Loading...
HomeMy WebLinkAbout12 - BA-003 C-3311 - San Miguel Drive Roadway ImprovementsJuly 24, 2001 CITY COUNCIL AGENDA ITEM NO. 12 TO: Mayor and Members of the City Council FROM: Public Works Department SUBJECT: SAN MIGUEL DRIVE ROADWAY IMPROVEMENTS, CONTRACT NO. 3311 -COMPLETION AND ACCEPTANCE RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond 1 year after Council acceptance. 5. Authorize a budget amendment transferring $43,100 from the unappropriated Circulation and Transportation Fund Balance to Account No. 7261- C5100535. DISCUSSION: On June 27, 2000, the City Council authorized the award of the San Miguel Drive Roadway Improvements contract to Holland -Lowe Construction Inc., of San Bernardino, California. The project was an Orange County Transportation Authority (OCTA), Measure -M sponsored project and consisted of: • A six -foot roadway widening • Median with dual left turn lanes • Pavement, sidewalk, curb and gutter • Curb access ramps reconstruction • Catch basin, storm drain, and traffic signal system modifications • Street light and fire hydrant relocation • New pavement striping and markings installed for San Miguel Drive between Avocado Avenue and MacArthur Boulevard The project provided an additional left turn lane for westbound San Miguel Drive traffic turning onto southbound Avocado Avenue. The Irvine Company (TIC) provided an easement for the roadway widening work in consideration of the installation of parkway SUBJECT: San Miguel Drive Roadway Improvements, Contract No. 3311 -completion And Acceptance July 24, 2001 Page 2 landscaping along both sides of San Miguel Drive. TIC will maintain these requested improvements. A pre- construction meeting for the project was held on August 31, 2000, and at that time the contractor's schedule called for completion of the project during the second week of December 2000 due to the lead -time required for purchase of the traffic signals. Due to the fact that construction during the holiday season within Newport Center was deemed unacceptable, the City postponed the start of construction until January 18, 2001. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract costs follows: Original bid amount: $213,728.00 Actual amount of bid items constructed: 230,629.14 Total amount of change orders: 40,625.30 Final contract cost: $271,254.44 The increase in the amount of actual bid items constructed over the original bid amount resulted from the need for additional excavation, traffic loops, Type B curb, concrete sidewalk, and asphalt pavement exceeding the bid item quantities. The final overall construction cost, including change orders, was 26.9 percent over the original bid amount. Since the construction costs exceeded the 125 percent threshold of the original contract, the additional expenditure requires Council approval pursuant to the Council Policy Manual. A total of eight change orders were issued to complete the project. They were as follows: 1. $6,742.50 provided for the increased labor and materials costs due to the postponement of the contract start date. 2. $1,201.07 provided for the potholing of underground utilities. 3. $10,205.97 provided for the relocation of two electrical service cabinets and one irrigation service cabinet. 4. $2,589.00 provided for the installation of three additional traffic information signs. 5. $8,095.67 provided for one new electrical service cabinet and the grinding of asphalt within the median. 6. $5,754.02 provided for the underground boring and replacement of a 2 -inch traffic signal conduit. 7. $1,737.07 provided for the removal and replacement of additional curb and gutter. 8. $4,300.00 provided for the grinding and removal of existing traffic striping. SUBJECT: San Miguel Drive Roadway Improvements, Contract No. 3311 -Completion And Acceptance July 24, 2001 Page 3 Funds for the project were budgeted in the following accounts: Description Account No. Amount San Miguel Drive Improvements 7284- C5100535 $93,922.00 San Miguel Drive Improvements 7261- C5100535 $177,332.44 Total $271,254.44 The original scheduled completion date was March 22,2001. Due to weather delays, underground utility potholing, utility service cabinet relocations, grinding of the asphalt below the median, and underground boring of the traffic signal conduit, the work was extended to June 8, 2001. All work was completed by the revised completion date. Respectfully submitted, P BLIC WO DEPARTMENT Steve Badum, Director By: CA- 6'w'glv2.V R. Gunther, P.E. Construction Engineer City of Newport Beach BUDGET AMENDMENT 2001 -02 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates X Increase Expenditure Appropriations Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues NX from unappropriated fund balance EXPLANATION: NO. BA- 003 AMOUNT: $43,100.00 Increase in Budgetary Fund Balance AND X Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance This budget amendment is requested to provide for the following: To increase expenditure appropriations by $43,100 for San Miguel Drive Roadway Improvements, Contract No. 3311 - Completion and Acceptance. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account 260 3605 REVENUE ESTIMATES (360 1) Fund /Division Account EXPENDITURE APPROPRIATIONS (3603) Division Number Account Number Division Number Account Number Division Number Account Number Division Number _ Account Number Division Number Account Number Signed: Signed: Signed: Description Fund Balance Description Description 7261 Trans and Circulation C5100535 San Miguel ImprvmVAvocado /McArthur Administrative Approval( City Manager City Council Approval: City Clerk Amount Debit Credit $43,100.00 $43,100.00 Date Date