HomeMy WebLinkAboutManager's_Report (18)Manager's Re
ort
December 8, 2010
Harbor Resources
C4 �:
Dredging — Rhine Channel
POLB schedule has been delayed by a couple months
Rhine material needed July 2011
Design plans are 99% complete
City has postponed going to bid until final logistic details
are resolved with the POLB to avoid costly change
orders later
Allows more planning
Possible bid release January 2011?
Coastal Commission postponed till January — giving
Coastal staff more time to prepare
Add temporary moorings and floating docks in H and K
fields for dislocated Rhine vessels
AL
LyF
Log Boom
Log Boom back at its most effective position at
North Star Beach
Traps debris before it enters the Lower Bay
Regularly maintained by General Services who
corals the debris, dries it on the beach and hauls
away.
Boom previously relocated near the Coast Highway
Bridge during the Upper Bay dredging project for
safety reasons
e.
Balboa Marina Public Access Slips
■ Harbor Commission reviewed concept plans on October 20
Irvine Company and City staff met with Linda Isle residents on November 9.
* Next Steps
Irvine Company requests a
pre -HC meeting with 3
Harbor Commissioners in
mid January to review final
plans
HC to officially review
project at the February
meeting
Other Issues
Balboa Island Bulkhead Report
Current under final review by Public Works
staff
Bay Island Project
No movement on this project from Harbor Resources
perspective.
Still need Coastal Commission approval.
Next Meeting
Wednesday, January 12, 2011
6:00 pm
Council Chambers
For More Information
http://www.newportbeachca.gov/HarborResources
Chris Miller, Harbor Resources Manager
❑ cmiller @newportbeachca.gov
❑ (949) 644 -3043
Shannon Levin, Harbor Resources Supervisor
❑ shannon @newportbeachca.gov