Loading...
HomeMy WebLinkAbout09 - 2014-2015 Playground Improvements - NOC and Contract Termination for Contract No. 5855 (CAP15-0030 and CAP15-0031)9-1 NEWPORT BEACH City Council Staff Report COUNCIL STAFF REPORT CITY OF April 12, 2016 Agenda Item No. 9 ABSTRACT: On November 25, 2014, City Council awarded Contract No. 5855, 2014-2015 Playground Improvements project to Malibu Pacific Tennis Courts, Inc. (MPTC), for a total contract cost of $119,800.00 with an $18,200.00 (15 percent) allowance for contingencies. The work has been completed and staff now recommends closing out the project. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project; b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release the Faithful Performance Bond one year after acceptance by the City Council. FUNDING REQUIREMENTS: Funds for the construction contract were expended from the following account: TO:HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM:David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY:Peter Tauscher, Civil Engineer, ptauscher@newportbeachca.gov PHONE:949-644-3316 TITLE:2014-2015 Playground Improvements - Notice of Completion and Contract Termination for Contract No. 5855 (CAP15-0030 and CAP15-0031) 2014-2015 Playground Improvements - Notice of Completion and Contract Termination for Contract No. 5855 (CAP15-0030 and CAP15-0031) April 12, 2016 Page 2 9-2 Account Description Account Number Amount Building Excise Tax 7271-C4002021 $23,298.75 Building Excise Tax 7271-C4002020 $45,547.75 Total:$68,846.50 DISCUSSION: Overall Contract Cost/Time Summary Awarded Contract Amount Final Cost at Completion Contingency Allowance Actual Contract Change % Due to Directed Change % Due to Unforeseen Change $119,800.00 $68,846.50 15% or less -42.5% -42.5% 0.0% Allowed Contract Time (days) 30 Actual Time Under (-) or Over (+)42 The work under this contract consisted of removing and disposing older playground improvements; installing and adjusting new playground equipment; removing and installing a drinking fountain; and installing flexible play surface systems at six playgrounds throughout the City. The six playgrounds included in this project were Channel Place Park, Irvine Terrace Park, Bayside Park, Buffalo Hills Park, Harbor View Park, and Spyglass Hill Reservoir Park. The contract has been completed. A summary of the contract cost is as follows: Original bid amount:$ 119,800.00 Actual cost of bid items constructed:$ 75,846.50 Total change orders:$ 0.00 Liquidated damages:$ (7,000.00) Final contract cost:$ 68,846.50 The final construction contract cost is now approximately 42.5 percent below the original contract amount. This reduction was a result of (1) liquidated damages being applied due to failure to meet the contracted completion date; and (2) negotiated credit to offset for the contractors installation of material not meeting the contract specifications. 2014-2015 Playground Improvements - Notice of Completion and Contract Termination for Contract No. 5855 (CAP15-0030 and CAP15-0031) April 12, 2016 Page 3 9-3 Contract specifications established a 25 consecutive working day construction period. Despite many attempts by staff to work with MPTC on staffing allocation and establishing a construction make-up schedule, staff recognized MPTC’s inability to satisfactorily complete the work by the February 25, 2015 scheduled completion date. In a letter dated March 11, 2015 (Attachment B), MPTC was notified of the deficiencies and reminded of the $250.00 per calendar day liquidated damages. With much reluctance, the contract was substantially completed on April 24, 2015, which exceeded the construction period by 42 days. In a letter dated July 7, 2015 (Attachment C), the City further withheld $40,453.53 due to MPTC’s inability to provide a SpectraTurf manufacturer warranty, maintain their certified installer status, and installation of unapproved flexible play surfacing material. This deduction is proportional to the amount of unwarrantable work. Upon final negotiations, staff recommends deducting a total of $50,953.50 from MPTC’s final contract and terminates Contract No. 5855. A summary of the project schedule is as follows: ENVIRONMENTAL REVIEW: On November 25, 2014 the City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302(c) (Construction resulting in no expansion of facility capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A – Location Map Attachment B – Letter to MPTC for Liquidated Damages - Dated March 11, 2015 Attachment C – Letter to MPTC to Provide Warranty - Dated July 7, 2015 Estimated Completion Date per 2014 Baseline Schedule March 30, 2015 Project Awarded for Construction November 25, 2014 Contract Completion Date with Approved Extensions February 25, 2015 Actual Substantial Construction Completion Date April 24, 2015 9-4 9-5 9-6