HomeMy WebLinkAbout07 - 1998-99 Sidewalk, Curb & Gutter Replacement (C-3227)11 • July 12, 1999 CITY COUNCIL AGENDA ITEM NO. 7 TO: Mayor and Members of the City Council FROM: Public Works Department SUBJECT: 1998 -99 SIDEWALK, CURB AND GUTTER REPLACEMENT - COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3227 RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the bonds 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. DISCUSSION: On February 22, 1999, the City Council authorized the award of the 1998 -99 Sidewalk, Curb and Gutter Replacement project to JDC, Inc., of Rancho Cucamonga, California. The contract provided for the reconstruction of sidewalk, curb and gutter, cross - gutter, and root pruning of 160 City trees within the City's Westcliff, Harbor Highlands and Dover Shores communities. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $86,445.00 Actual amount of bid items constructed: 86,445.00 Total amount of change orders: 14,268.37 Final contract cost: $100,713.37 Due to a favorable bid on the sidewalk bid item, a significant amount of sidewalk reconstruction was added to the project. To cover the cost of the extra improvements, a change order in the amount of $14,268.37 was authorized by the City Manager. The final overall construction cost, including the change order, was 16.5% over the original bid amount. SUBJECT: 1998.99 SIDEWALK, CURB AND GUTTER REPLACEMENT -COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3227 July 12, 1999 Page 2 Funds for the project were budgeted in the following funds: Description Account Number Amount General Fund (Sidewalk, C &G Rep. Prog.) 7013- C3130016 $ 54,095.00 Gas Tax (Sidewalk, C &G Rep. Prog.) 7181- C3130016 46.618.37 TOTAL $100,713.37 All work was completed by May 28, 1999, ahead of the June 7, 1999 scheduled completion date. Respectfully submitted, PUBLIC WORKS DEPARTMENT Don Webb, Director By: r %lLccuJ Horst Hlawaty, P.E. Construction Engineer 0 0 \VAS nsv"u NPeW%ShamdCOUNCaI YN-00vwr+zse -s9 Slde lkC -1=Ax