HomeMy WebLinkAbout13 - C-3094 - Buck Gully & Little Corona Beach Outlet Modification• April 12, 1999
CITY COUNCIL AGENDA
ITEM NO. 13
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: BUCK GULLY /LITTLE CORONA BEACH OUTLET MODIFICATION,
CONTRACT NO. 3094 - COMPLETION AND ACCEPTANCE
RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the bonds 35 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil
Code.
. 4. Authorize a budget amendment to appropriate $165,800.62 from the General
Fund Reserve to Tide and Submerged Land Fund Account No. 7231- C5100333.
5. Authorize a budget amendment to reduce the Contributions Fund Account No.
7251- C5100333 by $534,300.
DISCUSSION:
On August 24, 1998, the City Council authorized the award of Buck Gully /Little Corona
Beach Outlet Modification contract to Gillespie Construction, Inc. of Costa Mesa,
California. The contract provided for the reconstruction and repair work of damages at
the Buck Gully outlet caused by the El Nino winter storms of 1997 -98. Work included
the grading of the channel, reconstruction of the weir wall and supporting piers,
placement of rip -rap for bank toe protection, replacement of a sewer pipe line, repair of
concrete stairs and hand rails, construction of a new asphalt concrete roadway and
other items of work. The contract has now been completed to the satisfaction of the
Public Works Department. A summary of the contract cost is as follows:
Original bid amount: $359,762.00
Actual amount of bid items constructed: 362,066.00
Total amount of change orders: 39,259.62
Final contract cost: $401,325.62
• The increase in the amount of actual bid items constructed over the original bid amount
resulted from the need for additional soil importation and grading exceeding the bid
SUBJECT: Buck Gully /Little Corona Beach Outlet Modification, Contract No. 3094 - Completion And Acceptance
April 12, 1999
Page 2
item quantities. The final overall construction cost including change orders was 11.6%
over the original bid amount.
A total of five (5) change orders were issued to complete the project. They were as
follows:
1. A change order in the amount of $21,445.44 provided for the reconstruction of a
slope supporting the roadway near the Buck Gully sewer pump station. The slope
failure was noticed after award of contract.
2. A change order in the amount of $13,091.39 provided for the lengthening of several
piles supporting the weir wall into bedrock.
3. A change order in the amount of $4,363.64 provided for extending a 12 -inch
exposed aluminum storm drain into the Buck Gully riverbed.
4. A change order in the amount of $1,159.15 provided for the placement of an asphalt
berm adjacent to the roadway to prevent water run -off onto a slope.
5. A credit change order in the amount of ($800.00) provided for the reduction of 40
feet of sewer pipe replaced under a lump sum bid item. •
The December 1997 storm washed out the Buck Gully bottom control structure. The
February 1998 storm caused more damage in the mouth of Buck Gully. When
meetings were held with the Federal Emergency Management Agency (FEMA/State
Office of Emergency Services (OES) representatives after these storms, it was
estimated that all of the Buck Gully repairs would be eligible for either FEMA or OES
reimbursement. In the 1998 -99 CIP General Contributions Division, funds were
budgeted in anticipation of receiving $750,000 in FEMA/OES reimbursements. The
$750,000 estimate was based on a field site visit without the benefit of construction
plans. Construction contracts have been awarded for $433,703. In the FEMA/OES
review of the contracts, they have declared many items ineligible for reimbursement.
For this contract, our actual reimbursement will be approximately $147,000 instead of
the budgeted $365,000. A budget amendment is needed to reduce the Contribution
Fund project account to the amount that will be received from FEMA/OES and to
appropriate funds to cover the remaining contract amounts.
The contract will be funded as follows:
Account Name
Account No.
Amount
Tide & Submerged Land Fund
7231- C5100333
$ 36,000.00
Contribution Fund
7251- C5100333
$147,325.00
Sewer Master Plan Improvement
7531- C5600292
$ 52,200.00
Unappropriated General Fund Reserve
$165,800.62
Total
$401,325.62
\WIS_t \SYS\ Users\ PBMShamd \COUNCILTY98'9Mpn1- 12\Buck Gully C-3094.dw
•
SUBJECT: Buck Gully /Little Corona Beach Outlet Modification, Contract No. 3094 - Completion And Acceptance
April 12, 1999
Page 3
• The budget amendment is needed for the following actions:
Reduce the Contributions Account No. 7251- C5100333 by $534,300.
Appropriate $165,800.52 from the General Fund Reserve to Account No. 7231 -
05100333.
The $534,300 reduction in the Contributions Fund account makes the adjustment
needed to reflect the estimated reimbursement and $316,297.75 over estimate in
project costs. When the final disbursements from FEMA/OES are made, more
adjustments may need to be made.
The scheduled completion date for the Buck Gully /Little Corona Beach Outlet
Modification was November 13, 1998. Due to inclement weather and extra work, the
project was extended to January 7, 1999.
Resp lly submitted
PUBLIC WORKS DEPARTMENT
Don Webb, Director
•
By:
Horst Hlawaty, P.E.
Construction Engineer
11
\ \MIS 1\SVS \USerS1 BW\ShdreMCOVNCIL\FV98-99W.p6l . lZS.lk Wily C•3094AM
City of Newport Beach NO. BA- 057
BUDGET AMENDMENT
1998 -99 AMOUNT: $218,000.52
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates Increase in Budgetary Fund Balance
X Increase Budget Appropriations AND X Decrease in Budgetary Fund Balance
X Transfer Budget Appropriations No effect on Budgetary Fund Balance
X from existing budget appropriations
from additional estimated revenues
X from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
To reduce contributions to the actual amount expected from FEMA/OES and appropriate funds to cover the remaining contract
amount. There was a prior budget amendment to Buck Gully /Little Corona Beach Outlet capital project in the amount of
543.250 in June 1998.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account
Tidelands 230 3605
Contributions 250 3605
REVENUE APPROPRIATIONS (3601)
Fund /Division Accountt
EXPENDITURE APPROPRIATIONS (3603)
Description
Fund Balance Control
Fund Balance Control
Description
Signed:
Signed:
Amount
Debit Credit
$165,800.52
$534,298.27
$52,200.00
Aufomafic
534,298.27
$165,800.52
$52,200.00
�Date_
Date •
Signed:
City Council Approval: City Clerk Date
Description
Division
Number
7251
Contribution
Account
Number
C5100333
Buck Gully /Little Corona Beach Outlet
Division
Number
7531
Sewer Main Replacement
Account
Number
C5600292
Sewer Main Master Plan Improvement
Division
Number
7231
Tidelands - Capital
Account
Number
C5100333
Buck Gully /Little Corona Beach Outlet
Division
Number
7531
Sewer Main Replacement
Account
Number
C5100333
Buck Gully /Little Corona Beach Outlet
Division
Number
Account
Number
Signed:
Signed:
Amount
Debit Credit
$165,800.52
$534,298.27
$52,200.00
Aufomafic
534,298.27
$165,800.52
$52,200.00
�Date_
Date •
Signed:
City Council Approval: City Clerk Date