HomeMy WebLinkAbout16 - Morning Canyon StabilizationCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 16 June 27, 2006 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department R.Gunther, P.E. 949 - 644 -3311 or rgunther @city.newport- beach.ca.us SUBJECT: MORNING CANYON STABILIZATION —COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3517 RECOMMENDATIONS: 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond one (1) year after Council acceptance. DISCUSSION: On September 13, 2005, the City Council authorized the award of the Morning Canyon Stabilization contract to Sunquest General Engineering. The first phase of the project was the stabilization of the canyon slopes by constructing seven rock - filled gabion grade control structures, a rock - filled gabion bank protection structure, placing fill, grouted rock riprap, storm drain extensions, and fencing in order to bring the canyon into readiness to accept storm water flows. The second phase of the work completed included slope backfill, planting of various California native shrubs and trees, and hydroseeding. The plant establishment is complete and contractor plant maintenance will be finished prior to the retention release. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $796,518.50 Actual amount of bid items constructed: $738,463.00 Total amount of change orders: $ 41,543.63 Final contract cost: $780,006.63 Momirg Canyon Stabilization - Completion And Acceptance of Contract No. 3517 June 27, 2006 Page 2 Five change orders totaling $41,543.63 were issued for the project and provided for a temporary fence, road stabilization rock, access road repair with sandbags, access road repair with rock, and landscape additions. The final overall construction cost, including Change Orders, was 2 percent under the original bid amount. Environmental Review: This project is categorically exempt 'from the provisions of CEQA per Section 15333 pertaining to small habitat restoration projects. A Notice of Exemption was filed with the County Clerk on June 6, 2005. Funding Availability: Funds were expended from the following accounts for the project: Account Description Account Number Amount General Fund 7014- C5100805 $591,433.63 Private Contributions 7251- C5100805 $188,573.00 Total: $780,006.63 The original contract completion date was December 14, 2005. The majority of the work was completed prior to the heavy rains in January, 2006. However, due to the extension of the rainy season into late Spring, the completion date for the remaining work was delayed to April 20, 2006. All work was substantially complete by the extended date. Prepared by: Submitted .. �� RGunther, P.E. Construction Engineer lien G. Badum is Works Director