HomeMy WebLinkAbout19 - Santa Ana Heights Fire Station & Training CenterCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 19 May 9, 2006 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Lloyd Dalton, PE 949 -644 -3328 or Idalton @city.newport- beach.ca.us SUBJECT: SANTA ANA HEIGHTS FIRE STATION AND TRAINING CENTER — CONTRACT NO. 3626 RECOMMENDATIONS: 1. Approve the plans and specifications. 2. Affirm the categorical exemption from provisions of the California Environmental Quality Act (CEQA). 3. Approve a budget amendment appropriating $4,542,397 from the General Fund Capital Improvement Reserves to account 7456- C2320669 representing the General Fund contribution to the project. 4. Award Contract No. 3626 to Bemards Bros., Inc., for the Total Bid Price of $6,495,000, and authorize the Mayor and the City Clerk to execute the contract. 5. Establish an amount of $650,000 to cover the cost of testing, unforeseen work and permits and an amount of $227,397 for construction management by GKK Works. 6. Direct the City Manager to ensure that the General Fund contribution to this Project is reimbursed by funds from the Santa Ana Heights redevelopment project area as soon as practicable. DISCUSSION: Since December 2000, the time that the Orange County Fire Authority's station off of Campus Drive at John Wayne Airport was destroyed by fire, the City and the County have endeavored to replace that station with a facility within Santa Ana Heights (SAH). By May 2001, the City and the County had agreed that the City would construct a temporary station off of Zenith Avenue near Bristol in SAH to serve the SAH community and the airport area. The SAH temporary fire station has been in place at that location since that time. Subject. Fire Station No. 7 and Training Center — Award Contract No. 3626 May 9, 2006 Page 2 Concurrent with the operation of the temporary fire station, the City, the County, and the Orange County Development Agency have worked to plan a new permanent station for the area, with the City taking the lead on location and design. The SAH Project Advisory Committee (SAH PAC) has been involved in this discussion as well. A search of the City's website will show a number of SAH fire station - related agenda items that have brought the project through design and to the point of Bid Award. Bid Award. At 11:00 am on April 4, 2006, the City Clerk opened and read the following Total Bid Prices for this project: Bidder Total Bid Price Low Bernards Bros., Inc. $6,495,000 2 Erickson -Hall Construction Co. 6,543,000 3 DJM Construction Co., Inc. 6,9111,000 4 Woodcliff Corporation 6,978,000 The low Total Bid Price is 33% above the Architects Estimate of $4,900,000. Attachment 1 is bid summary for this project. The low bidder, Bernards Bros., Inc., is a State - licensed general building contractor which pre - qualified with City staff last March to bid on the project. Bernards has successfully completed recent school, community center, multi -use park center and other publicly - financed projects for other public agencies. In March of 2005, City staff conducted a contractor pre - qualification process in accordance with established procedures set by the State Department of Industrial Relations. This effort assures that only experienced and qualified firms would be bidding against each other on this and three other City building projects. Staff advertised and invited experienced general building contractors to submit data concerning their firm's qualifications to the City. Staff then evaluated the data and granted prequalification to 20 firms, including Bernards. The contract provides for the demolition of existing homes, garages, and other structures from the site and the construction of an 11,027 square foot fire station (including a 1,200 sf Training Room available for community use when training is not occurring) with utility stubs for a future training tower, landscaping, and irrigation systems. Attachment 2 shows a map of the proposed location and the floor plan. Please note that, in earlier iterations of the design, there was a silo structure incorporated into the design. Discussions with the SAH Project Advisory Committee (PAC) led us to remove the silo design and change it to more simple, traditional roof. We did not do a new schematic on the new roof — in large part to save costs. The. contract requires that all work be completed within 265 consecutive working days. Assuming that the Notice to Proceed is issued on June 1st, work should be completed by June 1, 2007, except for working day extensions due to unforeseen work, labor and materials delays, inclement weather. Liquidated damages are $1500 per calendar day. RRM Design Group prepared plans, specifications and an estimate for the project. Subject. Fire Station No. 7 and Training Center - Award Contract No. 3626 May 9, 2006 Page 3 Plans have been reviewed by the City's Building Department, the Irvine Ranch Water District and the Costa Mesa Sanitary District since the site is within their water and sewer service areas. Training Tower. This contract does not include the training tower proposed for the site. The tower, a prefabricated building, is expected to cost $740,000 to design, purchase and install. $350,000 of that amount will come from a grant from Santa Ana College for fire training facilities. The remaining funds will come from general funds set -aside for fire training purposes. The project itself is proposed within the FY 2006 -07 Capital Improvement Program that the Council will consider in May and June 2006. Upon completion of this contract work, the City will award a separate contract to construct the training tower. Geotechnical Services: Geotechnical services will be provided by outside consultants per the On -Call Professional Services Agreement approved by Council in June 2005. Construction Management Services: Council authorized the awarded a construction management agreement with GKK Works at the April 25 City Council meeting contingent upon awarding contracts for the Newport Coast Community Center and the Santa Ana Heights Fire Station. Funding Needed to Complete Project: On July 8, 2003, the City, the County of Orange, and the Orange County Development Agency (OCDA) entered into an agreement whereby the City would purchase land for a fire station in SAH and would design and construct the station using redevelopment funds from the Santa Ana Heights Redevelopment Agency (SAH RDA). This Agreement set aside $2.5 million to purchase the land and $1.6 million to construct the station. The actual land cost for the SAH Fire Station site was $4,181,000 ($1,681,000 more than the City - County -OCDA outlined in the Agreement). As shown in Table A, the construction costs for the station at $6,495,000, not including design, contingency and construction management fee, are significantly higher by $4,814,000 than anticipated in the Agreement. The total cost for this Project, including land purchase, is $11.93 million. All of these funds are reimbursable with RDA funds IF the City is successful in the transfer of some SAH RDA authority to the City. The SAH RDA has sufficient funding to cover the $11.93 million cost of this Project plus the other projects on the SAH Project Advisory Committee (PAC's) project list, even assuming a conservative projection of incoming tax increment over the next 10 years. Q N m oc0000 or �n u> a O v1 0 0 o th o O m a 'm R t9 t9 t9 (R t9 t9 t9 t9 M ri EL y fD r r N Q y Cy n w Nl ill ill iA ill N) H) O N r Q m cor cow y C N I!1 1n m Q W W W W W W W 0o a`uo uZ W = N N o�� LL $Q a c i w er °a U a o z i o °' a w w aE c0, 0000 0 o 0 0 o m � D c C U IM 0000 Cl u>oo o Ch 0 n E p N O O E N ¢ y m d C aS wwww wwwww ww.n p m y ct _ m L2 U� e IL 0 0 o d IL 0 w Qa a a.ci c�xm d � m Li U rni p aEi N 1 � y c J U 2 U _ "c a c L2 d a d a in F m IL c p E a E o a mU u o < < LL o m y p d u m ` �C7 �O�,U m:3prnm cc rn000 7a vii IL <UU With a budget amendment, sufficient funding will be available in the following accounts to provide for these expenses: Description Account Amount Santa Ana Heights Fire Station and Training Center 7456- C2320669 $2,830,000 General Fund — Capital Improvement Reserve 7456- C2320669 $4,542,397 Total $7,372,397 Environmental Review: This project is categorically exempt from the provisions of CEO A per Section 15332, Class 32, pertaining to urban infill development projects. A Notice of Exemption was filed with the County Clerk and posted on February 24, 2006, for thirty days. Prepared . ..D.. Design Attachments: 1. Bid Summary 2. Location Map and Floor Plan 3. Budget Amendment Submitted by: m G. Badum Works Director H Z U w Q w a, mQ �w On N w Y 2 K O U. 0 OV U j IL 00 _ w 4 x U U W d � oU U Z w O� Fp Q U O O m _ w w w� W U W W Z 0 H wa ATTACHMENT 1 . . . . . . . . . . . . or LL+ AW IP V 0� O SL All ATTACHMENT 2 (1 of 2) City of Newport Beach BUDGET AMENDMENT 2005 -06 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates X Increase Expenditure Appropriations AND Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues NX from unappropriated fund balance EXPLANATION: NO. BA- 06BA -067 AMOUNT: Sa,sa2,3s7.00 Increase in Budgetary Fund Balance X Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance This budget amendment is requested to provide for the following: To increase expenditure appropnations for the Santa Ana Heights Fire Station by $4,542,397 from the General Fund Reserve for Capital Improvements. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Amount Fund Account Description Debit Credit 010 3776 General Fund - Reserve for CIP $4,542,397.00 REVENUE ESTIMATES (3601) Fund /Division Account Description 9455 6000 SAH Fire Stationlfransfer In $4,542,397.00 EXPENDITURE APPROPRIATIONS (3603) Signed: � /%ia� //i ( � S 3- 06 Finrancial Approval: Administrative Services Director Date Signed: Administrative Approval: City Manager Date Signed: City Council Approval: City Clerk Date Description Division Number 7456 SAH Fire Station Account Number C2320669 SAH Fire Station $4,542,397.00 Division Number 9010 General Fund Account Number 9900 Transfer Out $4,542,397.00 Division Number Account Number Division Number Account Number Division Number Account Number Signed: � /%ia� //i ( � S 3- 06 Finrancial Approval: Administrative Services Director Date Signed: Administrative Approval: City Manager Date Signed: City Council Approval: City Clerk Date `EE sw W 2 N b<g °�– b z g S F } a E y t 3 79 2 -b; MO �! Y �z � a ¢ �m � m.ori zb[e vii '� k' E °b •2 LL k °g Ao£ c�5 `g <E `g e € re '2$ ga �• us u4 €Y .2 m2U v'N�44 <i-` C vl ,eza o•tg �N`y.:Eo c��v° fiS c"7%`L - °dE 1 u�k+u�¢vi view �i vie �dmad ¢d <d m ti o d a5d od[�id mdZ dma<m zdmtid d mtid uia i�d �d ad 0 I I - < o, ti)T 1- 1® - S-- i / — ------- - - -- - -- Fa O old L-» -- - - - - -FF -I -------- oily I IN ll ll ll ll ll I 4\ Q � \ i i lz �n • o� \s 0 • —_—N \ o ` \ F O 0 Z W W J 7 :w 3 I II 1 \ \ I ` r� U co cI UI Z I IL lz a R S2 x Lo e a F2 12 �I��III 7 :w 3 I II 1 \ \ I ` r� U co cI UI Z I IL lz a R S2 x Lo