RE: Structural Certification for Installation of Residential Solar
Halley, Lynne:9 Royal St. George Rd, Newport Beach, CA 92660
Attn: To Whom It May Concern
PU220101; 111
01 vm6u St. GAto%e"/
276-220-0064
This Letter is for the existing roof framing which supports the new PV modules as well as the attachment of
the PV system to existing roof framing. From the field observation report, the roof is made of Composition
shingle roofing over roof plywood supported by 2X6 Rafters at 24 inches . The slope of the roof was
approximated to be 18 degrees and having an allowable maximum beam span of 8 feet between supports.
After review of the field observation data and based on our structural capacity calculation, the existing roof
framing has been determined to be adequate to support the imposed loads without structural upgrades.
Capacity calculations were done in accordance with applicable building codes.
Design Criteria
Code 2016 California Building Code (ASCE 7-10)
Risk category II Wind Load (component and Cladding)
Roof Dead Load Dr 10 psf V 110 mph
PV Dead Load DPV 3 psf Exposure C
Roof Live Load Lr 20 psf
Ground Snow S
0 psf
If you have any questions on the above, please do not hesitate to call.
Sincerely,
Eugene Munyanziza, P.E.
EV Engineering, LLC
prolects(@evengineersnet.com
http://Www.evengineersnet.com
Current
Rome_wable,.
Engineering
Exp:06/30/2020
951-254-5655
Projects@currentrenewableseng.com
http://www.currentrenewableseng.com/
Building Division
OCT 0 2 2019
1/1
11
=� EV projects@evengineersnet.com 276-220-0064
ENGINEERS http://www.evengineersnet.com
Structural Letter for PV Installation
Date:
Job Address:
Job Name:
Job Number:
Scope of Work
This Letter is for the existing roof framing which supports the new PV modules as well as the attachment of
the PV system to existing roof framing. All PV mounting equipment shall be designed and installed per
manufacturer's approved installation specifications.
Table of Content
Sheet
1 Cover
2 Attachment checks
3 Snow and Roof Framing Check
4 Seismic Check and Scope of work
Code
2016 �ajifvrma Budd11
ln$eod� (ASC
Risk category
II
Roof Dead Load
Dr
10 psf
PV Dead Load
DPV
3 psf
Roof Live Load
Lr
20 psf
Ground Snow
S
0 psf
Wind Load
(component
and Cladding)
V
mph
Exposure
C
References
1 California Residential Code 2016
2 NDS for Wood Construction
Sincerely,
Eugene Munyanziza, P.E.
EV Engineering, LLC
projects@evengineersnet.com
httl3://www.evengineersnet.com
Current
Renewables.
Engineering
Exp:06/30/2020
951-254-5655
Projects@currentrenewableseng.com
http://www.currentrenewableseng.com/
=! EV projects@evengineersnet.com
ENGINEERS http://www.evengineersnet.com
Wind Load Cont.
Risk Category = II ASCE 7-10 Table 1.5-1
Wind Speed (3s gust), V „ 11'Q mph ASCE 7-10 Figure 26.5-1A
Roughness= C ASCE 7-10 Sec 26.7.2
ExposureASCE 7-10 Sec 26.7.3
Topographic Factor, Kn=
1.00 ASCE 7-10 Sec 26.8.2
Ridge Height =
14.0 ft
Eave Height =
9.0 ft
Mean Roof Height, h =
13.0 ft
Pitch =. '
SB�d�Degrees
Adjustment Factor, X =
1.21 ASCE 7-10 Figure 30.5-1
Buidling Width =
55.0 ft
Building Length =
100.0 ft
a = 3.60 ft ASCE 7-10 Figure 30.5-1
Where a: 10% of least horizontal dimension or 0.4h, whichever is smaller, but not less than 4% of least
horizontal dimension or aft (0.9m)
Uplift (0.6W) Zone 1(psf) Zone 2 (psf) Zone 3 (psf)
Pnet30= -18.1 -25.5 -40.2 Figure 30.5-1
Pnet= 0.6 x), x KZT x Pnet30)= 13.14 18.51 29.19 Equation 30.5-1
Downoressure (0.6W) Zone 1 (psf) Zone 2 (psf) Zone 3 (psf)
Pnet30= 9.7 9.7 9.7 Figure 30.5-1
Pnet = 0.6 x T x KZT x Pnet30)= 7.04 7.04 7.04 Equation 30.5-1
Rafter Attachments: 0.6D+0.6W (CD=1.6
Lag Screw Connection
Attachement max. spacing= fi ft
5/16" Lag Screw Withdrawl Value= 266 Ib/in Table 12.2A - NDS
Lag Screw Penetration= 2.S in DFLassumed
Prying Coefficient 1.4
Allowable Capacity with CD= 760 Ib
0.6D+0.6W Dpv+0.6W
Zone Trib Width Area (ft) Uplift (lbs) Down (lbs)
1 6 16.5 187.1 165.7
2 6 16.5 275.8 165.7
3 3 8.3 225.9 82.8
Max= 275.8 < 760
CONNECTION IS OK'
1. Pv seismic dead weight is negligible to result in significant seismic uplif, therefore the wind uplift
governs
2. Embedment is measured from the top of the framing member to the tapered tip of a lag screw.
Embedment in sheading or other material does not count.
4Current 951-254-5655
"0.'s Renew able Projects@currentrenewableseng.com
4 " Engineering http://www.currentrenewableseng.com/
276-220-0064
=,WEV projects@evengineersnet.com
90111111111ENGINEERS http://www.evengineersnet.com
276-220-0064
Max Length, L = `
8i0` ft
(Beam it7awmum Allgwdble Horizohtal Span) <
Tributary Width, WT =
24 in
Dr=
10 psf
20 plf
L, =
20 psf
Design Value
Wdown=
7.04 psf
42.3 plf
PV=
3 psf
18 PH
Load Case:DL+0.6W (CD=1.6)
Pv max Shear 165.7 lbs
Max Moment, Mu= wLz/8 = 642 Ib -ft Conservative
Max Shear, V,= wL/2+Pv Point Load = 318 Ib
Load for deflection= 20.0 psf < Dr+Lr= 30 psfK.. .,.
Note: Proposed loading will add less than 10% of the existing loads.
Member Caoacity
IDF-L'fyo;2;�
Design Value
Cr
Cr
Ci
C,
Kr
X
Adjusted Value
Fb =
900 psi
1.0
1.3
1.0
1.15
2.54
0.85
0.8
2324 psi
F„=
180 psi
N/A
N/A
1.0
N/A
2.88
0.75
0.8
311 psi
E =
1600000 psi
N/A
N/A
1.0
N/A
N/A
N/A
N/A
1600000 psi
Em;n =
580000 psi
N/A
N/A
1.0
N/A
1.76
0.85
N/A
867680 psi
Depth, d =
Width, b =
Cross-Sectonal Area, A =
Moment of Inertia, Ixx =
Section Modulus, Sxx =
Allowable Moment, Mall = Fb Sxx =
Allowable Shear, Vail= 2/3F„'A =
Current
Renewables.
Engineering
5.5 in
1.5 in
8.25 in'
20.7969 in 4
7.5625 in'
1464.6 Ib -ft DCR=M„/M,ii = 0.27 < 1
1710.7 Ib DCR=VdVall = 0.19 < 1
951-254-5655
Projects@currentrenewableseng.com
http://www.currentrenewableseng.com/
MT EV projects@evengineersnet.com 276-220-0064
� ENGINEERS http://www.evengineersnet.com
Siesmic Loads Check
Roof Dead Load
10 psf
% or Roof with Pv
47%
Dpv and Racking
3psf
Averarage Total Dead Load
11.4 psf
Increase in Dead Load
5.6% OK 1
The increase in seismic Dead weight as a result of the solar system is less than 10% of the existing structure and
therefore no further seismic analysis is required.
Limits of Scope of Work and Liability
We have based our structural capacity determination on information in pictures and a drawing set titled PV plans -
Halley, Lynne. The analysis was according to applicable building codes, professional engineering and design
experience, opinions and judgments. The calculations produced for this dwelling's assessment are only for the
proposed solar panel installation referenced in the stamped plan set and were made according to generally
recognized structural analysis standards and procedures.
Current 951-254-5655
Hencawablos, Projects@currentrenewableseng.com
Engineering http://www.currentrenewableseng.com/