HomeMy WebLinkAbout08 - C-3206 Newport Pier RepairsJuly 26, 1999
CITY COUNCIL AGENDA
ITEM NO. 8
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: 1998 -99 NEWPORT PIER REPAIRS - COMPLETION AND
ACCEPTANCE OF CONTRACT NO. 3206
RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the bonds 35 days after the Notice of
Completion has been recorded in accordance with applicable portions of the Civil
Code.
DISCUSSION:
On April 12, 1999, the City Council authorized the award of the 1998 -99 Newport Pier
Repairs contract to John S. Meek Company of Wilmington, California. The contract
provided for the repair work to the pier including the replacement of five (5) wood piles.
The contract has now been completed to the satisfaction of the Public Works
Department. A summary of the contract cost is as follows:
Original bid amount: $189,975.00
Actual amount of bid items constructed: 172,709.00
Total amount of change orders: 15,200.00
Final contract cost: $187,909.00
The decrease in the amount of actual bid items constructed over the original bid
amount resulted from a reduced amount of polyethylene pile wrap placed as measured
in the field. The final overall construction cost including change orders was 1.1 % under
the original bid amount.
The following two (2) change orders were issued to complete the project:
A non - compensatory change order provided for a 23 working day time extension due to
unavailability of pile wrap material.
A change order in the amount of $15,200.00 provided for installing two additional piles
at the unit cost. Following removal of the marine growth during construction, these piles
were found to be severely damaged.
SUBJECT: 1998 -99 Newport Pier Repairs -Completion And Acceptance of Contract No. 3206
July 26, 1999
Page 2
Funds for the project were budgeted in the Tideland & Submerged Land Fund - Account
No. 7231- C5100153 (Newport/Balboa Pier Inspection /Replacement).
The original scheduled completion date was May 28, 1999. Due to extra work and the
approved time extension, the project was Completed on July 9, 1999.
Respectfully submitted,
PUBLIC WORKS DEPARTMENT
Don Webb, Director
By:
Horst Hlawaty, P.E.
Construction Engineer
•