HomeMy WebLinkAbout31 - C-3312 - Ocean Pier RehabilitationSeptember 25, 2001
CITY COUNCIL AGENDA
ITEM NO. 31
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: OCEAN PIER REHABILITATION, CONTRACT NO. 3312 — AWARD
OF CONTRACT
RECOMMENDATIONS:
1. Award Contract No. 3312 to John S. Meek Company, Inc. for the Total Bid Price
of $2,699,440, and authorize the Mayor and the City Clerk to execute the
contract.
2. Establish an amount of $200,560 to cover the cost of testing and unforeseen
work.
3. Authorize a Budget Amendment for the following:
A) Appropriate Oil Spill Fund interest earnings in the amount of $324,000 to
Account No. 7295- C5100565.
B) Appropriate $200,000 from the unappropriated balance of the Water
Enterprise Fund to Account No. 7501- C5100565.
C) Appropriate $50,000 from the unappropriated balance of the Wastewater
Enterprise Fund to Account No. 7501- C5100565
D) Transfer $249,000 from Ocean Front Walkway Project Account No. 7295 -
05100568 to Account No. 7295- C5100565.
DISCUSSION:
On July 11, 2000, the City Council approved a Professional Services Agreement with
Noble Consultants, Inc., to prepare plans and specifications for rehabilitating the
Newport and Balboa Piers. Staff from General Services, Utilities, Fire and Lifeguard
Operations, and Public Works provided input into the project. Public Works Staff also
met with the Assistant City Manager and representatives from the restaurants on
each pier to establish the most favorable period for construction, especially the pier
closure period. Furthermore, Staff has made every effort to foresee and mitigate
coordination issues between the pier work and other construction projects that are
scheduled to be under construction concurrent with the pier work.
SCOPE OF WORK:
The City's 60 -year old ocean piers are in need of their biennial repairs, plus a
SUBJECT: OCEAN PIERS REHABILITATION, CONTRACT NO. 3312 —AWARD OF CONTRACT
September 25, 2001
Page 2
complete rehabilitation to restore their original structural integrity and provide an
additional service life of approximately 20 years. The base contract items include:
• Removing and replacing pier gates and signs
• Replacing 15 defective piles, various stringers, pile caps, hair pins, bolts, and
cross bracing
• Removing abandoned wiring and utility conduits
• Reinstalling all communication, power, gas, water, and sewer conduits under
the deck or within "pipe chases" in the deck to facilitate future access
• Installing a 4 -inch fire main on Balboa Pier
• Repairing the roof of the Lifeguard Workshop (under Newport Pier)
• Rehabilitating the lifeguard boat access way (also under Newport pier)
• Replacing the timber subdeck and the concrete deck on both piers
• Replacing the pipe handrail on Balboa Pier with a wooden handrail
• Replacing fishing benches and cutting boards on both piers
• Installing signs prohibiting vehicles weighing more than 3 tons (6,000 pounds)
from using the piers
PROJECT SCHEDULE
Upon execution of the contract documents, the contractor will order replacement
timber members and piles. Certain items of construction could commence as soon
as November 1, 2001. Construction will then continue for approximately 5 months,
with deck and handrail replacement being performed during the latter stages of work.
The final items of work will be to reinstall sinks, cutting boards, benches, gates, and
signs.
For safety, the piers must be closed to the public during deck and railing
replacement. Each pier closure will be limited to a two -month period. In addition,
because the new deck is thicker than the existing deck, one -inch "down" ramps must
be built within each door into Ruby's Restaurant. The City will reimburse Ruby's for
constructing their three ramps. No ramps are needed at Newport Seafood since the
restaurant floor is elevated above the deck.
Work at Balboa Pier will be performed concurrent with the Balboa Pier restroom
reconstruction and Phase 1 of Balboa Village construction. The pier contractor will
use a portion of the Balboa parking lot for staging pile replacement, but must vacate
the area by April 1, 2002, for parking lot reconstruction under the Balboa Village
contract. The pier restroom contractor will be using a portion of the A Street parking
lot for his staging area (see attached Location Map).
PROJECT COST:
Noble's Engineer's Estimate provided for constructing the contract items listed above.
At 11:00 A.M on September 12, 2001, the City Clerk opened and read the following
bid for this project:
SUBJECT: OCEAN PIERS REHABILITATION, CONTRACT NO. 3312 —AWARD OF CONTRACT
September 25, 2001
Page 3
BIDDER TOTAL BID AMOUNT
Low John S. Meek Company, Inc. $2,699,440
The low total bid amount is 26 percent above the Engineer's Estimate of $2,140,000.
The low bidder, John S. Meek Company, Inc., possesses a General Engineering
Contractor "A" license and has satisfactorily performed previous contract work for the
City.
Although there are relatively few qualified marine contractors on the West Coast,
Staff believed that the project would draw several qualified bids. Staff contacted
several potential marine contractor bidders and discovered that most of these
specialty contractors were currently overloaded with existing projects. Several stated
that they did not have the ability to take on additional work, especially a project with a
tight timetable such as our project. The low bid of $2,699,440 was higher than
anticipated. This cost is most likely predicated upon rehabilitating both piers within a
five -month construction period along with the current market situation.
Upon award of the construction contract, Staff may retain supplemental construction
inspection services to assist City Staff in managing this project to ensure the project
schedule. The design consultant, Noble, is already under contract to provide shop
drawing reviews and plan clarifications to the construction manager. The project will
also involve considerable involvement from Public Works, General Services, and
Utilities Departments.
CONSTRUCTION FUNDS:
The project is being funded with proceeds from the City's $4,770,000 settlement of
the 1990 American Trader oil spill (Oil Spill Fund). The City has allocated $2,077,000
(44 percent) of its portion of the settlement for pier rehabilitation. Additionally,
interest earnings within the Oil Spill Fund are currently available in the amount of
$324,000. Due to the need to reconstruct the existing utilities serving the pier
restaurants and to repair /add fire suppression water mains to the project, funds in the
amount of $200,000 from the Water enterprise Fund and $50,000 from the
Wastewater Enterprise Fund should be appropriated to cover the additional costs.
The City Council may elect to divert some of the proceeds allocated for other oil spill
remediation projects into the pier allocation. It should be noted that approximately
$200,000 of additional interest earnings is projected to be available by June 2002.
Other projects include Corona del Mar Beach Improvements ($476,000), Ocean
Front Walkway and Lighting ($449,000), Beach Access Walkways ($290,000),
Lifeguard Communications Center Improvements ($500,000), and Marine Education
Facility ($500,000).
Staff recommends transferring $249,000 from the Ocean Front Walkway and Lighting
project to this Ocean Pier Rehabilitation project. As additional interest earnings
become available, the Ocean Front Walkway project can be the target for
reappropriation. In addition, if savings are achieved in other Oil Spill projects, these
funds can be reappropriated to the Ocean Front Walkway project.
SUBJECT: OCEAN PIERS REHABILITATION, CONTRACT NO, 3312 —AWARD OF CONTRACT
September 25, 2001
Page 4
Total estimated construction costs are:
Base Bid $2,699,440
Contingency (7.5 percent) 200,560
Total Estimated Construction Cost $2,900,000
The following accounts are available for construction:
Account Description
Newport/Balboa Pier Rehabilitation
Oil Spill Fund Interest Earnings
Water Enterprise Fund
Ocean Front Walkway
Respectfully subnutte-d,-
PUBLIC WORKS DEPARTMENT
Stephen G. Badum, Director
By: zr� ;:
Lloyd Dalton, P.E.
Design Engineer
Attachment: Location Map
Account Number
7295- C5100565
Fund Balance
7501- C5100565
7295- C5100568
Total
Amount
$ 2,077,000
$ 324,000
$ 250,000
$ 249,000
$ 2,900,000
0 ®® f
N ;/
ao ;,
QO
���m� ��' ; -= " " mod :;�
(L w
w
�41
0
City of Newport Beach
BUDGET AMENDMENT
2001 -02
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
X Increase Expenditure Appropriations
Transfer Budget Appropriations
SOURCE:
X from existing budget appropriations
from additional estimated revenues
X from unappropriated fund balance
EXPLANATION:
NO. BA- 008
AMOUNT: $az3,000.00
Increase in Budgetary Fund Balance
AND X Decrease in Budgetary Fund Balance
No effect on Budgetary Fund Balance
This budget amendment is requested to provide for the following:
To increase expenditure appropriations to cover testing and unforeseen work related to the Ocean Pier Rehabilitation
Contract No. 3312.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Description
Fund
Account
Description
295
3605
Misc Restricted Revenue Fund Balance
500
3605
Water Fund Balance
REVENUE ESTIMATES (3601)
Number C5100565 Newport & Balboa Pier Rehabilitation
$573,000.00
Fund /Division
Account
Description
EXPENDITURE APPROPRIATIONS (3603)
Amount
Debit Credit
$324,000.00
$250,000.00
Description
Division
Number 7295 Misc Restricted Revenue
Account
Number C5100568 Ocean Front Walkway
$249,000.00
Division
Number 7295 Misc Restricted Revenue
Account
Number C5100565 Newport & Balboa Pier Rehabilitation
$573,000.00
Division
Number 7501 Distribution & Piping
Account
Number C5100565 Newport & Balboa Pier Rehabilitation
$250,000.00
Division
Number
Account
Number
Division
Number
Account
Number
' Autom tfa System Entry.
Signed:
Financial proval: Administrative 5ervices Director
Date
Signed:
.
Administrative Appr al: City Manager
ffate
Signed:
City Council Approval: City Clerk
Date