CITY COUNCIL AGENDA
ITEM NO. 12
TO: Mayor and Members of the City Council
FROM: Public Works Department
SUBJECT: COOPERATIVE AGREEMENT BETWEEN THE CITY OF COSTA MESA
AND THE CITY OF NEWPORT BEACH FOR THE CONSTRUCTION OF
MEDIAN LANDSCAPING AND HARDSCAPE IMPROVEMENTS ON
IRVINE AVENUE BETWEEN WESTCLIFF DRIVE AND DOVER DRIVE,
CONTRACT NO. 3279
RECOMMENDATION:
Approve the Cooperative Agreement (Agreement) between the City of Newport Beach
(Newport Beach) and the City of Costa Mesa (Costa Mesa) for the construction of
median landscaping and hardscape improvements on Irvine Avenue between Westcliff
Drive and Dover Drive, and authorize the Mayor and the City Clerk to execute the
Agreement.
DISCUSSION:
Staff requests City Council approval of the Agreement for the construction of median
landscaping and hardscape improvements along Irvine Avenue between Westcliff Drive
and Dover Drive. The improvements include stamped colored concrete, concrete
slough walls, trees, shrubs, ground cover, and irrigation systems.
The City boundary between Newport Beach and Costa Mesa within the project limits
generally exists along the centerline of Irvine Avenue, and therefore this project
involves the cities of Newport Beach and Costa Mesa. Prior to constructing the
proposed improvements, the Agreement must be executed by both the Newport Beach
and Costa Mesa City Councils. The Costa Mesa City Council authorized its Mayor to
sign the Agreement on June 3, 2002.
The Agreement outlines the administrative, construction, and maintenance costs and
responsibilities for Newport Beach and Costa Mesa. Newport Beach will supervise the
construction of this project within the budgets and schedules established by both cities.
The project plans, specifications, and cost estimates have been reviewed and approved
by both cities. Construction will begin in late June 2002, and should be completed by
mid - August 2002, prior to the start of fall session at Mariners Elementary School.
The total cost for the project is estimated at $192,000, which includes a 10 percent
contingency. Costa Mesa will reimburse Newport Beach for their share of the
SUBJECT; COOPERATIVE AGREEMENT BETWEEN THE CITY OF COSTA MESA AND THE CITY OF NEWPORT
BEACH FOR THE CONSTRUCTION OF MEDIAN LANDSCAPING AND HARDSCAPE IMPROVEMENTS ON
IRVINE AVENUE BETWEEN WESTCLIFF DRIVE AND DOVER DRIVE, CONTRACT NO. 3279
June 11, 2002
Page 2
construction costs estimated at $85,000. The total cost for construction administration,
survey, testing, and inspection is estimated at $20,000 of which Costa Mesa would be
responsible for $10,000.
The total annual irrigation and maintenance costs for the median improvements are
estimated at $6,000. Costa Mesa will reimburse Newport Beach for 50 percent of the
total annual cost at approximately $3,000. Costa Mesa is not currently contributing to the
maintenance of the existing medians and trees.
The contract for this work will be awarded this fiscal year. Funding is provided in the
current Capital Improvement Program budget.
Respectfully submitted,
-- �, /
PUBLIC WORKS DEPARTMENT
Stephen G. Badum, Director
i
By: 411—
Fong e, P.E.
Project Manager
Attachments: Agreement
Project Location Map
IRVINE AVENUE MEDIAN IMPROVEMENTS (C -3279
,
c� FIRE
STA TION
m
0 P
MARINERS
SCHOOL
sue.
�FFT SHOPPING
/ PLAZA
s�
CORONADO AT
NEWPORT APARTMENTS
�6
y
s].
LEGEND
® WORK LOCATION
L OCA TION MAP
N. Ts
COOPERATIVE AGREEMENT
For
Irvine Avenue Median Improvements from Westcliff Drive to Dover Drive
This Agreement is made and entered into this day of , 2002, by and
between the CITY OF NEWPORT BEACH ( "Newport Beach ") and the CITY OF COSTA MESA
( "Costa Mesa "):
RECITALS
WHEREAS, the median improvements as more particularly described in Exhibit "A ", attached
hereto and incorporated herein by this reference, on Irvine Avenue between Westcliff Drive and
Dover Drive (the "Project "), is a project that involves both the cities of Newport Beach and Costa
Mesa because the city boundary line between the two cities exists along the centerline of said
medians on Irvine Avenue.
WHEREAS, the parties acknowledge that the medians currently contain numerous eucalyptus trees
(the "Trees') that are currently existing and heretofore maintained by Newport Beach and shall
remain the sole responsibility of Newport Beach.
CONTRACT TERMS AND CONDITIONS
Newport Beach will supervise the construction of the Project to the best of its ability within the
established budget and time frame, and shall implement and complete the Project under
guidelines established jointly by Newport Beach and Costa Mesa, and will follow all public bid
and contract procedures.
2. The terms of this Agreement cover the administrative responsibilities and cost allocation for
said responsibilities of the parties with regard to the Project, but not the actual construction of
the Project itself,. although Newport Beach will be responsible for and cause the actual
construction of the Project to be completed.
3. Costa Mesa has reviewed and signed the final design drawings and reviewed the engineer's
construction cost estimate (Attachment `B "). Costa Mesa shall receive a complete breakdown
of the construction costs of the apparent low bidder prior to award by the City of Newport
Beach. If the low bid is more than six percent (6 %) above the engineer's estimated cost for
Costa Mesa, Costa Mesa reserves the right to terminate this Agreement. If the bid is awarded,
Newport Beach shall provide Costa Mesa with a complete breakdown of the actual costs prior to
invoicing Costa Mesa, and Costa Mesa shall be invoiced for its proportional share of the costs
incurred by Newport Beach upon completion of the construction work.
4. Subject to prior approval by Costa Mesa of the construction contract award, Costa Mesa will
reimburse Newport Beach for Costa Mesa's share of forty -five percent of the construction costs
(estimated at $85,000) and half of the costs for construction administration, survey, testing, and
The effective date of any notice or written communications sent by one party to the other shall
be the date received if by personal service, the time of transmission if such communication is
sent by facsimile; or 48 hours after deposit in the U.S. Mail as reflected by the official U.S.
postmark.
11. Each of the parties agrees to do all things in a timely manner reasonably necessary or
convenient to carry out the spirit, intentions and objectives described in this Agreement whether
or not expressly prescribed herein and no consent, agreement, approval, concurrence, decision,
determination or action shall be unreasonably withheld by either party.
12. Prior to filing any legal action because of controversy or claim arising out of this Agreement or
alleged breach thereof the parties agree that they shall first attempt resolution of said
controversy or claim through voluntary mediation or as otherwise designated in writing by the
City Manager of Newport Beach and the City Manager of Costa Mesa. Said City Managers
shall be the selected representatives of each City to act in each respective City's behalf with
respect to any controversy or claim arising out of this Agreement.
13. Except as specified in paragraph 14 herein below, each party shall defend, indemnify, hold free
and harmless the other party, its elected officials, its officers and employees, from and against
any and all liability, claims, losses and demands, including attorney's fees and other reasonable
costs incurred in defending any such claim, whether resulting from court action or otherwise,
arising out of the acts, errors or omissions of the indemnifying party, its employees and/or
authorized subcontractors, whether intentional or negligent, in the performance of this
Agreement.
14. The City of Newport Beach shall defend, indemnify, hold free and harmless Costa Mesa, its
elected officials, its officers and employees, from and against any and all losses, damages,
liability, claims, allegations of liability, suits, costs and expenses, including attorney's fees and
other reasonable costs incurred in defending any such claim, for. damages of any nature
whatsoever, including, but not limited to, bodily injury, death, personal injury, property damage,
or any other claims directly attributable to or caused solely by the existing Trees.
15. This Agreement represents the entire understanding of the parties as to those matters contained
herein, and no prior oral or written understanding shall be of any force or effect with respect to
those matters covered in this Agreement. This Agreement shall be governed by and construed
in accordance with the laws of the State of California, and construed as if drafted jointly by
Newport Beach and Costa Mesa. This Agreement may be amended at any time by the mutual
consent of the parties by an instrument in writing.
16. The persons executing this Agreement on behalf of the parties hereto warrant that they are duly
authorized to execute this Agreement on behalf of said parties and that by so executing this
Agreement the parties hereto are formally bound to the provisions of this Agreement.
This Agreement shall be made effective upon execution by both parties and shall remain in effect
until both parties agree to amend or terminate it.
3
inspections (estimated at $10,000). Newport Beach will be responsible for the remaining fifty -
five percent of the construction costs (estimated at $100,000) and half of the costs for
construction administration, survey, testing, and inspections. The total cost of this project for
Costa Mesa is estimated at $95,000. Newport Beach will invoice Costa Mesa when the Project
is complete and Costa Mesa shall make payment to Newport Beach within thirty days of the
invoice.
5. Change orders affecting Costa Mesa shall be reviewed and approved by Costa Mesa prior to
Newport Beach granting approval to the contractor.
6. After construction of the Project has been completed, Newport Beach will arrange for and
supervise the irrigation and maintenance of the improved medians (initially estimated at $6,000
per year). Costa Mesa will reimburse 50% of the total annual maintenance cost (Costa Mesa's
share estimated at $3,000 per year) to Newport Beach annually and within thirty days of receipt
of an invoice from Newport Beach. Within 30 days of request from Costa Mesa, Newport
Beach shall provide Costa Mesa with an accounting of said maintenance costs with supporting
documentations for the annual invoice. Notwithstanding the above, Costa Mesa shall not be
responsible for any extraordinary costs associated with the existing Trees. Extraordinary costs
include, but are not limited to, any costs for removal, trimming, disease control, replacement, or
other costs directly attributable to the maintenance of said Trees.
7. Inspectors and/or engineers from both Cities will coordinate for construction inspections and a
site walk prior to Project completion.
8. As referenced in the Drawings, Special Provisions, Proposal and Contract for the Project, "City"
shall refer to Newport Beach and the contract responsibilities held by Newport Beach.
9. Newport Beach shall require that the independent contractor provide all necessary insurance
coverage for construction work, as specified in Section 6 -1 of the Special Provisions and
Section G of the Contract for the Project. Newport Beach and Costa Mesa shall be named as
additionally insured parties in the Special Provisions and Contract for the Project, and shall be
insured for the amounts specified in Section 6 -1 of the Special Provisions and Section G of the
Contract.
10. The following staff members, or as otherwise designated in writing by the City Manager of
Costa Mesa or the City Manager of Newport Beach, shall be the selected representatives of each
City to act in each respective City's behalf with respect to this Agreement. Any notices,
requests, approvals, or communications concerning this Agreement or the work hereunder may
be provided by personal delivery, facsimile or first class U.S. Mail and shall be addressed to
each representative as noted below:
To Newport Beach:
William Patapoff
Public Works Department
P.O. Box 1768
Newport Beach, CA 92658 -8915
(949) 644 -3311
2
To Costa Mesa:
Bruce Hartley
Public Services Department
P.O. Box 1200
Costa Mesa, CA 92628 -1200
(714) 754 -5164
IN WITNESS WHEREOF, Newport Beach and Costa Mesa have caused this Agreement to be
executed by its duly authorized officers and representatives, respectfully, on this day of
2002.
CITY OF NEWPORT BEACH
By: Tod W. Ridgeway, Mayor
By: City Clerk
APPROVED AS TO FORM:
By: City Attorney
CITY ` COSTA MESA
By:' i inda Dixon,
^.By: City Clerk
Pu7y
4
APPROVED AS TO FORM:
y: City Attorney