HomeMy WebLinkAbout13 - C-3612 & BA-082 - Mariners Village Landscape ImprovementsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 13 June 24, 2003 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Antony Brine, Principal Civil Engineer 949 -644 -3311 tbdne@city.newport-beach.ca.us SUBJECT: MARINERS VILLAGE LANDSCAPE IMPROVEMENTS — AWARD OF CONTRACT NO. 3612 — APPROVE AMENDMENT NO. 2 TO PROFESSIONAL SERVICES AGREEMENT WITH METROPOINTE ENGINEERS RECOMMENDATIONS: 1. Approve the plans and specifications. 2. Affirm Categorical Exemption for the work. 3. Award Contract No. 3612 to Belaire -West Landscape, Inc. for the Total Bid Price of $295,940, and authorize the Mayor and the City Clerk to execute the contract. 4. Establish an amount of $29,594 to cover the cost of unforeseen work. 5. Approve Amendment No. 2 to the Professional Services Agreement with MetroPointe Engineers for the Mariners Village Improvement Project at a contract price of $7,530 and authorize the Mayor and the City Clerk to execute the Amendment. 6. Approve a Budget Amendment of $55,064 from the unappropriated balance of the General Fund to Account No. 7014- C2700500 to pay for additional design and construction costs. DISCUSSION: At 11:00 A.M. on June 10, 2003, the City Clerk opened and read the following bid for this project: BIDDER TOTAL BID AMOUNT Belaire -West Landscape, Inc. $295,940.00 Subject: Mariners Village Landscape Improvements — Award of Contract No. 3612 — Approve Amendment No. 2 to Professional Services Agreement with MetroPointe Engineers June 24, 2003 Page: 2 Only one bid was received and it was 8% higher than the engineer's estimate. This project provides for the installation of new landscaping and irrigation equipment along the northerly sidewalk of Coast Highway from Riverside Avenue to approximately 600 feet south of Tustin Avenue. The landscaping improvements consist of twenty -two (22) Washingtonia Robusta palm trees — 30 feet in height -- and low height shrubs. The palm trees will be located in 5 -foot by 5 -foot planter areas with tree grates or shrub plantings at the base of the trees. Work will also include the removal and replacement of concrete sidewalk, and trenching of AC pavement in Coast Highway to install irrigation crossovers. There is also minor traffic signal modification work involved in the contract. Staff considered a rejection of the bid, and a re -bid of the project. However, there are some potential drawbacks to a re -bid which made us consider the option to accept the submitted bid. When projects are re -bid, experience shows that bids often come in higher the second time. Also, re- advertising and bidding the project in this case would push back the construction schedule into the Christmas shopping season. Some of the business owners in the Mariners Village had some strong concerns with the potential impacts of construction continuing beyond November, with the Boat Parade and a new retail business opening. Staff also reviewed the submitted bid with General Services, who concurred that the bid was reasonable given the complexity and size of the project. Staff called a number of the contractors who picked up plans and specifications, but did not bid on the project, to determine if they would bid if the project was re- advertised. The contractors stated that they did not bid, and probably would not bid again for different reasons: the plans were in metric, the amount of landscaping was small, many different types of work involved, too busy, small profit. The low bidder, Belaire -West Landscape, Inc., possesses a General Engineering "A" contractor's license as required by the project specifications. Belaire -West Landscape has significant experience in completing projects on Caltrans facilities. Given all of the above factors, it was decided to accept the submitted bid. Staff is requesting the appropriation of $55,064 from the unappropriated balance of the General Fund to cover the additional construction costs included in the bid, and the additional design costs included in Amendment No. 2 with MetroPointe Engineers. During the completion of the final construction plans and specifications, the City and Caltrans required additional revisions to the landscape construction documents. MetroPointe Engineers performed the extra services required to complete the documents for a total fee of $7,530. A copy of the scope of the additional services, and the Amendment No. 2 are attached for your review. Subject: Mariners Village Landscape Improvements — Award of Contract No. 3612 — Approve Amendment No. 2 to Professional Services Agreement with MetroPointe Engineers June 24, 2003 Page: 3 Environmental Review: A Categorical Exemption, Section 15303, Class 3, was filed with the County Clerk on May 10, 2002 for this project. Funding Availability Upon approval of the recommended Budget Amendment there will be sufficient funds available in the following account for the work: Account Description Account Number Amount General Fund 7014- C2700500 $333,064 Prepared by: Lam= Antony Brine, .E. Principal Civil Engineer Submitted by: Attachments: Location Map Amendment No. 2 with MetroPointe Engineers Budget Amendment Project Description The Mariner's Village Public Improvements Plan proposes enhanced public improvements within the existing public right of way of East Coast Highway, Riverside Avenue, Tustin Avenue and Avon Street. Additionally, improvements are planned within the alley connecting Riverside and Tustin Avenues and the municipal parking lot located east of Tustin Avenue. The proposed improvements are generally described as follows: Within the East Coast Highway right -of -way: 1. Washington Robusta (Mexican Fan) palm trees and Ligustrum (Privet) hedge planters will be placed in regular intervals along the northerly sidewalk between Riverside and Tustin Avenues. 2. The existing landscaped median between Riverside and Tustin Avenues will be enhanced with additional plantings. 3. Two existing painted medians (one east of Tustin Avenue and one west of Riverside Avenue) will be landscaped. Within the Riverside Avenue, Tustin Avenue, Avon Street and alley rights -of -way: 1. Street trees with tree grates and additional planter extensions will be placed within the existing sidewalk areas. 2. Pedestrian -scale street lighting and street furniture will be added. Within the existing municipal parking lot 1. Shade trees and shrub plantings will be added without reducing parking. 2. Pedestrian -scale lighting for enhanced security will be added. . • • • ol 07M .. IVA .. �- AMENDMENT NO. 2 TO PROFESSIONAL SERVICES AGREEMENT WITH METROPOINTE ENGINEERS THIS AMENDMENT NO. 2 TO PROFESSIONAL SERVICES AGREEMENT, entered into this day of , 2003, by and between the CITY OF NEWPORT BEACH, a municipal corporation, (hereinafter referred to as "CITY ") and METROPOINTE ENGINEERS, whose address is 3151 Airway Avenue, Suite J -1, Costa Mesa, California, (hereinafter referred to as "CONSULTANT'), is made with reference to the following: RECITALS: A. On January 22, 2002, CITY and CONSULTANT entered into a Professional Services Agreement, hereinafter referred to as "AGREEMENT, for Engineering Design services for the Mariners Village Improvement Project, hereinafter referred to as "PROJECT. B. KIRBY & COMPANY is listed in the AGREEMENT as a Subconsultant providing their professional consulting services to METROPOINTE ENGINEERS. C. CITY and CONSULTANT have entered into one previous AMENDMENT of the AGREEMENT. D. CITY and CONSULTANT mutually desire to amend AGREEMENT, hereinafter referred to as "AMENDMENT NO. 2,° as provided here below. E. CITY desires to enter into this AMENDMENT NO. 2 to reflect additional services not included in the AGREEMENT and to extend the term of the AGREEMENT to December 31, 2003. F. CITY desires to compensate CONSULTANT for additional professional services needed for PROJECT. NOW, THEREFORE, the parties hereto agree as follows: 1. CONSULTANT shall be compensated for services performed pursuant to this AMENDMENT NO. 2 according to "Exhibit A" dated June 13, 2003, attached hereto. 2. Total additional compensation to CONSULTANT for services performed pursuant to this AMENDMENT NO. 2 shall not exceed Seven Thousand, Five Hundred and Thirty Dollars ($7,530). 2003. 3. The term of the AGREEMENT shall be extended to December 31, 4. Except as expressly modified herein, all other provisions, terms, and covenants set forth in AGREEMENT shall remain unchanged and shall be in full force and effect. IN WITNESS WHEREOF, the parties hereto have executed this AMENDMENT NO. 2 on the date first above written. APPROVED AS TO FORM: By: By: City Attorney ATTEST: By: LaVonne Harkless City Clerk CITY OF NEWPORT BEACH, A municipal corporation Mayor City of Newport Beach METROPOINTE ENGINEERS f.Wsem\pbw\sharedl greements*01 -02Metnopointe- manners village - no. 2.doc ietroPointe r. June 13, 2003 City of Newport Beach Mr. Tony Brine P.O. Box 1768 Newport Beach, CA 92558 Subject: Additional Budget Request— Amendment No. 2 Landscape Additional Scope of Services Dear Tony; MetroPointe Engineers is requesting a contract amendment for additional budget to perform additional scope of services for landscaping as described in the attached letter, dated June 9, 2003 from Kirby & Company. The additional amount of this request is $7,530. We are also requesting the amendment extend the contract period from it's present termination of September 1, 2003 to December 31, 2003 to ensure the entire construction period is covered. Please call me 9 you have questions or require additional information. Sincerely, Marie Marston, P.E. Project Manager EXHIBIT A 3151 Airway Avenue • Suite J -1 o Costa Mesa, CA 92626 Bus: (714) 438 -1095 • Fax: (714) 438 -1097 June 9, 2003 Ms. Marie Marston MetroPointe Engineers, Inc. J J4 t 2003 3151 Airway Avenue, Suite J -1 Costa Mesa, California 92626 Regarding: Mariner's Village: Coast Highway Streetscape Revisions (MML002A) Dear Marie: Enclosed is the Addendum to Subconsultant Professional Services Agreement for revisions on the above referenced project. As requested, Kirby & Company prepared exhibits for presentation to the Mariner's Mile Business Owners Association and attended an additional meeting on 8/12/02 to discuss the impact of the CalTrans comments. This resulted in the decision to pursue a variance from CalTrans regarding the line of sight'requirements along Coast- Highway. Additionally, we attended another extra meeting on 7/23 /02 to review the potential landscape easements with property owners. The original agreement included three plan check revisions, which were performed in July, August and November of 2002. During the plan check process in April 2003, the City and CalTrans requested additional revisions to the landscape construction documents. Please call me at 949 /376 -1695 with any question you may have about the enclosed. Thank you. With regards, Kirby & Company Ci��� e Anne Kirby Principal Enclosures. cc: Tony Brine, City of Newport Beach (with enclosures) KIRBY & COMPANY 118 Camemy Heights Pho: 949- 376 -1695 Laguna Niguel, Califomia 92677 Fax: 949 - 240 -9986 ADDENDUM TO SUBCONSULTANT PROFESSIONAL SERVICES Project Name: Mariner's Village: Coast Highway Streetscape Revisions Kirby & Co. Project Number: MML002A Date: June 9, 2003 This addendum by and between MetroPointe Engineers, Inc. (Consultant) and Kirby & Company (Subconsultant) is for the Sub consultant to perform extra services on the subject project. SCOPE OF SERVICES Task I. Landscape Exhibits & Revisions Consultant will: 1. Identify areas for landscape easements to accommodate landscape improvements on private property and attend extra meeting to review plan with property owners. Provide easement locations to Consultant for reference to prepare easement documents. 2. Visit the site to explore revised palm locations as requested by the City. Revise irrigation documents to accommodate new palm locations. 3. Based on CalTrans plan check comments, prepare photographic exhibits and plan overlay exhibits on the landscape documents for presentation to the MMBOA. These plans were used to discuss the options and approach to be taken with CalTrans on subsequent submittals and to request a variance for the line of sight. 4. Prepare for and meet with the MMBOA one time in excess of original scope of work. Task II. Revisions to Landscape Construction Documents Consultant will: 1. Revise irrigation and planting construction documents to delete palms at the Coast Highway setback and the median per CalTrans plan check. 2. Coordinate with City staff on requested irrigation and landscape revisions. 3. Revise description of landscape estimate for bid purposes based on revisions requested by CalTrans and the City to landscape and irrigation construction documents. Page 1 Project Number: MML002A June 9, 2003 4. Per City request, visit site to review the existing Trachycarpus fortunei palms for added scope. Add note to landscape construction documents to box and relocate of the existing palms per City request. 5. Revise irrigation and electrical construction documents to respond to revision in City criteria for irrigation documents. 6. Coordinate revisions with the project team. REIMBURSABLE COSTS: The following costs shall be reimbursed at cost and are not included in the Fee for Professional Services: A. Cost of copies of drawings, specifications, reports and cost estimates; xerography and photographic reproduction of drawings and other documents furnished or prepared in connection with the work of this contract. Estimate $680. Please refer to 'Compensation for Professional Services' for the estimate of Reimbursable Costs. COMPENSATION FOR PROFESSIONAL SERVICES Services described above shall be provided based on a fixed fee basis as follows: Task Task I. a. b. Task II. a. b. Fee Total Description Fee /Phase Landscape Exhibits & CalTrans Revisions Landscape $2,400 Irrigation 1,560 Revisions to Landscape Construction Documents Landscape 1,400 Irrigation 1,490 Reimbursable Expenses Total $6,850 680 $7,530 Fees for Professional Services shall be billed monthly for progress payment based upon percentage of work complete. Reimbursable Costs shall be billed with fee invoices. REVOCATION: This proposal shall be considered revoked if acceptance is not received within 60 days of the date hereof. Page 2 City of Newport Beach BUDGET AMENDMENT 2002 -03 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates X Increase Expenditure Appropriations Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues PX from unappropriated fund balance EXPLANATION: NO. BA- 082 AMOUNT: F $55,064.00 Increase in Budgetary Fund Balance AND X Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance This budget amendment is requested to provide for the follovAng: To increase expenditures for the Mariners Village Landscape Improvements, C-3612. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account 010 3605 REVENUE ESTIMATES (3601) Fund /Division Account EXPENDITUREAPPROPRIATIONS (3603) Description General Fund Fund Balance Description Signed: Signed: Signed: Administrative City Council Approval: City Clerk Services Director Amount Debit Credit $55,064.00 . Automatic $55,064.00 a-14;-0,3 Date DIlie Date Description Division Number 7014 Miscellaneous & Studies Account Number C2700500 Economic Development - Mariners Mile Division Number Account Number Division Number Account Number Division Number Account Number Division Number Account Number Signed: Signed: Signed: Administrative City Council Approval: City Clerk Services Director Amount Debit Credit $55,064.00 . Automatic $55,064.00 a-14;-0,3 Date DIlie Date