Loading...
HomeMy WebLinkAboutSS3 - Civic Center UpdateConstruction Update August 9, 2011 So where are we and where are we going? What does it look like? What about Contingencies? Are there any Change orders How much success had we had with our Value engineering program? What about schedule? � R ,1 saw Y T r� sp Alt jTttTft ..ter 's 6 2 7 --Inman s c. X L 0 �E/ a a Y 11 =word � cAnrwna 12 3 0 1 1 �4 j vffir f�I• ~ i my., A K , w �s r ' �` {'�► T 14 15 What about Contingencies? Construction Contingencies (included in GMP) GMP Phase 1- Mass Excavation and Shoring Wall Grade and recompact small landslide - $34,842 Grading refinements (Wetlands /Archeological Protection) - $91,620 Retaining wall deletion (credit) $125,000 Plan Check Revisions to Shoring Wall - $144,790 Library HVAC Utility Relocation - $264,845 (advanced from Phase 3) Unforeseen soil conditions /Rock - $37,000 Total contingency to date = - $448,097 Phase 1 contingency allocation = $490,400 Balance of Phase 1 contingency remaining = $42,303 16 Construction Contingencies (included in GMP) Stone Stair Trends - Allowance overrun - $12,287 Power Inverter - Design Omission - $89,786 Total contingency to date = - $102,073 Phase 2 contingency allocation = $336,078 Balance of Phase 2 contingency remaining = $234,005 Overexcavation for Library and Waterproofing - $29,858 Phase 3 contingency allocation = $1,930,822 Balance of Phase 1 contingency remaining = $1,9oo,964 Total Construction Contingency used to date = $580,028 or o.56% Total Project Contingency Remaining (All) _ $2,177,272 or 70 17 Potential Unanticipated Contingency Items ( currently under review by City, CW Driver, and Design Team) SCE /AT &T /Cox revisions that were not previously identified during design Weather Damage — Cost submitted to FEMA ($62K) Typical miscellaneous design changes /pricing omissions EM Are there any Change Orders to the Owner's Contingency? So far, no change orders or added costs incurred to Owner's Contingency. $2,623,000 balance in "Owner's Contingency" is untouched. All potential changes must be approved by the City Council Building Committee and reported back to Council. 19 Value Engineering "A continuing process" VE items included in current GMP = $668,050 Electrical , insulation, stone, roofing VE items confirmed post GMP = $275564 Open Parking Structure, Parking Structure Lighting VE pending final review = $376,888 Landscaping, waterproofing, Concrete, Electrical, HVAC Design Fee Savings (SD thru CD) _ $188,146 Total = $1,508,648 20 What about Schedule.? Currently, still aiming for Dec 2012 completion Some problem areas Difficulties with Shoring wall approvals Weather — Winter 2010 rains SCE changes to design requirements Minor design changes and conflict resolution Steel package submittal approval delays has caused fabrication start date to slip. 21 Construction to Date Construction Contract Total = $ 104,306,931 Expended to date = Total Const. Contingency used = Potential Savings $ 19�904�865 R 410,211(0.390 • Const. Contingency Remaining = $ 2,347,089 ( 85%) • Owners Contingency Remaining = $ 2,623,000 4 Value Engineering savings = $ 1,508,648* Optimistic Cost projection (3/22/11) _ $101,259,207 So far, we are on track to achieve some or all of those savings. * $668,05o already included in GMP 22 For more info and a link to the monthly newsletter, check http://www.ne3vpoir-tbeachca.gov/index.aspx?page=1,54.9 Or contact Steve Badum Public Works Director 949 - 644 -3311 sbadum@ne"ortbeachca.gov Or William Hahn Project Manager with C.W. Driver 949 - 261 -5100 whahn(@cwdriver.com 23