Newport Boulevard southerly of Hospital Road; and (ii) The construction of facilities necessary to brims reclaimed water to West Newport and /or the Property: Any Standard For Compliance: Submit $250.000 check Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ t )-z HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 114 Timing For Completion: Prior to the Issuance of a Building Permit Text of Mitigation Measure: Rooftop mechanical equipment screening on the emergency room expansion shall not extend closer than fifteen feet from the west edge of the structure and no closer than ten feet from the edge of the structure on any other side. Standard For Compliance: Shown on approved building plans Compliance: Emergency room expansion completed in 1993. The above - mentioned mitigation measure was included City of Newport Beach Verification Approved on: Approved by: Signature: _ 1z3 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 115 is Timing For Completion: Prior to the Issuance of a Building Permit Text of Mitigation Measure: Noise from the emergency room expansion rooftop mechanical equipment shall not exceed 55 dBA at the property line. Standard For Compliance: Approved acoustical analysis: incorporate mitigation measures, if required Compliance: Emergency room expansion completed in 1993. The above - mentioned mitigation measure was included City of Newport Beach Verification Approved on: Approved by: Signature: _ rzY HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 116 Timing For Completion: Not Specified Text of Mitigation Measure: The Project Sponsor shall lay 75% of the cost of plantine thirty 24 -inch ficus trees (or the equivalent) in the berm between the service road and Villa Balboa southerly of the tennis courts. Planting shall occur on Villa Balboa property. Standard For Compliance: Provide funds for ficus trees Compliance: Check for $5.737.50 paid to Villa Balboa Community Association on February 21.1992. City of Newport Beach Verification Approved on: Approved by: Signature: _ HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 117 • Timing For Completion: Ongoing During Project Operation Text of Mitigation Measure: Use of the heliport/helipad shall be limited to emergency medical purposes or the transportation of critically ill patients in immediate need of medical to the west and south. Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ /Z6 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: • Mitigation Measure: 118 Timing For Completion: Prior to the Issuance of a Building Permit Text of Mitigation Measure: For any building subject to the issuance of the building permit by the Office of the State Architect, Hoag Hospital shall submit to the State Architect a Standard For Compliance: Submit letter from State Architect Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ o--7 A " ' HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 119 • Timing For Completion: Ongoing During Project Operations Text of Mitigation Measure: Non - vehicular activities. such as the operation of the trash compactor, which occur in the vicinity of the service /access road shall be operated only between the hours of 7:00 a.m. and 7:00 p.m. daily. Standard For Compliance: Documented as part of Development Agreement annual review Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ M . .. Project: HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING • Mitigation Measure: 120 Timing For Completion: Within One Year From the Date of Final Approval of the Planned Community District Regulations and Development Plan by the California Coastal Text of Mitigation Measure: Commission, as an interim measure, the project sponsor shall implement an acoustical and /or landscape screen to provide a visual screen from and reduce noise to adjoining residences from the loading doc area. The design process for the Critical Care Surgery Addition shall include an architectural and acoustical study to insure the inclusion of optimal acoustical screening of the loading dock area by--that addition. Subsequent to the construction of the Critical Care Surgery Addition, an additional acoustical study shall be conducted to assess the sound attenuation achieved by that addition. If no significant should attenuation is achieved, the hospital shall submit an architectural and acoustical study impacts along the service access road, enclosure shall be required. Any enclosure required Standard For Compliance: the Cardiac Services Addition City of New aort Beach Verification Approved on: Approved by: Signature: _ 1.2.9 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 121 • Timing For Completion: Prior to the Issuance of a Grading Permit Text of Mitigation Measure: for the subject phase of development This analysis shall utilize the EMFAC7EP emission factor program for the build out year of the subject phase of development, and the CALINE4 CO hot spot model or the model recommended for such analysis at that time. The results of this analysis shall be submitted to the City of Newport Beach Planning Department for review. City staff will verify consistency with the results of the project build out CO analysis. Standard For Compliance: Approved CO hot spot analysis Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 13d I ., HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: ® Mitigation Measure: 122 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: The methane gas facility and all building on the lower campus shall be subject to all laws and regulations applicable, including, but not limited to. the Federal Regulation contained in 29 CFR 1910. the State Health and Safes Code, Division 20, Chapter 6.95, and the regulations of OSHA and the National Fire Protection Association. Prior to the issuance of building permits on the lower campus, the project sponsor shall submit to the Newport Beach Fire Department a compliance review report of all the above referenced laws and regulations. Standard For Compliance: Shown on approved building plans Compliance. City of Newport Beach Verification Approved on: Approved by: Signature: _ 131 HOAG HOSPITAL MASTER PLAN MITIGATION MONITORING Project: Mitigation Measure: 123 Timing For Completion: Prior to the Issuance of Each Building Permit Text of Mitigation Measure: The design of the critical care /surgery addition shall incorporate screening devices for the windows which face the Villa Balboa area for the purpose of Standard For Compliance: Shown on approved building plans. Only applicable to Critical Care Surgery Addition which is no longer being proposed, except that window screening will be provided for Cardiac Services Addition to be shown on interior design Plans as requested by City staff on April 13, 1993. Compliance: City of Newport Beach Verification Approved on: Approved by: Signature: _ 132-