HomeMy WebLinkAbout25 - Hyatt Regency Environmental Impact ReportCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 25
January 13, 2009
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Planning Department
Jaime Murillo, Associate Planner
(949) 644 -3209, imur !!!oa(%city.newgort- beach.ca.us
SUBJECT: Contract for Environmental Consulting Services
Hyatt Regency Environmental Impact Report (EIR)
APPLICANT: Sunstone Hotel Investors, Inc.
ISSUE
In accordance with Council Policy F -14 (Authority to Contract for Services), the City
Manager shall provide notice of a permit application and a brief description of the
proposed project to the City Council when a contract for professional services is paid for
by funds in an applicant deposit account and the total cost for services exceeds
$100,000.
RECOMMENDATION
Receive and File.
DISCUSSION
This report is intended to provide notice to the City Council of a contract for professional
services between the City of Newport Beach and The Planning Center for the
preparation of an Environmental Impact Report (EIR) associated with a project to
expand the existing Hyatt Regency Hotel at 1107 Jamboree Road. The current contract
is in the amount of $236,590, which was paid for by the project applicant ( Sunstone
Hotel Investors, Inc.); however, the scope of work has been expanded to include
additional analysis required to complete the Final EIR. The Draft EIR will be revised to
incorporate a revised site plan (moving a timeshare building to increase the biological
resources buffer areas) and to include updated biological resources information. An
amendment to the contract is also required to cover additional work required to respond
to a comment letter received from the City of Irvine and to allow for additional project
management and public hearing time. The estimated budget to complete this additional
January 13, 2009
Page 2
analysis is $25,200, resulting in a total contract amount of $261,790. The applicant has
been notified of the amended contract amount and has agreed to fund the amount.
The project includes the addition of 88 timeshare units, an expanded 11,032 square -foot
ballroom, a 10,072 square -foot spa and new pool, and a new two -level parking garage.
Implementation will require demolition of 12 existing hotel rooms and the Terrace
Ballroom and removal of a nine -hole golf course. The expansion will require the
following approvals from the City:
• A parcel map to reconfigure two existing lots, allowing the timeshares to remain
on one parcel and the hotel on the other, and to establish finished grades for the
purposes of measuring height.
• A use permit to allow the expansion of the existing hotel and establishment of a
timeshare development. A use permit is also required to allow the proposed
timeshare buildings and ballroom to exceed the 26 -foot base height limit.
• A modification permit to allow commercial tandem parking and to allow the
architectural tower and finial element of the proposed ballroom to exceed the 35-
foot maximum height limit.
• A development agreement between the City and the operator of the timeshare
development relating to the amount of tax payable to the City for the right of
occupancy of the timeshare units.
• Certification of an Environmental Impact Report.
The Final EIR is currently under preparation and will consist of the circulated Draft EIR,
the response to comments on the Draft EIR, and revisions to the Draft EIR. A January
27, 2009, City Council hearing is tentatively scheduled for review of the project and EIR.
Prepared by:
7aime Murillo, Associate Planner
RIUsersIPLMSharedlProfessional Services Agreements & ContractslHyatt - Planning CenteMyatt Council Report 4.doc
AMENDMENT NO.4
TO
PROFESSIONAL SERVICES AGREEMENT WITH THE PLANNING CENTER
FOR PREPARATION OF AN EIR FOR THE HYATT REGENCY NEWPORT
BEACH EXPANSION
THIS AMENDMENT NO. 4 TO PROFESSIONAL SERVICES
AGREEMENT, is entered into as of this 13th day of January, 2009, by and
between the CITY OF NEWPORT BEACH, a Municipal Corporation ( "CITY "),
and THE PLANNING CENTER a California Corporation, whose address is 1580
Metro Drive, Costa Mesa, California, 92626 ( "CONSULTANT'), and is made with
reference to the following:
RECITALS:
A. On April 11, 2006, CITY and CONSULTANT entered into a Professional
Services Agreement, hereinafter referred to as "AGREEMENT ", for
environmental consulting services for the Hyatt Regency hotel
expansion, hereinafter referred to as "PROJECT'.
B. CITY and CONSULTANT have entered into three separate
AMENDMENTS of the AGREEMENT, the latest dated September 22,
2008.
B. CITY desires to enter into this AMENDMENT NO. 4 to reflect additional
services not included in the AGREEMENT or prior AMENDMENTS and to
extend the term of the AGREEMENT to March 10, 2009.
C. CITY desires to compensate CONSULTANT for additional professional
services needed for PROJECT.
D. CITY and CONSULTANT mutually desire to amend AGREEMENT,
hereinafter referred to as "AMENDMENT NO. 4, as provided here below.
NOW, THEREFORE, it is mutually agreed by and between the undersigned
parties as follows:
In addition to the services to be provided pursuant to the AGREEMENT,
CONSULTANT shall diligently perform all the services described in
AMENDMENT NO. 4 including, but not limited to, all work set forth in the
Scope of Services attached hereto as Exhibit A and incorporated herein
by reference. The City may elect to delete certain tasks of the Scope of
Services at its sole discretion.
2. City shall pay Consultant for the services on a time and expense not -to-
exceed basis in accordance with the provisions of this Section and the
r
Schedule of Billing .Rates attached to the AGREEMENT. Consultant's
compensation for all work performed in accordance with this
AMENDMENT NO. 4, including all reimbursable items and subconsultant
fees, shall not exceed Twenty Five Thousand Two Hundred Dollars and
no /100 ($25,200.00) without prior written authorization from City.
3. The term of the AGREEMENT shall be extended to March 10, 2009.
4. Except as expressly modified herein, all other provisions, terms, and
covenants set forth in AGREEMENT shall remain unchanged and shall be
in full force and effect.
IN WITNESS WHEREOF, the parties hereto have executed this AMENDMENT
NO. 4 on the date first above written.
APPROVED AS TO FORM:
Attorney
for the City of Newport Beach
ATTEST:
By:
LaVonne Harkless,
City Clerk
Attachments: Exhibit A — Scope of Services
CITY OF NEWPORT BEACH,
A Municipal Corporation
Mayor
for the City of Newport Beach
CONSULTANT:
By:
Dwayne Me
Corporate ecutive Officer
By:
Keith McCann
Chief Financial Officer
F:1UsersTLMSharedlProfessiona1 Services Agreements & ComracdsUiyatt - Planning Center\Planning Center Contract
Amendment No 4 01- 13- 09.doc
CO THE
PLANNING
CENTER
Governmental Services
Planning & Urban Design
Environmental Studies
School Facilities Planning
December 22, 2008
7580 Metro Drive
Costa Mesa, CA 92528
Mr. Jaime Murillo, Associate Planner
Phone: 714.955.9220
City of Newport Beach
3300 Newport Boulevard
Far: 716.955.9221
Newport Beach, CA 92658
costamesa@planningcemer.com
Subject: Request for Contract Amendment No. 4 for Environmental Services for
the Hyatt Regency Newport Beach Project (CNB- 09.OE)
Dear Mr. Murillo:
This letter is to request Contract Amendment No. 4 for The Planning Center's environmental services for
the Hyatt Regency Newport Beach Project. Our last contract amendment (August 18, 2008, as updated
September 24, 2008) addressed supplemental work for preparation of the Final EIR including
incorporating project detail about lighting plans, fuel modification, grading, and additional visual
simulations. The last amendment also included fees for additional meetings, project management related
to extending the project schedule, and additional intersection and parking analysis by IBI, the traffic
consultant. Contract Amendment No. 4 is required for additional effort beyond the approved scope of
work to revise the Final EIR to incorporate 1) a proposed new Local Coastal Plan Amendment, 2) a
slightly revised site plan (moving a timeshare building to increase the biological resources buffer area),
and 3) updated biological resources information. This amendment will also cover additional work
required to respond to the City of Irvine DEIR comment letter (received subsequent to our submittal of
Contract Amendment No. 3) and additional project management and public hearing time.
As summarized in Table 1, Cost Estimate, our existing contract as previously amended for this project is
for a total of $236,590, including subconsultants and reimbursables. To complete the processing of this
project, we are requesting $23,680 in additional labor fees for The Planning Center and $1,520 in fees for
IBI. No additional reimbursable costs are requested. Total contract amount upon approval of this
amendment will be $261,790, including suboonsultants and reimbursables.
THE PLANNING CENTER
SCOPE OF WORK
Task 1: Initial Study /Notice of Preparation
This task has been completed and there are no changes.
Task 2: Public Scoping Meeting
Subsequent to contract execution, the City decided that a public scoping meeting would not be
necessary for the project. The budget for this task was subtracted in Contract Amendment No. 1.
r ,
Mr. Jaime Murillo, City of Newport Beach
December 22, 2008
Page 2 of 5
Task M Screencheck Draft EIR
This task has been completed and there are no changes.
Task 4, Draft EIR
This task has been completed and there are no changes.
Task 5: Final EIR /Response to Comments
Additional scope of work included in this amendment includes:
• Response to City of Irvine comment letter (dated October 22, 2008)
• Update to the "Revisions to the DEIR" section to include a description of the proposed LCP
Amendment, revisions to the Site Plan, and supplemental biological resource information.
• Revisions to responses to comments received on the DEIR to correct the FEIR with respect to
the proposed LCP Amendment and site plan changes (or alternative method such as an
expanded introduction to the Response to Comments to explain and update the changes)
• Submittal of revised responses to commenting agencies
• Preparation of memorandum to the City explaining The Planning Center's position on whether
the proposed LCP requires recirculation of the DEIR
Additional work required for IBI to assist The Planning Center in preparing Response to Comments for OWWWA
the Final EIR is included in a separate scope, below.
Task 6: Mitigation Monitoring Program
This task has been completed and we are not anticipating any changes to project mitigation or the MMP.
Task 7; Findings of Fact and Statement of Overriding Considerations
The draft Findings of Fact and Statement of Overriding Considerations has been completed. These will
be updated to reflect the revisions to the project including the proposed LCP Amendment and site plan
revisions.
Task 8; Public Hearings /Meetings
The Planning Center's project manager (JoAnn Hadfield) and one additional environmental professional
have attended the two Planning Commission public hearings held on this project. Our scope of work
includes our attendance at up to two additional public hearings (by JoAnn and Nicole Vermillion,
noise /AQ specialist). We do not anticipate more than two more public hearings, and therefore have not
revised this task or associated cost estimate.
Task 9: Notice of Determination
This task has not been initiated and we are not recommending any changes.
,Mr. Jaime Murlilo, City of Newport Beach
December 22, 2008
Page 3 of 5
Task 10: Project Management and Coordination
Resolution of Coastal Commission and wetlands issues has resulted in more delays for processing this
project. As of the previous contract amendment, we anticipated approval of the project prior to
November 2008. This task, therefore, includes additional project management and coordination fees
based on an estimated approval by mid - February (assuming a Public Hearing on January 27, 2009, and
one additional City Council hearing, if needed). Additional fees for project management and coordination
have been based on an estimated 2 hours /week for an additional 17 weeks, in comparison to the
contract as approved to date.
IBI
The following additional scope of work for IBI is based on its revisions to their original scope of work, as
amended through Contract Amendment No. 3.
TASK 1: Project Definition
No additional work efforts are assumed under Task 1.
TASK 2: Existing Conditions
No additional work efforts are assumed under Task 2.
TASK 3: Future Traffic Conditions - TPO Analysis
No additional work efforts are assumed under Task 3.
TASK 4: Future Traffic Conditions - CEQA Analysis
No additional work efforts are assumed under Task 4.
TASK 5: Review of Applicant Parking Study
This task completed under previous contract amendment.
TASK 6: Response to Environmental Impact Report Comments
The budget augment under this request to cover the work required to respond to the City of Irvine DEIR
comment letter, which was received after the close of the DEIR public review period and after to the
previous contract amendment.
TASK 7: Meetings
The approved meeting and public hearing attendance task for IBI includes up to two meetings and two
public hearings. Bill Delo has attended one public hearing, and therefore this task currently
accommodates his attendance at one additional hearing.
TASK 8: Future Traffic Conditions - Construction Analysis
This task was completed under previous contract amendment.
0
Mr. Jaime Murlllo, City of Newport Beach
December 22, 2008
Page 4 of S
SUMMARY COST ESTIMATE AND SCHEDULE
Attached Table 1 summarizes the previously approved contract and requested Contract Amendment No.
4 by task and consultant. This contract amendment request is for a total of $23,680 for The Planning
Center labor and $1,520 for IBI labor. No additional reimbursable costs are requested. Approval of this
4th Contract Amendment would bring the total contract amount to $261,790 for the Hyatt Regency
Newport EIR. For purposes of planning and budgeting, it is assumed that the revised site plans due from
the project applicant will be available to The Planning Center by January 9, 2008, and that the revised
Final EIR, and revised Facts and Findings and Statement of Overriding Considerations will be submitted
to the City by January 16, 2008, to ensure City staff time to review the revised document and to finalize
the staff report prior to the City Council public hearing.
We look forward to working with the City and the Hyatt consultant team to successfully complete this
project. Please contact me with any questions you may have regarding this contract amendment
request.
Sincerely,
THE PLANNING CENTER
JoAnn Hadfield
Director, Environmental Services
Attachment
�1
Mr. Jaime Murlilo, City of Newport Beach
December22,2008
Page 5 of 5
Task
Total Approved
Contract through
Amend. No. 3 (as
signed October
31,2008)
Requested
Contract
Amendment
# 4
Total
Task 1. Initial Stud /NOP
$4,250
$0
4,250
Task 2. Public Sco ing Meeting
0
0
0
Task 3. Screencheck Draft EIR
79,840
0
7,9840
Task 4. Draft EIR
6,450
0
6,450
Task 5. Final EIR/Response to Comments
42,975
14,935
57,910
Task 6. Mitigation Monitoring Program
750
0
750
Task 7. Statement of Findings/Statement of Ovemding
Considerations
1,400
1,350
2,750
Task 8. Hearings/Meetings
11,085
11,085
Task 9. Notice of Determination
200
0
200
Task 10. Project Management and Coordination
27,905
7,395
35,300
Subtotal - Labor
$174,855
$23,680
198,535
IBI Group (Traffic)
$35,710
$1,520
37,230
Co stone Resource Management Cultural
3,609
0
3,609
Subtotal - Subconsultards
$39,319
$1,520
40,839
TOTAL LABOR
$214,174
$25,200
239,374
Reimbursable Expense Estimate
$22,416
$0
22,416