HomeMy WebLinkAbout20 - San Miguel Drive Street ImprovementsCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 20
June 8, 2010
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Fong Tse, Principal Civil Engineer
949 - 644 -3321 orftse @NewportBeachCa.gov
SUBJECT: SAN MIGUEL DRIVE STREET IMPROVEMENTS — AWARD OF
CONTRACT NO. 4472
RECOMMENDATIONS:
1. Approve the project drawings and specifications.
2. Award Contract No. 4472 to GASS Construction Company, Inc. for the Total Bid
Price of $1,170,000 and authorize the Mayor and the City Clerk to execute the
contract.
3. Establish an amount of $117,000 (10 %) to cover the cost of unforeseen work.
4. Establish an amount of $12,500 to cover the cost of construction material testing.
5. Establish an amount of $2,500 to cover the cost of printing and incidentals.
6. Approve a Budget Amendment No. to recognize the contribution of funds
in the amount of $1,302,000 from Zoning Implementation and Public Benefit
Agreement between the City and the Irvine Company LLC dated January 8, 2008
and appropriating $1,302,000 into Capital Project Account No. 7251- C1002025
7. Direct Staff to seek reimbursement for the project funding ($1,302,000) pursuant
to the Zoning Implementation and Public Benefit Agreement between the City
and the Irvine Company LLC dated January 8, 2008
DISCUSSION:
At 10:00 A.M. on May 27, 2010 the City Clerk opened and read the following seven bids
for this project:
BIDDER TOTAL BID AMOUNT
Low GASS Construction Company, Inc. $1,177,000.00
2 All American Asphalt $1,194,194.00
3 Sequel Contractors, Inc. $1,214,012.00
4 RJ Noble Company $1,239,931.00
San Miguel Drive Street Improvements
June 8, 2010
Page 2
5 Jezowski & Markel Contractors, Inc. $1,290,049.00
6 1 C E Engineering $1,383,757.00
7 Excel Paving Company $1,477,453.00
The low total bid amount is 33% lower than the Engineer's Estimate of $1,750,000. The
received bid prices reflect the current market competitiveness. The low bidder, GASS
Construction Company (GASS) possesses a California State Contractors License
Classification "A" as required by the project specifications. A check of GASS'
references indicates satisfactory completion of similar projects for other public agencies.
GASS has successfully completed several similar improvement projects for the City as
GMC Engineering.
This project will realign both San Miguel Drive northerly and southerly curbs from
MacArthur Boulevard to approximately 500' west of Avocado Avenue. The
improvements when completed will include new curbs, gutters, sidewalks, raised
median with colored stamped concrete, plantings, irrigation, traffic signals, and a third
left -turn lane for vehicles travelling eastbound San Miguel Drive onto northbound
MacArthur Boulevard. The additional left turn lane will improve the operational efficiency
of this intersection by providing more left turn capacity. Additionally, the existing traffic
signal at the Avocado Avenue /Farallon Drive intersection will be replaced with a new
traffic signal equipped with wireless video detection to monitor and optimize traffic flow.
This project also included reconstructing the Fashion Island entry on the northwesterly
corner of San Miguel and MacArthur Boulevard intersection.
GASS is required by Contract to complete all work (less plant maintenance) within
ninety (90) consecutive work days in advance of the November - December shopping
season. In case of delayed work completion, GASS will be assessed liquidated
damages at the rate of $1,000 per calendar day.
Environmental Review:
This project is included within the Final Environmental Impact Report for the City Hall
and Park Development Plan, SCH2O9041010, which was certified by the City Council
on November 27, 2009.
Public Notice:
The Notice Inviting Bids was advertised in the City's official publication and in
construction industry publications. Prior to starting work, City - prepared notices will be
distributed by the Contractor to residents and businesses.
Construction Material Testing Services:
In addition to the contract costs, approximately $12,500 in construction material testing
services is estimated for this project. The work will be performed under the on -call
professional services agreement with Harrington Geotechnical Engineering.
San Miguel Drive Street Improvements
June 8, 2010
Page 3
Funding Availability:
This project will be funded under the Zoning Implementation and Public Benefit
Agreement between the City and The Irvine Company concerning properties located in
North Newport Center. The agreement provides for a circulation enhancement
contribution of $2.5 million to reimburse the City for circulation improvements within the
Newport Center area. Upon approval of the recommended Budget Amendment,
sufficient funds will be available in the following account for the project. Funds for this
project
Account Description
Newport Beach Civic Center
Proposed uses are as follows:
Vendor
GASS Construction Company
GASS Construction Company
Harrington Geotechnical
Various
Prepared b
Fong e
Princip I i\
Attachment:
I Engineer
Project Location Map
Account Number
7251- C1002025
Total
Purpose
Construction Contract
Construction Contingency
Construction Material Testings
Printing and Incidentals
Total:
Submitted by:
Amount
$ 1,302,000
$ 1,302,000
Amount
$ 1,170,000.00
$ 117,000.00
$ 12,500.00
$ 2,500.00
$ 1,302,000.00
w
0
V�
�O
�JP
Qo�� s92 O�J�
F�
DFtNE
J�
FARALLON ORjVF
JQ-
Q '
O V
GQp �Q'
JO
Q'
LOCATION MAP
NOT TO SCALE
SAN MIGUEL DRIVE STREET IMPROVEMENTS
City of Newport Beach
BUDGET AMENDMENT
2009 -10
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
X Increase Expenditure Appropriations AND
Transfer Budget Appropriations
SOURCE:
from existing budget appropriations
X from additional estimated revenues
from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
NO. BA- 1OBA -052
AMOUNT: $1,302,000.00
P XIncrease in Budgetary Fund Balance
Decrease in Budgetary Fund Balance
No effect on Budgetary Fund Balance
To increase revenue estimates and expenditure appropriations to recognize funds from the Zoning Implementation & Public
Benefit Agreement between the City and the Irvine Company for San Miguel Drive street improvements.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account Description
REVENUE ESTIMATES (3601)
Fund /Division Account Description
250 4927 Contribtions - The Irvine Company
EXPENDITURE APPROPRIATIONS (3603)
Description
Division Number 7251 Contributions
Account Number C1002025 San Miguel Drive Street Improvements
Division Number
Account Number
Division Number
Account Number
Amount
Debit Credit
$1,302,000.00
$1,302,000.00
` Automatic System Entry.
Signed: C�ilwt l! I V� Vt[R/1LQ/L & •� �d
Financial ADO val: Administrative Services Director Date
Signed:
Approval: City
1u
Date
Signed:
City Council Approval: City Clerk Date
City of Newport Beach
BUDGET AMENDMENT
2009 -10
EFFECT ON BUDGETARY FUND BALANCE:
X Increase Revenue Estimates
X Increase Expenditure Appropriations AND
Transfer Budget Appropriations
SOURCE:
from existing budget appropriations
X from additional estimated revenues
from unappropriated fund balance
EXPLANATION:
NO. BA- IOBA -052
AMOUNT: $1,302,000.00
Increase in Budgetary Fund Balance
Decrease in Budgetary Fund Balance
X No effect on Budgetary Fund Balance
This budget amendment is requested to provide for the following:
To increase expenditure appropriations from the CIOSA Contnrction Fund and to increase revenue estimates and expenditure
appropriations to recognize funds from the Zoning Implementation & Public Benefit Agreement between the City and the Irvine
Company for San Miguel Drive street improvements.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE Amount
Fund Account Description Debit Credit
430 3605 CIOSA Construction Fund - Fund Balance $450,329.92
REVENUE ESTIMATES (3601)
Division Number
Account Number
Signed: �\ �l r • y
Financial Appro I: Administrative Services Director
Signed:
Signed:
(,IT A
Date
Date
G'14-10
Date
Fund/Division
Account
Description
250
4927
Contribtions - The Irvine Company $851,670.08
EXPENDITURE APPROPRIATIONS (3603)
Description
Division
Number
7251
Contributions
Account
Number
C2002038
San Miguel Drive Street Improvements $851,670.08
Division
Number
7432
CIOSA Loan Expenditures
Account
Number
C2002038
San Miguel Drive Street Improvements $450,329.92
Division Number
Account Number
Signed: �\ �l r • y
Financial Appro I: Administrative Services Director
Signed:
Signed:
(,IT A
Date
Date
G'14-10
Date