Loading...
HomeMy WebLinkAboutC-1123(A) - Combined capital projects, 1968/69, Corona del Mar areaApril 28, 1969 TO: CITY COUNCIL FROM: Public Works Department SUBJECT: ACCEPTANCE OF COMBINED CAPITAL IMPROVEMENTS, 1968 -69, CORONA DEL MAR (C -1123) RECOMMENDATIONS: 8 1. Accept the work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the bonds 35 days after the Notice of Completion has been filed. 4. Authorize time extension of 45 days. 5. Confirm Public Works approval of Change Orders 6, 7, & 8, in the amount of $9,772.10. 6. Authorize immediate payment of all money remaining due the Contractor. DISCUSSION: The contract for the construction of the Combined Capital Improvement Projects, 1968 -69, Corona del Mar area has been completed to the satisfaction of the Public Works Department. The bid price was: $215,863.00 Amount of unit price items constructed: 231,643.45 Amount of Change Orders: 10,987.25 Total Contract Cost: 242,630.70 Amount budgeted: 262,500.00 After award of the contract, it was found that approximately 100 additional water services would have to be replaced. These plus increases in other quantities accounts for the difference between the bid price and total bid items contracted. Change Orders 1 through 5 were for minor additions and revisions. As the first lift of asphalt was being placed on Second Avenue, a number of unforeseen soft spots developed in the sub - grade. Change Order #6 was issued authorizing the removal and replacement of the soft material. The cost was $1,171.72. Change Order #7 was issued authorizing the regrading of the parkways. The cost Was $1,751.03. . Due to the problems encountered with the soft sub -grade on Second Avenue, it was decided that an additional thickness of asphaltic concrete should be placed immediately. Previously it had been assumed that this could be deferred for two to three years. The Contractor had included the cost of excavation in his bid price for asphaltic concrete. A new price was agreed upon for the additional quantity required. Change Order #8 was issued confirming this unit price. The total cost was $6,849.35. The Contractor does not agree with the method and amount of payment for one of the contract items. It is not known at this time if he will pursue this matter further. The contract called for all work to be completed by December 10, 1968. Time extensions of 28 days for extra work and 17 days for rain are recommended. The work was substantially completed with the paving of Second Avenue on the first dry day, January 28,1969. DATE APR 2 8 1969 Page 2 April 28, 1969 Subject: Acceptance of Combined Capital Improvements, 1968 -69 (C -1123) Acceptance of the contract has been delayed while resolving differences in the measured amounts of the items of work and in attempting to resolve the remaining disputed pay item. Due to this delay, it is recommended that the requirement that 10% of the total contract amount be withheld for 35 days be waived and that all money due be paid immediately. No claims against the Contractor have been received. The bonds will be retained for the 35 day period. eph Devlin lic ks Director ldg UNITED PACIFIC INSURANCE COMPANY A MEMBER OF UNITED PACIFIC INSURANCE GROUP HOME OFFICE: TACOMA, WASHINGTON -1 _ m -. w.ika., - a 4t m..,i :: .��n ��g�. 5 41 CERTIFICATE OF INSURANCE This is to certify that the following policy of insurance, covering as stated, has been issued by the UNITED PACIFIC INSURANCE COMPANY of Tacoma, Washington, and is in force as indicated: This Certificate No. 2 , is evidence of Policy No. CLP 16525 , and is effective q/26 69 and expires p 6/7/69 at the hour designated in said policy, issued to (Monts -trey -Year) (Month Pay -1'e er) CLARENCE LANG DBA: CLARENCE LANG CEMENT CONTRACTORS (Name of Insured) by the UNITED PAC IF IC INSURANCE COMPANY. ADDITIONAL INTERESTS (Only items marked C are affected by this endorsement.) It is agreed that in consideration of a premium of $ TO BE DETERMINED BY AUDIT _ __ . (Enter amount -or 'included', 'charged', 'to be determined by audit', etc.) 1. The below name is (are) included as arW additional insured: 11 named insured: (see note below)` CITY OF NEWPORT BEACH 2. But only as respects the following: 4 SUBJECT OF INSURANCE COVERAGES AMOUNT OR LIMIT Operations performed by or for the BODILY INJURY $100,000. Ea. Person Named Insured, except liability for 300,000. Ea, Occurrenc damages assumed by Contract. PROPERTY DAMAGE 25,000. Ea. Occurrenc 50,000. Aggregate Owned by— _—_�.._.— . —_ — »> (Enter name -or 'him','them','it') 3. While: Maintained or used by,—.—.— >., --- _ .� `him —. —,., (Enter name -or ', 'them', 'it') In connection with operations for the City of Newport Beach TRjd 3/26/69 'Note: The insurance afforded by the policy applies separately to each insured against whom claim is made or suit is brought, but the inclusion herein of more than one insured shall not operate to increase the limits of the company's liability. 0 PRESIaENT Countersigned by. G -31 9-64 AUTHORIZED REPRESENTATIVE • G Agent WG H. RUTLEDGE INSURANCE This Endorsement No. I . forms a part of Policy No. CLP 16525 , and Is effective * 9 -3 -68 of the hour designated in said policy, issued to * CLARENCE LANG and JOHN COLE (MONTH-DAY-YEAR) DBA: LANG & COLE CEMENT CONTRACTORS by the UNITED PACIFIC INSURANCE COMPANY, *These spaces need not be completed if this endorsement and the policy bear the some inception data AMENDMENT OF POLICY (No Premium Change) It is agreed that the Only items marked Q are hereby affected. Q Principal Place of Guroging Q Location of Premises Q Nome of Mortgagee or Loss Payee Q Addreas of Mortgagee or Low Payee Q i i) t?Afta„c. t�f Antr•I ck' - a.) {10 6r1Gt7C: All terms and conditions of the policy to which this endorsement is attached remain unchanged except es herein specifically provided. RMjd 9/10/68 Counfarsigned by �� ''`.•'. ..'. ". � - .. -... _. Authorized Representative •wen oser C-28 9.56 t r Name of Insured Q Description of Automobile and Purchase Information �] Address of Insured Q Motor Number Q Policy Period Q Serial Number Q Coverage Q Occupation or Principal Business of Named Insured Q Limits of Liability Q Employer's Name & Description of Business is (are) amended as follows: CLARENCE LANG DBA: CLARENCE LANG CEMENT CONTRACTORS Only items marked Q are hereby affected. Q Principal Place of Guroging Q Location of Premises Q Nome of Mortgagee or Loss Payee Q Addreas of Mortgagee or Low Payee Q i i) t?Afta„c. t�f Antr•I ck' - a.) {10 6r1Gt7C: All terms and conditions of the policy to which this endorsement is attached remain unchanged except es herein specifically provided. RMjd 9/10/68 Counfarsigned by �� ''`.•'. ..'. ". � - .. -... _. Authorized Representative •wen oser C-28 9.56 t r UNITED PACIFIC INSURANCE COMPANY HOME OFFICE: TACOMA, WASHINGTON Agent CRAIG N RUTLEDGE INSURANCE Renews NEW Replaces COMPREHENSIVE LIABILITY DECLARATIONS POLICY Policy Number c LP 16 5 2 5 1. NAME OF INSURED CLARENCE LANG and JOHN COLE DBA: LANG 6 COLE CEMENT CONTRACTORS 24191 ANICERTON DRIVE 2. EL TORO, CALIF. ADDRESS OF INSURED 3. From 6 -7 -68 to 6 -7 -69 at 12:01 A.M. POLICY PERIOD (Month- Day-Year) (Month- Day-Year) standard time at the address of the named insured as stated herein. 4. The insurance afforded is only with respect to such and so many of the following coverages as are indicated by insertion of the limit of the Company's liability opposite the coverage. The limit of the Company's liability for each such coverage shall be as stated herein, subject to the terms of this policy having reference thereto. COVERAGES LIMITS OF LIABILITY MULTIPLE LIMIT PLAN: Bodily Injury Automobile S 100, 000. Each Person $ 300, 000. Each Occurrence - Liability Other than Automobile $ 100,000. Each Person $ 300,000. Each Occurrence $ 300,000. Aggregate Products - Completed Operations Property Damage Automobile $ 25,000. Each Occurrence Liability Other than Automobile S 25,000. Each Occurrence $ 250000. Aggregate SINGLE LIMIT PLAN Bodily Injury Liability Automobile $ Each Occurrence and Property Damage Liability Other than Automobile $ Each Occurrence $ Aggregate 5. ADDITIONAL INSURANCE: The following insurance is provided only for those coverages for which a Specific Amount, Limit of Liability or the word "Included" is entered below and then only in accordance with the provisions of the applicable coverage form attached to this policy: COVERAGE FORM AND COVERAGES j A. Personal Comprehensive [ ] Limits of Liability Multiple Limit Bodily Injury { $ Each Person $ Each Occurrence Personal Liability Plan: Property Damage $ Each Occurrence Single Limit Bodily Injury and { $ } Each Occurrence Plan: Property Damage Personal Medical Payments $ Each Person $ Each Accident B. Medical Payments [ ] Limits of Liability 1 Pmk-up body, sedan delivery or Automobile S Each Person - Private Passenger El Panel truck types are excluded if. , Type Owned 1 x" appears in the box. Automobile $ Each Person - Other than Private Passenger Type Owned Business $ Each Person $ Each Accident C. Automobile Physical Damage ❑ H. O Bodily Injury caused by Only Items Marked ❑ I• Uninsured Automobiles E. Broad Form Property Damage QX ❑ 1• F. Personal Injury Are "Included" ❑ H. G. Fire Legal Liability • Commercial ❑ L. S. The provisional deposit premium is $ 122. If the policy period is for more than one year, an additional provisional de p sit ranrium sh V be charged for each succeeding annual period. The premium is subject to ANNUAL dit. Countersigned b L ---�Authcri2ed Alfeat THESE DECLARATIONS WITH FORM CLP•99 3.65 CONSTITUTE THE ABOVE NUMBERED POLICY i l0 t„_ int A' r .Ito ,.. L k f 'v R r t , S,y t„_ int A' L k f R r t , S,y I t 4 IL .... $r �B t„_ int A' S 7 4:5)AO1f'-7 OAP,I A-V � MJ N a Ac k S 7 4:5)AO1f'-7 OAP,I A-V Ti i . a - A2 _ I �tv t R4> � a A _ I �tv t R4> � a 717 ,—Aw,.e. .� J s - -Z!s I I JK \,c. = - k, Nit IZ C- (4 2-Z - C-V7-�j, 0 bra 4CL_ C---3 1lp -*I- Q OMAN - I . ml_ TO: CITY COUNCIL FROM: Public Works Department f July 22, 1568 G_1� SUBJECT: COMBINED CAPITAL IMPROVEMENT PROJECTS, CORONA DEL MAR AREA, 1968 -69 CONTRACT 1123 RECOMMENDATIONS: Adopt a resolution awarding the contract to Walker & Bates for $215,863.00 and authorizing the Mayor and the City.Clerk to execute the contract. DISCUSSION: Three bids were received and opened in the office of the City Cleric at 10:00 A.M. on July 17, 1968. BIDDER ALT. 'A' ALT. 'B' Walker & Bates, Riverside $215,863.00 $236,305.00 Lynam -Wood, Corona Del Mar 224,209.90 256,904.90 Sully - Miller, Long Beach 245,623.00 ---- - - - - -- Alternate 'A' represents Asphalt Concrete pavement for Second Avenue; and 7 Alternate 'B' represents Portland Cement Concrete pavement for Second Avenue. The low bid for Alternate 'A' is 3% lower than the Engineer's estimate of $222,000 and for Alternate 'B' is 4% lower th i an the Engineer's estimate of $247,000. The work included in the contract and the funds available are: Storm Drain in Second Avenue $28,500.00 Annual Sewer System Betterment Program 4,000.00 Reconstruct Second Avenue in Corona Del Mar 13,000.00 Annual Street Reconstruction and Resurfacing Program 58,000.00 Reconstruct Alleys in Corona Del Mar 68,000.00 Annual Alley Reconstruction and Resurfacing Program 5,000.00 Construct 12 inch Water Main in Second Avenue, Corona del Mar 41,000.00 Annual Water Main Replacement Program 32,000.00 , An economic analysis of the two alternates indicates that the advantages of Portland Cement Concrete pavement for Second Avenue do not justify the substantial cost •' differential, therefore award based on Alternate 'A' is recommended. Special effort will be devoted to minimizing inconvenience to adjacent property owners and to vehicular traffic; however, it is emphasized that a certain amount of incon- venience will be unavoidable. The plans were prepared by the City. The estimated date of completion is.November 30, 1968. QADn APPROVED BY CITY COUNCIL . c� JUL 2 2 1968 oseph T Devlin DATE ublic rks Director DHW/rjh 0 TO: CITY COUNCIL FROM: Public Works Department 49 June 24, 1968 //-Z/ SUBJECT: COMBINED CAPITAL IMPROVEMENT PROJECTS - CORONA DEL MAR AREA, 1968 -69 (Contract 1123) APPROVED BY CITY COUNCIL RECOMMENDATION: DATE JUN c 4 1868 1. Approve the Plans and Specifications. 2. Authorize the City Clerk to advertise for bids to be opened at 10:00 A.M. on July 16, 1968. DISCUSSION: This contract consists of eight separately funded Capital Improvement projects within the Corona del Mar area. It is felt that lower unit prices will be obtained by combining these projects under one large contract. The Proposal includes alternate pavement surface materials for Second Avenue. Alternate "A" includes Asphaltic Concrete pavement and Alternate "B" includes Portland Cement Concrete pavement. The estimated cost of the work is: Alternate "A" Alternate "B" Storm Drain in Second Avenue $ 29,000 Sewer Main Relocation in Second Ave. 4,000 Second Ave. Reconstruction 46,000 Alley Reconstruction 739000 12 inch Water Main in Second Ave. 38,000 Water Main Replacement (Alleys) 32,000 U"d �fc ��nl a3.aoo $222,000 Funds available are: Storm Drain in Second Ave. Annual Sewer System Betterment Program Reconstruct Second Ave. in Corona del Mar Annual Street Reconstruction and Resurfacing Program Reconstruct Alleys in Corona del Mar Annual Alley Reconstruction and Resurfacing Program Construct 12 inch Water Main in Second Ave., Corona del Mar Annual Water Main Replacement Program $ 29,000 4,000 71,000 73,000 38,000 32,000 $247,000 {— /vv.00v $ 28,500enz- 4, 000,E -;._ .a-t 131000.,+ - <::•,»_ 58,000 68,000 ' 5,000 41,000 7_�o;. 32,000 $249,500 The availability of the funds is contingent upon Council approval of these items as presented in the Capital Improvement Projects section of the 1968 -69 City Budget. This project is being presented at this time in view of the need to reconstruct the alleys and Second Avenue as soon as possible and to construct the storm drain before the rainy season. Page 2 Subject: Combined Capital Improvement Projects - Corona del Mar Area, 1968 -69 (Contract 1123) The large quantity of underground construction also dictates that the work begin as soon as possible. A brief description of the portions of the project is indicated below: A. Storm Drain in Second Avenue. This portion of the project provides for a new storm drain system to carry the high intensity storm water flows from East Coast Highway to the Bay. The new drain will reduce the problem of these waters flowing over the curb at the existing sump in Fernleaf Avenue during periods of peak runoff. B. Annual Sewer S stem Betterment Program. This portion of the project provi es for construction of a sewer main at the intersection of Second and Dahlia Avenues to replace a section of main that now crosses over private property and under an existing structure. C. Reconstruct Second Avenue. This portion of the project provides for reconstruction of Second Avenue between Avocado and Heliotrope Avenues. The work includes replacement of curbs, gutters, alley approaches and cross gutters. The scope of the work now proposed in Second Avenue has been considerably expanded over that contem- plated when the original $13,000 appropriation was made a year ago; in addition the original appropriation represented only the differ- ential cost between reconstruction and the resurfacing work needed for the underground construction proposed. Thus additional funding is being provided from the street reconstruction program. An opening through the median in Avocado Avenue will also be con- structed. This opening will provide better vehicular circulation in the area. The priority of this work has been established in the Street and Alley Maintenance Study and was originally budgeted for reconstruction in Fiscal Year 1967 -68. The Proposal has been arranged to allow for alternate bids of Asphaltic Concrete or Portland Cement Concrete paving of Second Avenue. Because the alleys are to be reconstructed with Portland Cement Concrete, it is felt that a reasonably favorable price may be received for that alternate. The final choice of pavement material for Second Avenue at time of contract award will be subject to review of the initial cost, the anticipated life of the.material, and anticipated future maintenance cost. D, Reconstruction of Alleys in Corona del Mar. The alleys to be recon- structed in this project are to be paved with Portland Cement Concrete. the width of these alleys is such that the initial cost of P.C.C. is comparable to Asphaltic Concrete. The longer life, maintenance cost savings, and nature of the soil in the area determine the choice of P.C.C. 4 Page 3 Subject: Combined Capital Improvement Projects - Corona del Mar Area, 1968 -69 (Contract 1123) The priority of the alleys to be reconstructed has been established in the Street and Alley Maintenance Study. Due to the limited funds available, in 50% of the alleys, only that portion that has completely failed will be reconstructed. The actual amount of reconstruction per alley will depend upon the unit prices in the contract. In all cases the entire alley has been designed to provide for future reconstruction. E. Construct 12 inch Water Main in Second Avenue. This portion of the project will provide for construction of a 12 inch water main in Second Avenue from Avocado Avenue to Heliotrope Avenue. This main was recommended in a previous study by Montgomery Engineers in order to strengthen the system in the area. F. Annual Water Main Re lacement Pro ram. This portion of the project wi provide or the rep acement of deteriorated mains that exist where alleys are to be reconstructed. The new mains will maintain adequate flows for domestic and fire service requirements. The plans were prepared by the City. The estimated date of completion is November 30, 1968. Joseph T, Devlin Public Works Director DHW /ldg INDEX TO SPECIAL PROVISIONS I. SCOPE OF WORK 2. CONDUCT OF WORK 3. , COMPLETION OF WORK 4. SCHEDULE OF WORK 5: AWARD OF CONTRACT 6. :PAYMENT 7. GUARANTEE 8.. TRAFFIC CONTROL 9. EXISTING TRAFFIC SIGNS AND MARKERS 10. WORK ON PRIVATE PROPERTY 11. NOTIFICATION TO RESIDENTS AND BUSINESSES 12. UNFORESEEN DIFFICULTIES 13. CONSTRUCTION SURVEYS 14. PROTECTION OF EXISTING IMPROVEMENTS AND UTILITIES 15. CLEARING, GRUBBING, AND TREE TRIMMING 16. WATER 17. ADJUSTING UTILITY BOXES, MANHOLES, VALVE COVERS, SEWER CLEANOUTS, ETC., TO FINISHED GRADE 18. EARTHWORK 19. AGGREGATE BASE 20. ASPHALTIC CONCRETE M. PORTLAND CEMENT CONCRETE 22.. ADJUSTMENT OR REMOVAL AND REPLACEMENT OF WALKS AND LANDINGS 23. REINFORCING AND STRUCTURAL STEEL PAGE 1 2 2 PA 2 3 3 3 4 4 4 4 5 5 5 6 6 7 8 9 10 13 13 24; STORM DRAIN 25. SEWERS 26. WATER MAINS 27. REPLACE AND RECONNECT EXISTING WATER SERVICES (INCLUDING NEW SERVICES) 28. SAND PIPE BEDDING 29. LOWERING EXISTING STREET LIGHT CONDUIT 30. ADJUSTING MEDIAN SPRINKLER SYSTEM STANDARD DRAWINGS PAGE 13 15 16 18 19 19 19 SPlof19 CITY' OF' NEWPORT BEACH PUBLIC WORKS DEPARTMENT •M • • Y O:; CONTRACT NUMBER 1123 1. SCOPE OF WORK The work to be done under this Contract consists of six separate projects: (1) Project 1123A - Reconstruction of all or part of 23 alleys at various locations: Drawings A- 5029 -S through A- 5036 -S; Contract Sheets 2 -10. (2) Project 1123B - Reconstruction of Second Avenue from Avocado �... .._ u,. _ _..yam s _.y� ��_� z�, _,___ ,_ _•:�.,�;t.�.., -�-° �- Avenue to Heliotrope Avenue: Drawing R- 5618 -S; Contract Sheets 11 -17. (3) Proiect 1123C - Construction of a 12 -inch water main in Second Avenue from Avocado Avenue to Goldenrod Avenue: Drawing W- 5055 -S; Contract Sheets 18 -21. ' (4) Project 1123D - Construction of a storm drain in Fernleaf, Second, and Dahlia Avenues: Drawing D- 5039 -S; Contract Sheets 22, 23, and 24. i (5) Project 1123E - Construction of an 8 -inch sewer main in Second and Dahlia Avenues: Drawing S- 5027 -S; Contract Sheet 25. ' (6) Project 1123F - Replacement of 6 -inch water mains in various alleys: Drawings A- 5028 -S, A- 5029 -S, A- 5034 -S, A- 5035 =S, and A- 5036 -S; Contract Sheets 2, 3, 8, 9, and 10. ' �... .._ u,. _ _..yam s _.y� ��_� z�, _,___ ,_ _•:�.,�;t.�.., -�-° �- • • SP 2 of .19 The work, requires furnishing all Ubnr, ,bn, eriahs, "transportation, and:: equipment necessary to complete all work shown on the Plans in accordance with these Special Provisions, the City of Newport Beach's Standard Drawings, and Specifications, and applicable provisions of the State of California, Division of Highways' Standard Specifications, dated July, 1964. 2. CONDUCT OF WORK The Contractor shall maintain all job sites in a neat and orderly condition at all times. Excess spoil, debris, and broken pavement must be immediately removed from the job sites. The sites must be returned to an orderly condition,, as approved by the Engineer, as soon as the work is completed. ' The cost of all removal and cleanup work shall be included in the unit prices bid for the.various items of work and no additional payment will be made. t3, ..COMPLETION OF WORK ' The Contractor shall complete all work on the Contract within 120 consecutive calendar days after the date of execution of the Contract by the City. 4. SCHEDULE OF WORK A complete schedule of the Contractor's proposed sequence of construction must be submitted, in writing, to the City within ten (10) days after award of the Contract by the City Council. No work shall commence on any part ' of the Project until the schedule has been reviewed by the City with the Contractor, and the City has approved the schedule in writing. ' The Contractor must then make every effort possible to comply with the approved schedule. Deviation from the schedule may require a cessation of the work until a revised schedule has been resubmitted and approved in like fashion, by the City. Delays resulting from such an event will be the Contractor's responsibility and no additional time will be allowed for completion of the work. 1 .5. AWARD OF CONTRACT ' All Contractors are strongly encouraged to submit bids for both Alternate "A" and Alternate "B"; however submittal of a bid for only one Alternate will not constitute an incomplete bid. The City reserves the right to award the Contract for either Alternate "A" or Alternate "B ", regardless of which Alternate results in the lowest total bid. fl L • • SP 3 of 19 6. PAYMENT The prices bid for the various items of work shall include full compensation for all labor and materials necessary for construction of the items complete in place. Payment for incidental items of work not separately provided for in this Proposal shall be included in the price bid for other items of work. Where applicable, the prices bid for items of new construction shall include removal and disposal of the existing improvements. ;..� The Contractor shall guarantee, for a period of one year after acceptance of the Contract by the City Council, all materials and workmanship against any defects whatsoever, including trench and pavement settlement. Any such defects shall be immediately repaired at the Contractor's expense. 8. TRAFFIC CONTROL ' a. Traffic Control Plan. The Contractor must submit, with his Work Schedule, a Plan showing the methods, types and locations of traffic control to be used for all construction phases. This Plan must also be approved by ' the City before any construction commences. If modifications of the Plan are required during the construction period, each modification must be approved by the City prior to altering the previously approved Plan. b. Flagmen and Warning Devices, Barricades, warning devices and flagmen must be provided as indicated on this approved Plan or when, in the ' opinion of the Engineer, they are required for public safety or convenience. C. Areas Closed to Vehicular Traffic. Temporary closing of through 1 vehicular traffic will be permitted on Second Avenue, Fernleaf Avenue, and Dahlia Avenue, and at various alley locations during construction operations. The Contractor shall program his operations so as to minimize inconvenience to the public and so as to minimize inaccessibility to private properties from the alleys and streets involved. Attention is directed to the section of these Special Provisions regarding curing time and protection of concrete pavements. ' d. Access to Private Property. Vehicular access from either a public street or alley shall be maintained to all properties adjacent to the work. ' Reconstruction of alleys number 22b, 22c, and 23a, shall not begin until thru vehicular traffic is permitted on Fernleaf, Dahlia, and Second Avenues, unless otherwise directed by the Engineer. ' Temporary vehicular access shall be maintained from the nearest intersecting street or alley to private driveways on Second Avenue and Fernleaf Avenue. • SP4of 19 = Y: e. Traffic Circulation. In the event that the Contractor elects to close ' Second Avenue during the various construction operations, he shall provide temporary street crossings at alternate intersecting streets. . Detour signing must be maintained to provide adequate warning and traffic circulation acceptable to the Engineer. One lane of traffic must be maintained at all times on Avocado Avenue and Heliotrope Avenue. ' The cost of providing traffic control, including flagmen, warning devices, temporary detours, street crossings, etc. shall be included in the various ' bid items of work and no additional payment shall be made. 9. EXISTING TRAFFIC SIGNS AND MARKERS All traffic signs and markers that interfere with the work in this Contract, whether shown on the Plans or not, shall be removed by the Contractor, ' salvaged, and delivered undamaged, to the City Corporation Yard, located at 59Z Superior Avenue, Newport Beach, California. ' The cost of removing and salvaging, and transporting traffic signs and markers shall be included in the various items of work and no additional payment will be made. 10. WORK ON PRIVATE PROPERTY It shall be the responsibility of the Contractor to make arrangements to work.on private property when necessary to join existing improvements.' ' Advance notices describing the work and stating the name of the Contractor will be delivered to the residents and /or property owners adjacent to the work locations. These notices will not relieve the Contractor of his responsibility for notification as covered in Section 11 of these Special Provisions. ' 11. NOTIFICATION TO RESIDENTS AND BUSINESSES The Contractor must distribute to each affected residence or business a written notice forty -eight (48) hours in advance of commencing any construction work that will involve temporary inaccessibilty to the front or rear of the properties. Said notice shall state when his operations will start and approximately when they will end. If, due to unknown conditions, acts of God, strikes, or other delays, the ending date differs materially from that estimated, a secondary notice must be distributed. 1Z, UNFORESEEN. DIFFICULTIES Should unknown conditions, subsurface or otherwise, be discovered during the progress of the work, the City shall be notified immediately, The City will then make a determination as to whether these conditions SP .5 of, 19 constitute extra work and so notify the Contractor in writing within forty -eight (48) hours of first being informed of the conditions. 13. CONSTRUCTION SURVEYS All field staking for the control of construction shall be the responsibility of the Contractor and shall be performed under the supervision of a civil engineer or land surveyor licensed to practice in the State of California. Payment for all staking shall be included in the unit prices bid for the various items of work and no additional payment will be made. 14. PROTECTION OF EXISTING IMPROVEMENTS AND UTILITIES The Contractor shall be responsible for the protection of all improvements adjacent to work, such as sprinkler systems, drain pipes, lawns, plantings, brick work, masonry work, fences, walls, etc, located on either public or private property. If, in the construction of the work, any improvements are removed or damaged, other than those designated on the drawings, then such improvements shall be replaced in kind at the Contractor's expense. The exact location of existing utilities shown or not shown on the plans shall be verified in the field at the time of construction. The Contractor shall request each utility company to locate their underground Panes prior to commencing work. The City does not guarantee the presence or absence of utilities in any location. It will be the Contractor's responsibility to locate and uncover the existing utility lines sufficiently in advance of the work to determine their location and to work around the utilities at his own expense. 15. CLEARING, GRUBBING, AND TREE TRIMMING After removal of the existing curb, gutter, sidewalk, street or alley pavements, etc. by,the Contractor, the City's Parks, Beaches, and Recreation Department will trim tree roots sufficiently to provide for normal reconstruction procedures. It shall be the Contractor's responsibility to trim shrubs, bushes, tree limbs, etc. where protruding within alley rights -of -way as required to accommodate normal construction procedures. Payment for clearing, grubbing, and tree trimming shall be included in the unit prices bid for the various items of work and no additional payment will be made. ' • SP6of 19 The cost of all adjustments is included in the cost of associated items of 16. WATER The Contractor shall make his own provisions for securing and applying water necessary to perform his work. If the Contractor desires to use City water, he shall make arrangements for water purchases by contacting ' the City's Utility Superintendent, Mr. Phillips, at (714) 673 -2110, ext. 74. Payment for developing, furnishing, and applying water shall be included in the unit prices bid "for the various items of work and no additional payment will be made. ' 17. ADJUSTING UTILITY BOXES, MANHOLES, VALVE COVERS, SEWER CLEANOUTS, ETC. TO FINISHED GRADE ' and covers shall be removed and the manhole structure covered with a a. General. Adjusting existing utility boxes, manholes, valve covers, sewer cleanouts, etc, to finished grade shall be in conformance with the Standard Specifications and these Special Provisions. ' Before beginning construction, the Contractor and the Engineer will determine what utility boxes and /or covers are broken. These will be ' reset by the Contractor. The materials will be paid for by the owner. Those boxes and /or covers broken during construction will be purchased and reset by the Contractor. ' In either case, the cost of resetting these facilities is included in the cost of other items of work and no additional payment will be made. The cost of all adjustments is included in the cost of associated items of work and no additional payment will be made. b: Portland Cement Concrete Paved Areas. All manholes, valve covers sewer cleanout covers, water meter boxes, gas and electric boxes, etc. shall be adjusted to finished grade before concrete paving. ' C. Asphaltic Concrete Paved Areas. Except as otherwise. authorized by the Engineer, manhole frames, valve covers, and sewer cleanout covers, ' etc. , within the asphaltic concrete pavement area shall not be set to final grade until the final paving has been completed. The manhole frames and covers shall be removed and the manhole structure covered with a steel plate unless the existing cover is sufficiently below grade so as not to form an obstruction during the construction of the subgrade or base and the spreading and rolling of the asphaltic concrete (AC). The manhole ' openings shall be temporarily covered by suitable means. After the pavement has been completed, the necessaryportions of the subgrade, ' base and pavement shall be neatly cut away, the manhole built up, and the frames set to a grade flush with the surface of the adjacent pavement. The surrounding area from which the pavement, base or sub -grade has _. n_! uLd�bd3 -3-- �iVkS_��..�.�. ++.'L':.� SP of 19 ' been removed shall be backfilled to within 1 =1/2- inches of the surface with Portland cement concrete (PCC) conforming to Section 13 of the City's Specifications. The remaining 1- 1 /2- inches shall be backfilled with asphalt concrete wearing surface and compacted, the work shall be so. performed as to present a neat and thoroughly workmanlike appearance ' upon completion. Disposal of excess excavation or the importation of fill materials thus required to prepare the subgrade plane as shown on the Plans, shall be at the Contractor's expense. ' b. Subgrade Preparation. Subgrade preparation shall conform to the provisions in Section 21 of the State Standard Specifications, except ' that the subgrade within 0. 5 foot below the grading plane shall have a relative compaction requirement of 90 percent in lieu of the 95 percent specified in Section 21 -1.02 of the State Standard Specifications and Section 10 -07 of the City's Specifications. All of the Contractor's cost of subgrade preparation shall be considered to be included in the various unit prices bid for items requiring subgrade preparation and no additional payment will be made. C. Street and Alley Excavation. .Street and alley excavation shall include all the work required to excavate and dispose of the various materials removed to accommodate the design grades and structural section, as shown on the Plans and in accordance with these Special Provisions. The cost of street and alley excavation shall be included in the unit prices bid for the various items of associated work and no additional payment will. be made, iM C= a_.:..2eFe •� ^A'��5'T ':; ^v ✓s �1.: ��a..;:...= F _ 18. EARTHWORK a. General. Earthwork shall conform to Section 10, and applicable portions of Sections 15 -19 of the City's Standard Specifications and these Special Provisions. The cost of removal and disposal of existing street and alley pavements, miscellaneous concrete, etc, shall be included in the unit prices bid for the various items of work, and no additional payment will be made. Existing asphaltic concrete, Portland cement concrete or stone surfaces in street areas shall be saw cut at the join lines shown on the Plans. Asphaltic concrete surfaces in alley areas shall be saw cut 8- inches ' behind the right -of -way line. Portland cement concrete surfaces in alley areas shall be saw cut at the right -of -way line, or as shown on the ' Plans or as directed by the Engineer. Overexcavation and /or excessive pavement removal, created by the Contractor's operations beyond the limits described herein or shown on t the Plans, shall be replaced in kind at the Contractor's expense. Disposal of excess excavation or the importation of fill materials thus required to prepare the subgrade plane as shown on the Plans, shall be at the Contractor's expense. ' b. Subgrade Preparation. Subgrade preparation shall conform to the provisions in Section 21 of the State Standard Specifications, except ' that the subgrade within 0. 5 foot below the grading plane shall have a relative compaction requirement of 90 percent in lieu of the 95 percent specified in Section 21 -1.02 of the State Standard Specifications and Section 10 -07 of the City's Specifications. All of the Contractor's cost of subgrade preparation shall be considered to be included in the various unit prices bid for items requiring subgrade preparation and no additional payment will be made. C. Street and Alley Excavation. .Street and alley excavation shall include all the work required to excavate and dispose of the various materials removed to accommodate the design grades and structural section, as shown on the Plans and in accordance with these Special Provisions. The cost of street and alley excavation shall be included in the unit prices bid for the various items of associated work and no additional payment will. be made, iM C= a_.:..2eFe •� ^A'��5'T ':; ^v ✓s �1.: ��a..;:...= F _ SP 8_of -19 d, . Structural Excavation and Backfill. Structural excavation and backfill shall conform to Sections 16 -04 and 16 -07 of the City's Specifications and these Special Provisions. Backfill materials at all structures shall have a sand equivalent of not less than 30, and shall have a relative compaction of not less than 90 percent. The.lump sum or unit price bid for the applicable structure shall include the cost of structure excavation and backfill and no additional payment will be made. e„ Trench Excavation and Backfill. Special care shall be taken when excavating across landscaped areas, medians, sprinkler systems, etc. These improvements shall be left in a condition acceptable to the Engineer. Damage occuring to these improvements as a result of the Contractor's operations. shall be replaced in kind at the Contractor's expense. The Contractor shall compact the trench in accordance with Section 16 -07 of the City's Specifications, using water and /or whatever supplementary means are necessary, such as vibratory compactors or rollers, mechanical tampers, concrete vibrators, etc. to achieve a uniform compaction of not less than 90 percent relative compaction and to positively prevent any future trench settlement. Payment for trench excavation and backfill shall be included in the unit prices bid for the various items of associated work and no additional payment will be made. ' 19. AGGREGATE BASE Aggregate shall conform to the provisions for Class Z aggregate base ' which is 1 -1/2 -inch maximum as specified in Section 26 of the State Standard Specifications and these Special Provisions, ' At least 65 percent by weight of the material retained on the No. 4 sieve shall have at least one fractured face as determined by Test Method No. California 205. ' The R -value requirement will not be waived as provided in Section Z6- 1.02A. The provisions of Section 26 -1.035 are superseded by the following: At the time aggregate base is spread, it may have a moisture content sufficient to obtain the required compaction. Such moisture shall be uniformly distributed throughout the material, In lieu of the spreading requirements specified in Section 26, aggregate base material shall be spread upon prepared subgrade by means of 1 - I SP 9 Of 19 approved spreading devices which will deposit apuniform windrow or layer, and after apreading as above specified, the material_ahall be shaped in accordance with Section 26. Motor graders may be used for the aforementioned shaping. 'Tailgate spreading of the material by dump trucks will not be permitted except for spot dumping and in areas not readily accessible to approved spreading devices.. The use of bottom dumps will be permitted. Compaction shall conform to Section 11 -04 of the City's Specifications. ' The unit price bid for aggregate base shall apply to all aggregate base utilazed at the various project locations for sub -base materials, and as required to provide ingress and egress to properties during the construction 'operations as directed by the Engineer. f 20.. ASPHALTIC CONCRETE a. General. The provisions of Section 12 of the City's Specifications ' shall govern the furnishing and placing of _asphaltic concrete. b. Asphaltic Concrete Street Pavement. Aggregate grading requirements for base course may be either medium or coarse grading, 3/4 -inch maximum, as specified in Section 392.02 of the State Standard Specifi- cations. The mineral aggregate for surface course shall be 3/4 -inch maximum- medium grading. The mineral aggregate for 1 -inch and variable AC cap shall be 1/2 -inch maximum -fine grading. The amount of asphalt binder to be mixed with the mineral aggregate shall be between 3 percent and 7 percent by weight of the dry mineral aggregate. The exact amount of asphalt binder to be mixed with the mineral aggregate will be determined by the City. The provisions in Section 39 -2.04A and 39 -2. 04B are superseded by the following. At least 75 percent by weight of the material retained in the No. 4 sieve shall have at least one fracture face as determined by Test Method No. Calif. 205. Prime coat and paint binder shall be applied in amounts specified in Section 12 of the City's Specifications. Prime coat shall be liquid asphalt grade SC -250. Paint binder (tack coat) shall be mixing type ' asphalt emulsion with a bituminous base grade of 60 -70 paving asphalt. The unit price bid for asphaltic concrete pavement shall include full ' compensation for tack and prime coating, placing and compacting the materials on the Plans or directed by the Engineer. where shown 1 - SP 10 of 19 s$ 400MRi c. Temporary Asphaltic Concrete Pavement Replacement Trench Areas. Immediately after backfilling trenches in existing paved areas not scheduled for.`aomplete reconstruction or where directed by the Engineer, the Contractor shall place a temporary 1 -1/2 -inch minimum thickness, asphaltic concrete pavement. This, temporary pavement, when placed, .shall be compacted with ' a small roller or other means approved by the Engineer, and shall be maintained in a safe and neat condition until the permanent pavement treplacement has been constructed. The unit, price bid for temporary pavement replacement shall include full compensation for the materials, placement, maintenance, and removal of this pavement. ' d. Permanent Asphaltic Concrete Pavement Replacement - Trench Areas. All trenched areas outside of the proposed street and alley pavement reconstruction area limits will require permanent pavement trench. replacement. constructed in ' accordance with Section 16 -08 of the City's Specifications except as follows: The unit price bid for permanent AC pavement replacement ' in trench areas shall include full compensation for placement and compaction of the material in all trench areas lying outside the limits of street and alley reconstruction. ' e. Miscellaneous Asphaltic Concrete Patching and Feathering. Miscellaneous asphaltic concrete patching shall include all AC required, as indicated on the ' Plans and directed by the Engineer, to patch between existing improvements and alley paving, approaches, or street improvements. ' Payment for patching adjacent to the concrete alley improvements constructed in this Contract shall be limited to a maximum width of eight (8) inches. Additional asphaltic concrete patching required due to the Contractor's ' operations, but not shown on the Plans or approved by the Engineer, shall be at the Contractor's expense. Asphaltic concrete patching thickness shall be a minimum of four (4) inches. Subgrade shall be compacted as specified herein for subgrade preparation. ' The unit price bid for miscellaneous asphalt patching shall include full compensation for subgrade compaction, tack or prime coat, and placing the asphaltic concrete patch. ' 21. PORTLAND CEMENT CONCRETE I ' a. General. Portland cement concrete shall conform to Section 13 of the City's Specifications and these Special Provisions. ' PCC used for drainage and sewer structures, street and alley pavements, alley approaches, cross gutters, and spandrels shall be Class "A ", 1 -1/2 -inch maximum gradation. ' SP11of19 I PCC used for curbs, gutters, and sidewalks shall be Class "B ", 1-1/2-inch maximum gradation. ' PCC shall be barricaded immediately after placement and no vehicular traffic allowed thereon until beam test specimens yield a minimum modulus of rupture *of 450 psi tested as specified herein. Attention is directed to the amount of water and slump test requirements of Section 13 of the City's Specifications and the traffic and use provisions specified herein. ' Curing of concrete shall commence as soon as free water leaves the surface of the concrete but not later than three hours following placement of the concrete upon the subgrade in accordance with Section 13 -08 of the City's Specifications. The Contractor will be permitted to use concrete pumping methods to P o facilitate concrete placement. umped concrete shall have 3/4 -inch maximum aggregate gradation and have a slump of 3 to 5 inches. Air entrainment agents may be added to the concrete to the extent that the resultant air content will be 5 -7 percent by volume of the concrete mixture. b. Structures. Drainage structures shall be constructed in conformance with Section 51 of the State Standard Specifications, these Special Provisions, and as shown on the Plans. The unit price bid for each structure or modification of a structure, shall include full compensation for the work on the structure, complete in place, ' including structural excavation and backfill, concrete, reinforcing steel, pipe connections, etc. and no additional payment will be made. C. Portland Cement Concrete Strength Requirements. The 6 -1/2 -inch thick PCC for street and alley pavements, cross - gutters, spandrels and alley approaches shall attain a minimum modulus of rupture of 600 psi within 28 days Iafter placement. Attention is directed to Section 6 of the City's Specifications. The City will be responsible for all PCC specimen testing. ' d. Street and Alley Pavements, 6 -1/2 inches Thick. Weakened plane and contact joints shall be constructed as shown on the Plans and these Special ' Provisions. After the concrete has cured, the contact joints shall be cleaned and filled with an approved joint filler. ' If the new pavement extends less than two feet onto private property, a score mark shall be made parallel to the alley center -line at the property lines. ' If the new pavement extends beyond two feet onto private property, a standard weakened plane joint shall be constructed on the property lines. 1 ! ! SP 12'of 1g 1 PCC, 6 -1/2- inches thick shall be used to patch between new PCC improvements and existing PCC improvements. The unit bid for street and alley pavement, shall include full compensation for subgrade preparation, adjustment of all utilities to grade, materials, labor, equipment, and all incidental items required to construct the pavement as specified herein. e. Cross Gutters, Spandrels, and Alley Approaches,. 6 -1/2- inches Thick. Portland cement concrete alley approaches shall be constructed in conformance with Section 15 of the City's Specifications, these Special Provisions, and as shown on the Plans. The Unit price bid for removal and /or construction of cross gutters, spandrels, and alley approaches shall include full compensation for constructing the item, complete in place,, including subgrade preparation, curb returns, and adjusting to grade any manhole, valve or sewer cleanout covers that are within the approach areas. f. Residential Drive Approaches. Portland cement concrete residential ' drive approaches shall be reconstructed in conformance to Section 15 of the City's Specifications,. these Special Provisions, and as shown on the Plans. The unit price bid for removal and replacement of residential drive approaches ' shall include full compensation for reconstructing this item, complete in place, as shown on the Plans. g. Curb and Gutter. Type "A" curb and gutter, 6 -inch and 8 -inch curb face, shall be constructed in conformance to Section 15 of the - Standard Specifications. Street pavement shall be sawcut two feet from the existing curb face to accommodate the new gutter. The newly constructed curb and gutter shall be warped within two feet of join locations shown on the Plans or as specified by the Engineer. Curb and gutter flow lines shall remain at a constant grade to assure drainage flow. Aggregate base shall be placed under the new curb and gutter as shown on the Plans. The unit price bid per linear foot of Type "A" curb and gutter, 6 -inch and 8 =inch curb face, shall include all compensation for removing existing curb and gutter, preparing subgrade, including aggregate base, and constructing the specified curb and gutter as shown on the Plans. 1 Concrete curb and gutter will be measured for payment by the linear foot, in place, excluding those areas where alley approaches and their curb returns and drainage structures are to be constructed. 1 h. Sidewalk - 4 inches Thick. The unit price bid for removal and replacement of 4 -inch thick sidewalk shall include full compensation for constructing I' SP 13 of 19 1 _ this item in conformance to Section 15 of the City's Specifications, as shown ' on the Plans or as designated by the Engineer. i. Class "B" PCC Pipe Encasement and Supports.. Class "B" PCC for pipe ' encasement and supports shall be placed to the dimensions shown on the Plans. The unit price bid for Class "B" PCC for pipe encasement and supports shall include full compensation for excavation and placement of this item, 22. ADJUSTMENT OR REMOVAL AND REPLACEMENT OF WALKS AND LANDINGS i Brick, flagstone, concrete, etc. walks and landings adjacent to curb and gutters, driveways, alley approaches, and sidewalks shall be adjusted or removed and replaced in kind to meet the grade of the newly constructed facilities as shown on the Plans or as directed by the Engineer. ' The unit.price bid for this item shall include full compensation for all labor and materials required to complete the work. ' 23.. REINFORCING AND STRUCTURAL STEEL Reinforcing and structural steel shall conform to the requirements of Section ' 14 of the City's Specifications except that bar reinforcement shall be either intermediate grade or hard grade bars.. Steel shall be placed in accordance ' with the contract drawings. Payment for reinforcing and structural steel shall be included in the price bid for each item of work requiring reinforcing and structural steel and no additional payment will be made. 24. STORM DRAIN a. General. Storm drains shall be constructed in conformance with the ' requirements of Section 17 of the City's Specifications. The Contractor shall provide for continuous flow of storm and nuisance water ' during the progress of the work. The Contractor shall provide temporary berms, channels, sandbags, etc, to assure that storm water does not damage adjacent property. In all locations where a structure is constructed in line with the main storm drain pipe, the pipe connections are to be included in the unit price bid for the structure. All other pipe connections are to be considered in the unit price bid for the pipe and no additional payment will be made. Pipe will be measured by in -place linear feet. SP 14 of 19 �, ..... The cost of filling pipes to be abandoned with sand and the cost of pi-40W with brick and mortar existing or new storm drain pipe, shall be included with other items of work and no additional payment will be made. The unit prices bid for the various storm drain items therefore shall constitute full' compensation for all labor and materials necessary to ' construct the storm drain system, complete, in place, and operable, and shall include all incidental items of work not'separately provided for in the Proposal. b,_ Reinforced Concrete Pipe. Reinforced concrete pipe, furnished and installed, shall conform to Section 17 -02 of the City's Specifications. c.. Reinforced Plastic Mortar Pipe. The reinforced plastic mortar pipe 'and fittings, furnished and installed, shall be composed of a mixture of mineral aggregate and polyester resin reinforced with continuous glass filaments as manufactured by United Technology Center, 6151 West Century Boulevard, Los Angeles, California, or an approved equal. The Contractor shall submit shop drawings and manufacturer's specifications of the pipe units he proposes to furnish. Material test certificates must be submitted for the Engineer's approval prior to commencing construction. Installation shall be in conformance with the manufacturer's recommended methods and procedures and as approved by the Engineer. The manufacturer's technical representative shall be available for any assistance required during installation. The resin shall be a catalyzed isophthalic polyester resin. The aggregate shall be siliceous sand per A. S. T. M. C -33. The fiberglas reinforcement shall be a borosilicate type continuous glass roving with a polyester compatible finish. The gasket seals shall be a continuous ring of neoprene type rubber. The reinforced plastic mortar pipe shall exhibit, without failure, a minimum 1 stiffness factor of 15, 000 lbs /in2 /in for 36 -inch pipe and 24, 000 lbs /in2 /in for 42 -inch pipe at 5 percent deflection when tested per A. S. T. M. D- 2412 -65T. Failure shall not occur prior to a deflection of 15 percent of the pipe diameter. The average inside diameter of the pipe may be lees than the normal by not more than 1/8 -inch, when measured approximately 3 inches from the end of ' a section. The nominal wall thickness for Class 150, 36 -inch pipe shall be 0.46 inch, and have a minimum wall thickness of 0.43 inch. The nominal wall thickness for Class 150, 42 -inch pipe shall be 0. 52 inch, and have a minimum wall thickness of 0.49 inch. Each length of pipe and fittings shall have sufficient strength to withstand, + without leakage or structural damage, the hydrostatic proof pressure of 451 psi. C. Vitrified Clay Pipe Sewer Services. The vitrified clay pipe to be used for sewer services shall conform to the requirements specified for sewer mains. The work consists of connecting existing residential sewer services from a satisfactory point of connection to the new sewer main. Connections to the existing services shall be made with "band- seal" joints or an approved equal. ' The unit price bid for new 4 -inch VCP sewer services shall include the cost of excavating the trench, backfilling and compacting, removing and disposing ' of existing services as necessary, making the connection between the existing service and the new sewer main and all other work required to install the service as specified herein. Measurement for payment will be made from the outside end of the wye -bell to the upper end of the house connection. 25. SEWERS ' a. General, Interruption of sewer flow shall not be permitted until the ' newly constructed sewer is ready to be put into service. ,After diverting the sewer flow into the new sewer, the old 8 -inch vitrified clay pipe (VCP) sewer shall be abandoned by filling with sand and plugging the ends. ' b. Vitrified Clay Pipe Sewer Main. Vitrified clay pipe shall conform to Sections 16 -02 and 16 -06 of the City's Specifications and A. S. T. M. ' Designation C- 200 -64T, except that hotpoured joints will not be permitted. The joints shall be plastic, interlocking type, and shall conform to A. S. T. M. Designation C= 425 -64. ' Branches for residential sewer services shall be furnished and installed to replace existing services. Exact locations shall be determined in the field by the Engineer. Sewer pipe lengths will be measured from centerline of manhole to centerline of manhole. The unit price bid for 8 -inch sewer main shall include the cost of removing and disposing of the existing manhole, sand filling and plugging the existing t 8-inch-VCP sewer main to be abandoned, connecting the new VCP main to the new manholes, furnishing and installing the new wye- branches for sewer laterals, excavating and backfilling the trench and all other work required to construct the sewer main complete in place. C. Vitrified Clay Pipe Sewer Services. The vitrified clay pipe to be used for sewer services shall conform to the requirements specified for sewer mains. The work consists of connecting existing residential sewer services from a satisfactory point of connection to the new sewer main. Connections to the existing services shall be made with "band- seal" joints or an approved equal. ' The unit price bid for new 4 -inch VCP sewer services shall include the cost of excavating the trench, backfilling and compacting, removing and disposing ' of existing services as necessary, making the connection between the existing service and the new sewer main and all other work required to install the service as specified herein. Measurement for payment will be made from the outside end of the wye -bell to the upper end of the house connection. ' SP 1610f.19 d. Sewer Manholes. New sewer manholes shall be constructed at locations shown on the Plans. Manhole frames and covers shall be Alhambra A -1490 or equal, conforming to the requirements for "Grey iron castings" (A. S. T. M. Designation A -48, Class 30). The cover shall be set flush iwith the finished pavement grade. ' The Contractor shall remove and deliver the existing manhole frame and cover to the City of Newport Beach's Corporation Yard, 592 Superior Avenue, ' Newport Beach, California. The unit price bid per sewer manhole shall include the cost of the manhole, including frame and cover, connecting to the sewer mains, and all other work necessary to construct a complete and operable sewer system. 26. WATER MAINS a. General. Water mains and their appurtenances shall be constructed in accordance with Section 19 of the City's Specifications and these Special Provisions. b. Piping Materials. All water mains, unless otherwise specified, shall be asbestos cement water pipe conforming to Section 19 -02 of the City's Specifications. The minimum cover for 12 -inch pipe shall be 36 inches and for 6 -inch pipe shall be 30 inches, except as indicated on the Plans or as directed-by the Engineer. The unit prices bid for the various pipe sizes, as specified, shall include full compensation for all labor and materials necessary for construction of the pipe, connectipg'new dx existing services to'the main, and any other incidental items of work not .separately provided for in the Proposal. The basis of payment of pipe lengths shall be as measured on the horizontal, and as follows: (1) Centerline of coupling to centerline of coupling and /or valve. (2) Centerline of valve to centerline of valve. (3) Centerline of valve to centerline of fire hydrant. C. Valves and Fittings. Cast iron fittings shall be short body, cement lined in conformance with ASA Standard A21. 4 with rubber ring or hub ends, and shall conform to the requirements of ASA Standard A. 21. 10. All rubber ring joints shall conform to the pipe manufacturer's specifications and shall be ' free from rough spots and sharp edges. Flanged fittings shall conform to ASA Standard B16. 1. i S.P 17 of 19 _ Y All valves and fittings shall otherwise conform to the requirements of the City's Specifications, except that no caulked joints will be permitted with asbestos cement pipe. Rubber ring ends shall conform to the pipe manufacturer's specifications. All dead =end outlets shall be equipped with a blind flange, cap, or plug. All 6 -'inch and 8 -inch valves shall be furnished with all internal working parts of bronze including solid bronze discs. All 12 -inch valves shall be furnished with interior working parts of bronze except discs, which shall be cast iron with bronze facing. Valve stems shall be .cast or forged of bronze containing not more than 7 percent zinc nor more than 2 percent aluminum. The unit prices bid for the various valves, valves and tapping sleeves, crosses, tees, and reducers, as itemized in the Proposal, shall be for the items complete, in place, and operable. d. Hot =Tap Connections, Not tap connections shall be made by means of an F -5190 tapping valve and F -5195 tapping sleeve, as manufactured by Iowa Valve Company, or approved equal. The Contractor performing the hot tap operations shall have a minimum of five years' experience in that type of work and shall be approved by the City. The price paid for the tapping sleeve and gate valve will include all work for the item complete in place. e. . New Fire Hydrants. The unit price bid per fire hydrant installed shall include hydrant, connector pipe, and anchor block, all in accordance with Standard Drawing STD- 501 -L. Separate payment will be made for the valve. Fire hydrants shall be located as shown on the Plans or as directed by the Engineer. f. Relocating Existing Fire Hydrants. The unit price bid for relocating existing fire hydrants shall include plugging and removal from the existing main, and installing the hydrants, including additional new connector pipe as required and new anchor block, all in accordance with Standard Drawing STD - 501 -L. Relocated fire hydrants shall be located as shown on the Plans or as directed by the Engineer. Separate payment will be made for new valves, as required. ' g. Thrust Blocks. Thrust blocks shall be constructed in conformance with Section 19 -11 of the City's Specifications and Standard Drawing STD- 502 -L. The cost of installing or removing thrust blocks in the various locations shown ' on the Plans, or as directed by the Engineer, shall be included in the various items of work and no separate payment will be made. ' h. Connecting to Existing Water Mains. Connections to existing mains shall be made either by means of a sleeve type coupling or tapping sleeve, as shown on the plans. Couplings shall be Smith -Blair 433 Transition Cast Coupling, or ' approved equal. Tapping sleeves shall be as previously described. Interfering portions of existing water facilities shall be removed as required. At the locations where the Contractor is instructed to cut, plug, and remove r ' • '° SH 18 of 19 an existing tee, cross, elbow, etc., a concrete thrust block shall be placed behind the. plug. The Contractor, shall inform the Engineer and all affected residences by a written notice, one day in advance, when it will be necessary to shut down ' any portion of the existing system in order to connect new ;rains. ' The .Contractor. shall maintain the existing main and house connections in service until the new main has been pressure - tested, chlorinated, and approved by the Engineer for use. The cost of connecting to existing water mains at the various locations shown on the Plans,, or as directed by the Engineer, shall be included in the various items of work and no separate payment will be made. i. Testing New Mains and Services. Testing shall be performed in accordance to Section 19 -08 of the City's Specifications. Rubber ring joints in asbestos cement pipe need not be exposed during testing; All other types of joints and all service connections shall be left exposed during testing operations. j. Salvaging of Existing Valves, Tees, and Miscellaneous Appurtenances. All existing valves, tees, and miscellaneous appurtenances scheduled to be replaced under this Contract shall be removed by the Contractor and delivered to the City's Corporation Yard. The cost of removing and salvaging water valves, tees, and miscellaneous appurtenances shall be included in the various items of work and no additional payment will be made. 27. REPLACE AND RECONNECT EXISTING WATER SERVICES (INCLUDING NEW SERVICES) The Contractor shall replace and reconnect all water services with new materials between the new water main and all existing water meter service locations, as required. New services shall be installed at locations as directed by the Engineer. The existing 3/4 -inch meters shall be reconnected and the salvable meter boxes re -used. All meter boxes damaged by the Contractor's operations shall be replaced at his expense. The service pipe to the existing meter, ' including angle stop, shall be 1 -inch diameter. The Contractor shall use silver - soldered copper sleeve type connectors to join the new copper tubing to existing copper tubing. Flared fittings shall be used for 1 -inch diameter ' or smaller water services. All work shall be done in accordance with Standard Drawing STD - 503 -L. The unit price bid for replacement and reconnecting existing water services shall include all the work as shown on the Plans and as described herein. 1-1 0 28. SAND PIPE BEDDING Sand pipe bedding materials "A" and 1113" shall conform to the provisions for fine: aggregate,. Section 90 -3.03 of the State Specifications. Sand pipe bedding "A" and "B" for storm drain pipe and 1.2 -inch AC water main shall be placed as shown on the Plans, LACRD Drawing STD 76 -01, and when soft, spongy, unstable, or similar materials are encountered upon which the bedding material or pipe is to be placed, this unsuitable material shall be, removed to a depth ordered by the Engineer and replaced with sand pipe bedding. The unit price bid for sand pipe bedding shall include additional excavation, if required, and placement of this item at locations and to the cross section shown on the Plans. No additional payment will be made for sand pipe bedding required due to overexcavations beyond the limits shown on the plans or directed by the Engineer. 29. LOWERING EXISTING STREET LIGHTING CONDUIT The existing street lighting conduit in the median on Avocado Avenue shall be lowered to accommodate the water main and street construction. All work shall be performed with materials similar to the existing and in accordance with applicable portions of the City's Specifications and State Standard Specifications. The price bid for lowering street lighting conduit shall include all work .required as specified herein, shown on the plans, and directed by the Engineer. 30. ADJUSTING MEDIAN SPRINKLER SYSTEM The existing median sprinkler system shall be adjusted by lowering and removing sprinkler heads to accommodate the water main and street construction. Completion of the work shall produce an even water distribution over the remaining median to be replanted. Restoration of the landscaping will be accomplished by the City. All work shall be performed with materials similar to the existing and in accordance with applicable portions of the City's -Specifications and State Standard Specifications. The price bid for adjusting the median sprinkler system shall include all work required, as specified herein, shown on the Plans, and directed by the Engineer. C- 1123(A) See Contract File for Alley Reconstruction Program Site Map H C7 H H °z H a H O x x t n C N m O Ao 3 y V > o A 2 D T � a y a < r ^ T Z =a m m N N O A Z r' N Eqq o f'1 p-1 3 n W u �0 m' propolial Page No. of rages CUSTOM CRAFT MASONRY Willard Bailey - Carl Mclntee 407 Bolsa Ave. Newport Beach, Calif. Area Code 714 548 -1264 PROPOSAL SUBMITTED TO PHONE DATE City-L–of—Newport Beach . 12/2/69 STREET JOB NAME 3300 Newport Blvd. 432 Avacodo CITY, STATE AND ZIP CODE JOB LOCATION Newport Beach Ca ARCHITECT DATE OF PLANS JOB PHONE We hereby submit specifications and estimates for '•s Remove and replace brick planter $79.00 ate. -397— 20� 111P propDSr hereby to furnish material and labor — complete in accordance with above specifications, for the sum Of dollars ($ ) Payment to be made as follows: All material is guaranteed to be as specified. All work to be completed in a workmanlike 1r r manner according to standard practices. Any alteration or deviation from above specifica Authorized Signature i t tions involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents insurance. Note: This proposal may be or delays beyond our control. Owner to carry fire, tornado and other necessary Our workers are fully covered by Workmen's Compensation Insurance. withdrawn by us if not accepted within - -days. Arreptanre of f roposnl -The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized. Signature to do the work as specified. Payment will be made as outlined above. Date of Acceptance: Signature room 1 ra COPYRIGHT 1050 —NEW EMGEONO eusmc:e SERVICE, INC., rowNScxo, MA35. '*y - I PLACE -ADEQUATE bvXK 'M M&,TC14- SXIST; - - - - -- 1 0 bRICK V-ST. W4LL AD-1.70 51DEWALK, CITY OF NEWPORT BEACH MAWN o "" PURIM WnRJfQ n9DADrUVMT p-M911 L-1 0 ��i� -� 9 ,7 RICEIvIlt . --A PUBLIC �WORK" NVI'd k,,EWPOR T PEACH, CALIF. 6/� All--ld- cl GV a a-�- O-JIL- lj-"r ���� A, iz-L OtX_4tZX-�� 4klO-A-� OLI `_. �.�- - �a�J � — -mac .� �tJ«� ���� �� � � �� � %3 -3 L-�z •r 90 0 432 A VACA 00 ?Z11 J CITY OF NEWPORT BEACH CALIFORNIA 926to city xau 3300 Newport Blvd. (714) 073 -2110 October 14, 1969 Max Hurwitz, Esquire 430 - 32nd Street Newport Beach, California 92660 Dear Max: This is to advise that in reference to the unfinished grading and landscaping of your property at Fernleaf and Second Street, Corona del.Mar, that the City is unable to provide a contractor to do the necessary work. The terms and conditions of our Public Works project for streets, curbs, sidewalks, etc., did not specifically provide for the work that will be necessary to restore your lawn to a safe condition as originally existed. In view of the fact that the contractor is unavailable at this time to return and complete the project per City request, I would suggest that you have the work completed and submit the billing to the City of Newport Beach as a claim. It is my understanding from the project engineer, Mr. Derek White, that the Public Works Department will recommend that the bill be paid;by the City of Newport Beach. very truly yours, TULLY H. SEYMOUR City Attorney K TLW:eg Assistant City Attorney cc: Derek White k/ L PUB L 'C JORKS OEPA ENT Ci ty off Newpprt. ach N0. DATE ACTION ' P. W. DIR TO ASST. P. 9. DIREC. UTILITY SUPT. TRAFFIC ENGINEER ADMIN. AST. CITY ENG. DESIGN ENGINEER -. SUBDIV. ENGR. CO-OP PROJ. ENG. FIFID ENGINEER SECRETARY 1. Handle 5. Review & Comment 2. See P.W.D. 6. Prep. Written Report 3, Read 7. Prepare Reply 4. File 8. Post on Atlas Mao REMARKS: l ' 3 April 15, 1969 Agricultural Insurance Company 505 Shatto Place Los Angeles, California 90005 Attention: Mr. M. J. Brown, Claims Manager SU3JECT: C0,1LINEO CAPITAL PROJECTS, COROUD DEL MAR AREA, 1967 -58 - C -1123 Gentlemen: Reference is made to a claim by George blatson for alleged damages to his property at 2620 and 2628 East Coast Nighray, Corona del Mar, on or about January 10, 1969. This claim Sias forwarded to you under cover letter fron the City Clerk dated Iarcn 25, 1969. This is to inform you that, in our opinion, the damage was a result of the contractor's operations. The condition was aggravated by the physical location of the buildings damaged and their roof drainage system. The City accepts no responsibility for this occurrence. Very truly yours, Derek H. White Design Engineer vdw /em a 6 C Alyi FOR 11)2: QAGF S AG11iN -ST :l CITY OF 'NEWPORT BEAC3 _. _ \i.::.e o. Cilwiiialilr: I -... .l -�!1 1,4 \ • �� acdress of claimant: 6 02ic:: address to which notices are to be sent: Cate, _ ace and other circumstances Gf the occurrence or transaction which / av<; __ to z:.,, claim asserted: ee:'Q T/ L �U(n — -4/ 11-J J 7. ;enerai description of the indebtedness, obligation, injury, damage or loss .._curred• � �Q C� l�_) ` �.�i"�J�`c� }UT"'vV _' s c. \s ;e or names of the City employee or employees causing the injury, dama e �._.ount claimed as o: the data of presentation of the claim, includia:g the amount of any proses c'tive 1;1 "ary, damage or loss, insofar a6 :-t .._ay known at the L'.n:e of presentation of this cllaa�i`mn, togeetaer with. tre amou-zlt clai'med: Of ciai'm Grit or his number: WiZ a-al- —i- ri bus:: e at 2:20 B. Coast highway Corona del 'Nair , California my attorneys are: DEAN AND ROBINSON. All notices to be sent to Dean and Robinson, P,, 0. Box 128, 10951 Stanford Ave. Carden Grove, California. through 11-ha occurance on or about January 10, 1969, :a tws z zItre t impreveikents were had and done by the City of Newport Beach to the rear of the heretofore ,._.,. t:icnad pramises. C -_ work was unsatisfactorily done in that it E c.n-aitted water damage to the building and the contents t�.rs:in. I suffered damages in excess of $600.00 to goods ;.zras and merchandise in said building. si =ut the water damage was caused by improper grading either through imperfect engineering or a failure of .e City Work Crews to properly supervise the construc- tion or that Walker and Bates Construction failed to c: -aply with the specifications. "Hat 1 received total damages of $629.50. I J,Lciare under penalty of perjury that the io- true and correct. 1 - I i CITY OF NEWPORT;BEACH CALIFORNIk Agricultural Inousance Company 805 $hatto Place 1. Los Angeles, California 90005 Attention; M. J. grown, Claims Manager Gentlemen: Enclosed is Summons and Complaint for Damage to. Propfity, Case No. .10983 in Municipal Court of Orange County Harbor Judicial District, George Wateon- Plaintiff, City of Newport Beach, Walker k Bates Construction and Does I through V- Defendants. The original claim was sent to you on March 25, 1969. Very truly your*, Laura Lagios City Clerk dg Encl. cc: City Manager City Attorney Public Works Director Quinlan and Jennings Ins. Co. IN THE v,UNICIPAL COURT OF Case Number CIl"IT,41 ... EAPIDD21 ............................................................................................. 1— AL DISTRICT ;G_—_X_jR L) JUD10 .1 i_ y COUNTY OF ORANGE, STATE OF CALIFORNIA .11 ................................................................................................ OF vs. Va V. pal corporatiou, '.7) 2 V, incluolve !D&fendant(s) THE PEOPLE OF THE STATE OF CALIFORNIA, To tne above named Defendant(s): i. You aze directed to file with the. clerk of this court a WRITTEN PLEADING in response to the complLnt brought aZa:ls-z you in the above entitled action within TEN days after the service on you of this summons, if served within the above named County, or within THIRTY days if served elsewhere. You are riatilica' that unless you so file a written responsive pleading, said plaintiff (s) will take judgment for any .noicy or aasiages demanded in the complaint as arising upon contract, or will apply to the court for any other relief in the corn 'P, aint. Dated ... ........................................... ........... ................... ........... .... .. .......... / ...... .. / ........... .. / Clerk of the above-entitled Court. rk By .;e� ....... ... V.A..Q ......... ........ .............................. Deputy Cie., 7'1c ALV;007 UF AN ATTUI­..IEY ON ANY MATTCR CONNECTED WITH THE COMPI.i4iNT OR 'j. SJ.'%' AT7Z._­,1,ZY SNt LLD Z. WNT�2'.N LIMIT STATED IN' Tk;'S SLmYt0. "A defendant appears in an action when he answers, demurs, files a notice of motion to strike, or gives the plaintiff WtitCC" a0L:CC oi his appearance, or when an attorney gives notice of appearance for him." (Section 1014 Code of Civil Procedure.) Answers, demurrers and all other pleadings, must be typewritten in form pursuant to rule 501, California Rules of Court, ACCOM- Pl:N:FD WITH THE NECESSARY FEE, and filed with the Clerk of this Court, and should be accompanied by proof of service of a copy on piainciii or his attorney. A plcacing is a formal allegation of a claim or defense. (Section 420 Code of Civil Procedure). It must be typewritten or printed on legal size opaque white paper with numbered lines, bound at the top, numbered consecutively at the bottom, (Rule 1, Rules for the Cou:zs.) 'See reverse side for Proof of Service) I rw50-2432 ,9tTMM0N'-# C.C.P. 407, 410, 474, 416.1 etc. J, i'1aintiff FJZICIPAL COURT OF ORANGE COUNTY.HARBOR JUDICIAL DISTRICT COUNTY OF ORANGE, STATE OF CALIFORNIA G=RGE WATSON, Plaintiff, No. /Oq 23 Vs. CITY 02 N0UPORT BEACH, a muni- COMPLAINT FOR DAMAGE cipal corporation, ,GT41UI R & BATES TO PROPERTY v CONSTRUC'i'IONr, and DOES I through Defendants. - ti Plaintiff alleges: 1. At all times mentioned, defendant CITY OF NEWPORT BEACH was, and now is, a municipal corporation, duly organized and exist Lag und;:r the laws of the State of California. 2. a true names and capacities, whether individual, asso- ciate. corporate, or otherwise, of defendants DOES I through V. inclusive, are unknown to plaintiff, who therefore sues said de- fendants by such fictitious names, and plaintiff will ask leave to amend thiL complaint to show their true names and capacities when they have been ascertained. 3. At all times mentioned, defendants WALKER & BATES %,''STRUCTIO'N an-' DOES I through V, inclusive, were the agents, employes of defendant CITY OF NEWPORT BEACH, and all times mentioned were acting within the purpose and scope of suc , .agency anal employment. 1. 4. At all times mentioned, plaintiff was the owner o cert.in improved real property located in the City of Newport Bcac: e - Ci� Y 'ounc-11 lailad an refused to act on said c' --"- W" - -z' - of �`; 5 days af ter 4 ts pr"antztion and said c"aira %,.-L 2- 11 L Of Section 91-1.4 zae urlde h . z te p -la 0' -.-'a sl�ata 02 californiz�., at the expiliza-zlica of tied CC, of 45 days, to W46 , .. � o or about May 15, 1969. - plaintiff prays for judgment against de;zc-.:.�anns, 1. For damages in the sum of $1425.51; 2. r interest on said s,,= at the rate of 7% per annum nlar- --y 10, 1969; until paid; cos' 0 such other and further suit, and for the Co::_.. dzzx's just. Dated. 15, 1969. HIGBIE & HIGBIE Attorneys for Plaintiff By:. /s/ C. A. Higbie C. A. lia-904.e 3. CLAIM AGAINST T'dE CITY OF NEWPORT BEAC% T0: City Council ..._.., City of Newport Beach ATTENTIOV: City Clerk i. Ci.aimaa's Na e: George Watson Claimant's Post Office Address: P. 0. Box 275 Corona del Mar,`California 2. My attorneys are: Higbie & Higbie.' All notices are to be - sent to Higbie & Higbie, 229 Marine Avenue, Balboa Island,,' California, 92662. 3. Occurrence: On or about January 10, 1969, premises si- tuated at 2620 to 2628 East Coast Highway; Corona del Mar, California, received considerable water damage by %. reason of faulty.plans, specifications and woik by the City of Newport Beach in replacing the alley to the rear ' of claimant s premises:' The alley was improperly graded`:.." `:.. either through faulty plans and specifications or .faulty,. ...i .; construction by the City's agents Walker & Bates Cons- truction. IC was necessary to replace rugs and carpets and other' damage to the interior of 2620 East Coast Highway, in;,'::`.. the sum of $993.51 and to R. W. McClellan & Sons Inc,' cne Sim, of $432:00 to 'correct the grade to prevent fur- i' ther damages. i. Total damage :. $1,425.51- :y I declare under enalt f er'ur .that the'fore oin is P Y P P J Y g g true and correct.. ,i. T4dtson, G eorge a mart sm 7. EXArBI1� A •: :. S. I n I J 0 April 15, 1969 Agricultural Insurance Company 505 Shatto Place Los Angeles, California 90005 Attention: Mr. M. J. Brown, Claims Manager SUBJECT: COMBINED CAPITAL PROJECTS, CORONAD DEL MAR AREA, 1967 -68 - C -1123 Gentlemen: Reference is made to a claim by George Watson for alleged damages to his property at 2620 and 2628 East Coast Highway, Corona del Mar. on or about January 10, 1969. This claim was forwarded to you under cover letter from the City Clerk dated tdarch 25, 1969. This is to inform you that, in our opinion, the damage was a result of the contractor's operations. The condition was aggravated by the physical location of the buildings damaged and their roof drainage system. Tiie City accepts no responsibility for this occurrence. Very truly yours, Derek H. White Design Engineer DHW /em May 13, 1969 TO: PARKS, BEACHES, MID RECREATION DEPARTMENT, Attention: Rich Harrison FROM: Public Works Department SUBJECT: COMBINED CAPITAL PROJECTS 1968 -69 CORONA DEL MAR AREA, C -1123 Attached is a copy of a memo from Ton Woodruff re: cut slope at 501 Fernleaf. This is tie one I discussed wit* you in the field a couple of months ago! Is there a possibility that you can take care of it for us? If not can, you give me the name of a landscape company in Corona del Mar to whom I can issue a P.O. for one hour's work? Thanks, ,-6R� Derek H. White Design Engineer UH'W /em Att. PM Walker 9 Bates. 5947 Jasmine Street Riverside, California 92504 Subject: Surety The Western Casualty and Surety Company Bonds No. 355006 Project Corona del Mar Capital Improvements 1968 -69 Contract No.: 1123 Gentlemen:, The City Council on April 28, 1969 accepted the work of subject project and authorized the City Clerk to file a Notice of Completion and to release the bonds 35 days after Notice of Completion has been filed. Notice of Completion was filed with the Orange Countv Recorder on May 2, 1969, in Book No. 8946, Page 162. Please notify your surety company that bonds may be released 35 days after recording date. Very truly Yours, Laura Lagios City Clerk City of Newport Beach ih cc: Public Works Department ✓ CITY OF NEWPORT BEACH CITY ATTORNEY Department s TO: Public Works Director DATE: May 8, 1969 Attn: Derek White FROM: City Attorney SUBJECT: 501 Fernleaf, Corona del Mar Mr. Hurwitz, the owner of the above property, reminded me the other day that the City had not yet come out to repair the change in grade in his lawn,resulting from the installation of new curb work. Could you follow up on this matter and see that it gets completed as soon as possible. Thanks. TLW:ajr Tully H. Seymour City Attorney By '.✓ 7hoWas L. Woodruff Assistant City Attorney nA nA NOTICE OF COMPLETION PUBLIC WORKS To All Laborers and Material Men and to Every Other Person Interested: q6 I b5 I YOU WILL PLEASE TAKE NOTICE that on January 28, 1969 , the Public Works project consisting of mrma del Mar Capit-al Capital 7 YmvamPma 1968 -sq ( CONTRACT N0. 1123 ) on which taaTUox F RA+Aa was the contractor, and The Western asua1ty na d qurejy C'Mg= was the surety, was completed. CTTV OP NF`WPCIRT REACH I, the undersigned, say: I am the Public Works Director of the City of Newport Beach; the foregoing Notice of Completion is true of my own knowledge. I declare under penalty of perjury that the foregoing is true and correct. Executed on 6tri1 3n.1g6q at Newport Beach, California. I, the undersigned, say: I am the City Clerk of the City of Newport Beach; the City Council of said City on accepted the above described work as completed n ordere that a Notice of Completion be filed. I declare under penalty of perjury that the foregoing is true and correct. Executed on Api1 30 F 1969 at Newport Beach, California. - "2fi/)Li. cTh " V Ili /1/oT /Fy. T� i2,�S /OGFniTS Leif r -/Jei, S-S -�� II it ICI %L.. _G'O. , . �q'?!✓!� /.s.,7�>r': t6' 3-67_ ...._._.. /tee utfJ t'ai GAS no. �%�%p•.cFr v -/� s o. c. s;.... zoo I .... ... _ L/1�buccecs/e, 00 e4e..4 Sewer ."llee .. ... szeefa.. �- 7 /7 - -�8 �Pn JG� %per i ... III d -zJ 67 .. _...M1 T/ /Cae <f II II --.._..._._- _....... ... � Ci7y /776in e/ tse aT''••.• '7 —/7— i Via' 7-6 .... /�/b ices - ✓ ✓✓ � i II it ICI %L.. _G'O. , . �q'?!✓!� /.s.,7�>r': t6' 3-67_ ...._._.. /tee utfJ t'ai GAS no. �%�%p•.cFr v -/� s o. c. s;.... zoo I .... ... _ L/1�buccecs/e, 00 e4e..4 Sewer ."llee .. ... szeefa.. �- 7 /7 - -�8 �Pn JG� %per i ... III d -zJ 67 .. _...M1 T/ /Cae <f II II --.._..._._- _....... ... � Ci7y /776in e/ tse aT''••.• '7 —/7— i Walker and Bates 721 N. Main Riverside. California .Attention: Mr. R. W. Bates al April 26, 1969 Subject: Combined Capital Improvement Projects, 1968 -69, Corona del Mar Area Gentlemen: Reference is made to your letter dated February 24, 1969. It is still felt that the adjusted price for the additional asphaltic concrete is some- what high, however due to an implied agreement at the time the material was placed, this price will be paid for that quantity in excess of the original 1500 tons. Change Order #8 has been issued authorizing the extra pavement at the agreed upon unit price. We can find no evidence of additional areas of excavation and reconstruction on Fernleaf Avenue. Regarding the pay quantity for proposal item 12, paragraph 22 of the Special Provisions states that ". . . walks and landings adjacent to curb and gutters, driveways, alley approaches.. . ." shall be replaced as shown or as directed by the Engineer. Paragraph 21.d. mentions new pave - ment that "extends less than two feet onto private property..." and "extends beyond two feet onto private property...". It further states that the unit price bid "shall include full compensation.... to construct the pavement as specified herein." Paragraph 19.a. states "Portland cement concrete sur- faces in alley areas shall be saw cut at the right -of -way line, or as shown on the Plans or as directed by the Engineer." The construction notes on the plans show the typical locations for performing the different items of work. Note 014 is for construction of 61j-inch concrete pavement. This note appears only on those sheets dealing with the alleys. Note #20 requires the removal and replacement of "brick, flagstone or concrete walk and landings to meet new improvement grades." This note appears only on those sheets showing the street reconstruction. The estimated quantities in the proposal indicated 74,000 sq. ft. of 61 -inch P,C.C. alley pavement. The Plans show approximately 70,000 sq. ft. of pavement to be replaced within the alley right -of -way lines. The Plans also show approximately 2500 sq. ft. between the alley right- of-way and the adjacent garages. The planned quantities were increased approximately 2% to arrive at the proposal estimate, allowing for a slight overrun in the as built quantity. Page 2 Subject: Combined Capital Improvements Projects, 1968 -69, Corona del Mar Area The final measured quantity for item #4, A -inch thick alley pavement, was 77,924 sq. ft. Of this, 72.856 sq. ft. was within the alley rights -of -way and the remainder was for replacement of garage approaches. The garage approach replacement work was ordered during the removal and forming stages and the replacement was poured mono- lithically with the alley in most cases. Based on the above, your request for extra compensation must be denied. It is planned to present this matter to the City Council for acceptance of the work at their meeting to be held at 7:30 PM on April 28, 1969. We have recommended to the Council that immediate release of the 10% retention be authorized. A copy of the Public Works Department report to the Council is attached for your reference. Very truly yours, ep. Dunigan, Jr. Assistant Civil Engineer GPD /ldg Att. i ! C - T RAUB, BEIN, FROST & ASSOCIATES P. 0. Box 117 136 Rochester Street Costa Mesa, California Phone: (714) 548 -7723 DATE: April 9. 1969 WORK ORDER NO: 10764 ORDERED BY: City of Newport Beach 3300 Newport Boulevard Newport Beach, California INDIVIDUAL: Derek H. White PHONE NO. 673 -2110 JOB DESCRIPTION: Provide surveying Services to reset two lot corners on Lot 3, Block "0 ", Tract No. 323 as per request from Derek White of the City of Newport Beach. ESTIMATED TIME OF COMPLETION AFTER RECEIPT OF AUTHORIZATION: As soon as possible ESTIMATED FEE: The work will be done on a per diem basis in accordance with the following rates; however, our maximum fee will not exceed $ 125.00 RATES PER HOUR: Registered Engineer $ 90.00 Drafting $ 15.00 Design & Calculations $ 17.00 Field Survey Crew $ 37.00 Raub, Bein, Frost & Associates makes no representation concerning the cost figures made in connection with the maps, plans, specifications or drawings prepared by them other than that all cost figures are estimates only and the Engineer cannot be responsible for fluctuations in cost factors. Upon receipt of a signed copy of this Authorization, we will proceed with the subject work. All blueprints, filing fees or other miscellaneous charges advanced by our firm shall be an additional cost to you over and above the fees set forth herein. All sums that are owing shall be paid within ten (10) days following the initial billing. Any billings that are not paid when due shall thereafter bear interest at the rate of ten percent (1070) per annum until they are paid in full. Client hereby agrees that the balance as stated on the billing from engineer to client is correct, conclusive and binding on the client, unless client within ten (10) days from the date of the making of the billing, notifies engineer, in writing, of the particular item that is alleged to be incorrect. In the event Raub, Bein, Frost & Associates should require the services of an attorney for the collection of any sums due under this Agreement, the undersigned agrees to pay said reasonable attorney's fees together with any costs incurred in said collection. As a condition precedent to the performance of the work described herein, and as a consideration therefore, all parties to the performance of this work agree that in the event any one of them institutes a suit against any other party because of any failure or alleged failure to perform, error, omission or negligence, if such suit is not successfully prosecuted, or if it is dismissed, or if verdict is rendered for any defendant or defendants, the party instituting the suit hereby agrees to pay any and all costs of defense — including attorney's fees, expert witnesses' fees, and any other expenses of defense which may be needful — immediately following dismissal of the case or immediately upon verdict being rendered in behalf of any defendant. If this work is not completed within one year after the above date, we reserve the right to terminate this Work Order and renegotiate our fee. RAUB, BEIN, FROST & ASSOCIATES illiam J. Frost Authorized by: (Signature) Date Nfi +p WORK ORDER N0: 10764 no t a10402:si RAUB, BEIN, FROST & ASSOCIATES P. 0. Box 117 136 Rochester Street Costa Mesa, California Phone: (714) 548 -7723 DATE: . z ril 9, 1959 City of rlewport 3eacr. 3300 „ewoort Boulevard ;ewport each, California INDIVIDUAL: Derek V. iJhite PHONE NO. 673 -2110 JOB DESCRIPTION: Provide surveyinq services to reset t'do lot corners on Lot 3, Block "0 ", Tract 'ie. 323 as per request from Derek !:'kite of the City of iiewport ,each. ESTIMATED TIME OF COMPLETION AFTER RECEIPT OF AUTHORIZATION: As soon as possible ESTIMATED FEE: The work will be done on a per diem basis in accordance with the following rates; however, our maximum fee will not exceed $ 125.00 RATES PER HOUR: Registered Engineer $ 9() 00 Drafting $ Design & Calculations $ 17.00 Field Survey Crew $ 37.00 Raub, Bein, Frost & Associates makes no representation concerning the cost figures made in connection with the maps, plans, specifications or drawings prepared by them other than that all cost figures are estimates only and the Engineer cannot be responsible for fluctuations in cost factors. Upon receipt of a signed copy of this Authorization, we will proceed with the subject work. All blueprints, filing fees or other miscellaneous charges advanced by our firm shall be an additional cost to you over and above the fees set forth herein. All sums that are owing shall be paid within ten (10) days following the initial billing. Any billings that are not paid when due shall thereafter bear interest at the rate of ten percent (107c) per annum until they are paid in full. Client hereby agrees that the balance as stated on the billing from engineer to client is correct, conclusive and binding on the client, unless client within ten (10) days from the date of the making of the billing, notifies engineer, in writing, of the particular item that is alleged to be incorrect. In the event Raub, Bein, Frost & Associates should require the services of an attorney for the collection of any sums due under this Agreement, the undersigned agrees to pay said reasonable attorney's fees together with any costs incurred in said collection. As a condition precedent to the performance of the work described herein, and as a consideration therefore, all parties to the performance of this work agree that in the event any one of them institutes a suit against any other party because of any failure or alleged failure to perform, error, omission or negligence, if such suit is not successfully prosecuted, or if it is dismissed, or if verdict is rendered for any defendant or defendants, the party instituting the suit hereby agrees to pay any and all costs of defense — including attorney's fees, expert witnesses' fees, and any other expenses of defense which may be needful — immediately following dismissal of the case or immediately upon verdict being rendered in behalf of any defendant. If this work is not completed within one year after the above date, we reserve the right to terminate this Work Order and renegotiate our fee. RAUB, BEIN, FROST & ASSOCIATES Authorized by: '1 k'illiam J. Frost, Vice President (Signature) Date April 7, 1969 Raub, Bein, Frost, and Associates 136 Rochester Costa Mesa, California 92628 Gentlemen: Attached are two copies of a survey titled "Lot 3 and the nwly 20' of Lot 4, Block D, Tract 323, Newport Beach, California ° The two corner markers circled in red were removed during recent reconstruction of the alley. Please submit a proposal for replacement of these two corner markers. Very truly yours, �v Derek H. White Design Engineer DHW /em cc: Field Engineer Atts. April 6, 1969 City Engineer Newport Beach Calif. 92625 Dear Sir: Several months ago the alley in the rear of my hose was paved by the city of Newport Beach. Upon completion I discovered the entrance to my garage was several inches higher than it was prior to the concrete work. We are having difficulty removing our cars out of the garage due to scraping. This information was previously brought to the attention of your office. I would like action taken to correct the existing problOem. Yours truly, CBS Y =. ` APR �NEWPOR.T Charles F. Diets 617 Iris Corona del Mar Calif. 92625 CBS Y =. ` APR �NEWPOR.T C- 1123(A) See Contract File for Alley Reconstruction Program Site Plan r LANG'CONCRETE 24191 Ankerton'Drive E1 Toro, Calif. 92630 TO: CITY OF NEWPORT BEACH 3300 W. Newport Boulevard Newport Beach, California STATEMENT INVOICE #0655 April 1, 1969 Referenc : P.O. #10362 Labor and !materials for Walls and Steps $403.00 r &I)e (i S -6y 40.l.A14 � M W Shipped V _ OAddress. Z MrS E. B. Buman 504 fernleaf Corona del Mar. California 92625 March 13, 1969 Subject: Combined Capital Projects 1968 -690 Corona del Mar Area C -1123 Dear Mrs. Sumans The City has recently completed construction of various capital improvements in Corona del Mar. The design of the now storm drain required lowering the easterly side of Fernleaf Avenue to maximize the efficiency of the inlet structure. This has left a grade difference between your walks and the new sidewalk. We have made arrangements with Lang's Concrete to construct steps and walls. where necessary, to correct the height difference. Some of the work will have to be done on your property but at the City's expense. The contractor will discuss the retaining wall material with you prior to construction. Please sign a copy of this letter and return it to me as soon as possible. This will let 3s know that you approve of the project and give us permission to work on your property. If you have any questions. please call me at 673 -2110. Ext. 26. Very truly yours. Derek H. White Design Engineer DHW /em 0 Mrs. C. R. Chapman 502 Fernleaf Corona del Mar, California 92625 March 6, 1969 Subject: Combined Capital Projects 1968 -69, Corona del Mar Area C -1123 Dear Mrs. Chapman: The City has recently completed construction of various capital improvements in Corona del Mar. The design of the new storm drain required lowering the easterly side of Fernleaf Avenue to maximize the efficiency of the inlet structure. This has left a grade difference between your walks and the new sidewalk. We have made arrangements with Lang's Concrete to construct steps and walls, where necessary, to correct the height difference. Some of the work will have to be done on your property but at the City's expense. Please sign a copy of this letter and return it to me as soon as possible. This will let us know that you approve of the project and give us permission to work on your property. If you have any questions, please call me at 673 -2110, Ext. 26. Very truly yours, Derek H. White Design Engineer DHW /em C ZS March 5, 1969 Lang's Concrete Construction 24191 Ankerton Drive E1 Toro, California Attention: Ed Krausman Gentlemen: This will acknowledge receipt and acceptance of your Proposal received February 27, 1969 for the work to be performed at 500, 502, and 504 Fernleaf Avenue, Corona del Mar. You are authorized to do all the work as discussed. A Purchase Order will follow. Before beginning the work. please supply us with Certificates of Insurance. The following insurance requirements must be strictly followed. 1. The City of Newport Beach is to be named as an additional assured on the Public Liability and Property Damage Insurance. 2. The limit of insurance shall be as follows: A. Limit of Liability for injury or accidental death: One person $100,000.00 One accident $300,000.00 B. Limit of liability for property damage: One accident $ 25,000.00 Aggregate liability for loss$50,000.00 Very truly yours. De White Design Engineer DHW /ldg Lang's Concrete Construction 24191 e;: ton Drive W Toro, California City of Neiqport Beach Public dorks Department 3300 W. Yewnort Blvd. o LA Nelqrnort Beach I , California Att: 1-Ir. D. H. uhite Dear Sir: Please accept Yhl's prolDosal for construction of worI.- as discussed with associate envineer D.H. ;•hite on :' "-Ibruary 214-, 19/09. 500 fernleaf drypack u 502 Fernleaf out walk construct construct ader —all and steps - cons- -ruct , steps (5 risers) (north side) landing 3X5 12" retaining wall 504 2ernleaf o•, cut walk - construct steps (L!_ risers) $293.00 Construct stops on south side lot @ 502 Fernleaf 50,00 Construct 16" retainin- wall 50.0, Pren- leaf (;)oared concrete or brick) 110.00 IlesD�ct-l")117 submitted., .Ed Krausli n City of Newport P.O. Hoc 1935 Newport Beach, Dear Sirs: February 17, 1969 Beach California 92663 c -i/z3 Due to your slow responce in repairing a leak in the water line at 512 Dahlia Avenue, caused by workmen who were 'repaving the alley, I have acquired a 125.00 water bill. Ynu were notified on October 1Bth of the leak and a representative from the water department apparently tagged it a week later. However, nn attempt was made to repair the leak until I fixed it myself in December. I feel this is rasp-insible for the increased water bill and will therefore, pay you 513.90 which was the amount of the previius bill that also was higher than normal. I trust that you will agree that this is an equitable settlement. Sincrealy, Robert Cunnan 512 Dahlia Ave Corona Del Alar � 22 ll, Dear Sirs: 4 519 Fernleaf Ave Corona del Mar, Calif 90262 We moved to CdM last July and soon after our alley was torn up to put in new pipe lines. This is fine, but we still can't use our garage vi L & Naa N.ZI 6 iva U,i au,ai.i ,M1 pit' p'GSI our trailer with our boat in or out without getting them stuck in the trench between alley and our hardtop driveway back of our garage. I called several times and talked to the heads at City Hall and they promised to fill in the gullet' the next monday morning. That was during the Xmas holiday. Nothing has been done since then. I am sending a copy of this letter to the Mayor of CdM to let The Mayor know of my predicament. I hope someone sees fit to put my driveway back like they found it. I feel the men who did the contracting for the pipe lines were awfully slow in their clean up work. If nothing happens this week - I will write to the newspaper to see if they have some suggestion. Mrs. S. J. Garrett RECFIVFD F r-1 1 1969 PUBLIC WUMS DLPL J r 0 Nigson Construction Co., Inc. P. 0. Box 2238 Newport Beach, California 92663 Subject: Combined Capital Improvement Project, Corona del Dear Mr. Nigson: February 6, 1969 Mar Area -1123) Reference is made to your letter dated January 17, 1968 regarding water damage at 433 Dahlia Avenue. It is regretted that during construction of the new curb on Dahlia Avenue no provision was made for your 4 -inch drain line. A recent investigation of the site has shown the following: 1. Before any flooding of the buildings would occur, the water would over -top the sidewalk and cirb in front of 437 Dahlia nad flow into the street. This is the approximate location of the drain line outlet from 433, 435, and 437. 2. The damage in the lower level of 433 was apparently caused by seepage coming through the foundation :call, not from ponded or flowing water. 3. Subsequent to the damage, the drain line has beer re- connected, but in addition a concrete slab has been placed in front of 433 to divert any water away from the building. 4. There is a crack approximately 1 -inch wide in the front yard fill approximately five feet behind the sidewalk, indicating the fill nas settled and, therefore, probably was not sufficiently compacted during construction of the houses. Further evidence of the fill settlement is that the front porch at 435 has pulled away from t`.ie house, pulling the plaster stop and plaster with it. 5. The fill soil in the front yards appears to be of a type that would readily accept water, I. e. any rain falling on the 20 -foot front yard area would probably soak in rather than flow on the surface to an area drain. This soaking would result in the settlement and seepage through the wall. Page 2 Combined Capital Improvement Project, Corona del Mar Area (C -1123) February 6, 1969 From the above it appears that the damage which occurred at 433 and 435 Dahlia Avenue was a result of.l. lack of compaction of the front yard fill, and 2. Inadequate sealing of the foundation wall, It is felt that no liability exists on the part of the City or its contractor. If you have any questions regarding this matter, please call me at 673 -2110, Extension 26. ... . .... Very truly yours, G. P. Dunigan, Jr. Associate Civil Engineer GPD /em • E P. O. Box 2238 Newport Beach, Calif. 92663 Mr. Joseph T. Devlin Director of Department of Public Works City of Newport Beach Newport Beach, Calif. 92660 Dear Mr. Devlin: 0 January 17, 1969 A storm drainage project has been underway fos some time in the Dahlia Street area of Corona Del mar. We recently completed three duplexes at 433, 435 and 437 Dahlia St. and subsequently sold all three to Dr. Samuel A. Montgomery and Lois Jean Montgomery who are the present owners of the property. In an effort to provide optimum drainage for the buildings we went to great expense to gutter all roof areas and divert roof water directly from gutters and downspouts into an underground collection system that emerged from the site in front of 437 Dahlia St. in close proximity to the existing storn drain outlet for street water. A smell opening existed in the curb at this point to permit the 4' orangeburg pipe to release the roof water from all three buildings. After our work was complete the existing curb was removed by the crews repaving the streets. Our orangeburg was cut off two or three inches back from the curb to allow a form board to be inserted, a new curb was poured, and no provision was made to reinstall any piping to release the roof water. As a consequence, during the last rain storn, an excessive buildup of water occurred in front of 433 Dahlia Street causing water damage within the building in the amount of $400 or $Soo. We feel that a disregarding of existing drainage provisions by the contractor executing the street work has, in our case, created a legitimate liability, in view of which we would seek to cover our out -of- pocket expense incurred in repairing the damage. RECEIVED JAN 2 o 1969 PUBLIC WORKS DEPL Ve y ssinnccceerrely yours, James D. Higs , Pres. Higson Construction Co., Inc. CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT RECORD OF ORAL INFORMATION FROM: /y'IZ. IG/LHAQO LAJ2EnlCE IN PERSON I FIRM: 438 A TEL. .% %5-1714: _TELCON I VI bEL- MAP-, To` GAIL- Pj C- Ic.a ta T FIRM: P.W. DIRECTOR ASST.P.W. DIR. I NO.. UTILITY SUPT. 11NITIDATE .� CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT RECORD OF ORAL INFORMATION FROM: /y'IZ. IG/LHAQO LAJ2EnlCE IN PERSON I FIRM: 438 A TEL. .% %5-1714: _TELCON I VI bEL- MAP-, To` GAIL- Pj C- Ic.a ta T FIRM: P.W. DIRECTOR ASST.P.W. DIR. UTILITY SUPT. TRAFFIC ENGR. ASST. CITY ENGR. SUBDIV. ENGR. / DESIGN ENGR. CO -OP. PROJ. ENGR. FIELD ENGR. SECRETARY SUBJECT:_ C - 112 3 AL ce � Z7- L Fz-oM FILE: IIZ3 ZuD AycuvES i3c%WEE•J bAWLsA DATES f;- 9-E¢.1�1LEAF' OUTLINE OF INFORMATION RECEIVED &I GIVEN I ✓1 IVlr. l.a rc .1.4:ally Gr.Ile c1 ai- llfFrox:..,-c:: -�I / j.seu.../ 1:45 A. III was very .- .i✓... �{ cr (w"IL" t k3ec�ea> L.as P roP osc -d {o eorr. Ple.i� h.s d ✓.,/e.wc.I aPP ra <. el A+ 11Y I wor 4 P�.?e. -�7 1:.. i,. 3Je -✓I«� iL�e. �r:s }.n<i 1'e .C. w.4 As PL•a li- Co..,re_ }� i r•<. ..t. { -.on Cii,, .. IZub.eo Psi �.. .� ..� �<.. -�.1� Wlz:a� � <. ...1 7 O.ePre.s eci v.e i. il•'.s •....l 1.od) II�we +r'✓ Wwlk.c✓ a.,j 3..i�s }.,,re.•..�r.n �Pai -E:� ✓jai �CLC.P .-Iw C �l.; �e <I e.� ih� e.:.. }; .,y .�. C. C_. P..e. p<- �..a:.. ta✓ {1�.z A 9,Ai . 6.4 4k 1./ so.._e ,i i�.� {_.�,1� �., <{ `1...�..ic. -.41 oti �-.:� c•, c.r N� a.1s. �.a..�la lc: -.Jed iV<. }r i.h� C�.�ir <. c {or l<. <. .1 ,,p ✓..7 �� i«I� L...{ .- ...a�.:i: <.1 0.. 1.:: b- .:1t�:..� � L.:� 1':.I <..«lE ACTION REQUIRED PERSON RESPONSIBLE DATE DUE O NOTES MAKE COPIES FOR ADDRESSEES INDICATED BY "C" IN NO. BLOCK. ONr �e..lceL.o..s I 11 ti `` . tea...i�..s�.i :o.-. " :l -1f.J LW.. r c-v Aid w.41- CA, w:4t -. ..o•,., P c. C P n�. or h� o ld apP�l :< al C- 4iI -fold 1n:.� i i�. -.�i we•nl1 a.�, 4 4 0 6 G //27 January 31, 1969 Ms. Irene Doyle 2653 East Coast Highway Corona del Mar, California 92625 Subject: Combined Capital Projects, Corona del Ma:• Area, 1968 -69, C -1123 Dear Mrs. Doyle: Your letters to the Water Department of December 7, 1968 and January 25, 1969 have been referred to this office. Your letters indicate that the various inconveniences and losses of income suffered by your business were a direct result of the operations of the Contractor installing new water mains at that time. It is standard policy that individuals having grievance against a Contractor first request compensation from the contractor, unless, of course, the claim is covered by insurance. It is advisable to inform the City of the action taken. If compensation is not forthcoming within a reasonable period of time, the City should be notified ao that it may withhold sufficient funds from the final payment to the Contractor. Please direct your request to Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: Mr. R. W. Bates Your v r. truly, De i. ' 1,te Design Engineer DHW /em cc: B. Fisher, Water Billing P. Dunigan, Field Engineer January 30. 1969 TO: P. B. b RECREATION DEPARTMENT, Attention: Rich Harrison FROM: Public Works Department SUBJECT: Combined Capital Projects$ Corona del Mar Area, 1969 -69 This is to confirm our telephone.conversation of some days ago regarding two parkway trees in front of 504 Fernleaf Avenue in Corona del Mar. The grades of cur new curb and sidewalk have been lowered in order to improve the efficiency of the storm drain system. The parkway in the vicinity of 504 Fernleaf will have to be regraded approximately 18" lower. Will you please inspect the trees and determine if they can be replanted at the lower grade. If not please arrange to remove them at your earliest convenience. Also, please arrange to replant two trees of similar species and convenient size. after the parkway has been regraded. If new trees must be purchasedp they may be paid for from Account 02- 3397 -177. Derek H. White Design Engineer DHW /em cc: Field Engineer 0 0 January 20, 1909 :7alker and Bates Construction Company 5947 Jasmine Street Riverside, Ca. Cleanin.- expense resuitin� from sever stoppar_e and overflow, December 26, 1966, in 442 Dahlia Avenue, Corona Del ;;ar, Ca. : 2,W. Ladd 6 hours z N2.50 D. V. Alder -tan o hours 1., 2.50 Cleanin;; runs (Al's Rug Cleaners) Cleaning bedsoreads (.:r. Best Cleaners) Detergent and disinfectant Paid by D. V. Alder-.;;an, Cwner 440 Dahlia Avenue Corona Del 3:ar, Ca. 92025 ' - -1 ................. C ES SENT TO: n LL:: eger y ^� i'u iii: 'A':u a- Direclop � I ILIA U:IiII([ IlilCa'fU, QComcilmauy El ;15.00 15.00 20.00 5.00 4.31 w59.31 -viz 3 0 `L e -//Z3 0 a WALKER & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 5647 JASMINE STREET ENGINEERING k BUILDING RIVERSIDE. CALIFORNIA 62504 February 24, 1969 City of Newport Beach 3300 Newport Beach Blvd. Newport Beach, Calif. RE: Letter Dtd. January 21, 1969 Combined Capital Projects 1968 -69 Corona Del Mar Area Attention: Derek White Gentlemen: FRGNEs1 666 -9690 666 -7406 In our original prices we figured 1'k days to pave the whole job at a cost of $750.00 per day. The first day we quit paving because of the sub grade condition, our bill from Industrial for the z day came to $746.55. We then had additional move ins on two rollers plus outs, sweeping, tact coat, plus the fact we spent 8 days on the paving counting spotting in the spots that were removed and replaced. Then there is also the fact that the price on our asphalt from Industrial was increased as we no longer had a high production job. In addition of these costs I figured that our additional costs were approximately $1,500.00 and adding this to our original laydown prices, less removals I came up with the figure that I quoted you which I feel was quite fair. I would also like to- .again bring up the fact that we have measured a total of 7,081 Sq. Ft. that we enterpate as coming under the section of the specifications relating to walks and landings. I think you are still paying us at $.70 per sq. ft, on this item and I think we should get this matter settled as soon as possible. Very truly yours, WALKER & BATES BY: ;�l RWB /hh R.W. BATES Partner RECEIVED FE92 1969 PUBLIC WORKS DEPT. r • WA L K E R & BATES PUBLIC WORKS , ENGINEERING PROJECTS • COMMERCIAL GENERAL CONTRACTORS 3947 JASMINE STREET ENGINEERING & RDILDING RIVERSIDE, CALIFORNIA 92304 City of Newport Beach 3300 Newport Blvd. Newport Beach, California Attention: Derek White Gentlemen: PNGN[91 888.9890 889.7409 January 21, 1969 P r ' V JAN 2 3 1969 PUBLIC WORKS DEPL RE: Combined Capital Projects 1968 -69 Corona Del Mar Area At our meeting of January 21, 1969 with Mr. Pat Dunnigan, Derek White, Ben Nolen, Pete Ashton with Walker & Bates and myself present we dis- cussed the completion of asphalt paving to be done on Second Avenue in Corona Del Mar. We agreed that prior asphalt paving operations all lines, grades, and compaction were established to plans and specifications. At the time that asphalt paving operations were commenced it became evident that the sub grade design would not support the loads that were required to complete the paving operations. The problem being that soft spots began coming to the surface and causing the asphalt base course to crack. You have instructed us to remove these soft spots and fill them with stable material. The removal of these spots to be on time and material basis and the replacement of asphalt base material to be negotiated. At this time the base course is laid and it appears that there are several areas that will have to be removed and replaced before the final cap is placed. We have agreed that we will use such caution as economically feasible in the paving operations of the finish course and you have agreed to waive the specifications in regards to the asphalt rollers to be used. We will use two 6 to 8 ton rollers instead of the 8 to 10 and 10 to 12 ton roller. Even with the precautions there is still the possibility that if any more soft spots develop during the paving operations you may not get the desired ride you are looking for and also that you may have some craking showing thru to the surface coarse. It is our feeling that the problems we are encountering in the paving operations are due to unsuitable sub soil conditions and not attributable in any way to a lack of sub grade preparation on our part. We feel that the steps you are authorizing us to take in completing the project at this time should in no way WA L K E R & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 3947 JASMINE STREET ENGINEERING t BUILDING RIVERSIDE, CALIFORNIA 92304 January 21, 1968 be construed as meaning that we agree that this is the answer to the problem, as we are proceeding with the work. We are proceeding only because this is the only thing short of removing several feet of native soil and all asphalt and base that has been placed to date, and because it is your choice not to do so. In going over our figures to arrive at.a price for the additional asphalt paving it looks like we added approximately 100 tons to the original figure on Fernleaf which would make a total of 1600 tons. Any tonnage over the 1600 tons will be placed at $12.68 per ton. RWB /hh Very truly yours, WALKER & BATES BY: AO O-4� R.W. BATES Partner PNONEO. 666 -3630 669.7409 CITY OF NE14PORT BEACH PUBLIC WORKS DEPARTMENT 3300 14. Newport Boulevard Date January 20, 1969 TO: E. M. Brady, D. D. S. Box 304 Corona del Mar, Calif. 92625 ATTENTION: SUBJECT: Combined Capital Projects. Corona del Maer area - 1968 -69, C -1123 We are Transmitting the following: No. Copies Description Remarks: Copies to: Original and one Lot Survey by J. S. Raub 12 -8 -51 Lot 4 Block 0, Tract 323, N. B. The lot corners will be reset by the City or Raub, Bein, Frost & Associates DHW /em Derek H. White Design Engineer ----�- -°~v- w°-x�--�. --�~---'-' _ ----_ -_---^_ o,nlcv^omxEn296 F` ^,,zm DENIISTRY 1108 TRANSAMFRI�A ' ao/mmo a�,.ncnCc v� � soo ,x OLIVE STREET Em,Cmu /t LOS ANGELES --'---- ---_----_-�---__ - '_ - -_ -- ------_--- �-- --------'------�-� ' -� ' -� ---- - --�----�---' --------1 ----_-'--------_' _--'--_'----_- �------_------'�L----'--�-'�������r���v��--�Q - '��-��_---�'-'--_----_--'-�-'-------'--__� " v � � �' CITY OF NEWPORT BEACH CALIFORNIA 91660 City }call 3.400 Newport Blvd. (714) 073-2110 January 20, 1969 Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: Mr. B. C. Walker Subject: Combined Capital Projects 1968 -69, Corona del Mar Area C -1123 Gentlemen: This is in response to our telephone conversation last Wednesday and your letter dated January 15, 1969, regarding the Second Avenue construction portion of the project. It is my understanding that the majority of the subject sub -grade failures have occurred as a result of the nature of the native soils and the prevailing inclement weather. It appears that the high intensity wheel loads of the asphalt concrete delivery trucks pumped the underlying moisture to the surface, this creating the failures. We have authorized excavation and removal of the bad material in specific areas. This work will be paid for on a time and materials basis. The base coarse has been "blade laid" and seems to be satisfactory. The finish coarse will be laid with a "parabolic" rather than "straight" crown. This will probably require more asphaltic concrete than estimated. I understand that a tentative agreement has been reached with you to the effect that the estimated 1500 tons of A. C. will be paid,for at the contract price of $20.50 per ton. Additional A. C, required for paving will be paid for at approximately one -half the contract price per ton. Please let me know the unit price that you propose. Very truly yours, Derek H. White Design Engineer cc: Field Engineer 1 11 rIZ 3 WA L K E R & BATES PUBLIC WORKS • ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 5947 JASMINE STREET ENGINEERING k BUILDING RIVERSIDE, CALIFORNIA 82304 PxoNes, 686 -9690 689.7409 January 15, 1969 City of Newport Beach 3300 Newport Blvd. City Hall Newport Beach, California RE: Combined Capital Projects 1968- 69,Corona Del. Mar Area Attention: Mr. Derek White Gentlemen: It is apparent that certain areas of the paved road section on the above mentioned job are failing due to poor sub -soil con- ditions. In so far as the preparation of sub - grade, laying of base material and the paving are being done by Walker & Bates in accordance with the specifications and detailed cross sections we cannot be res- ponsible for the failure of the paved road unless remedial work in manner is done on the sub - grade. Please let us haar from you regarding this matter at your earliest opportunity. BCW /hh RECFIVE0 JAN 171969 PUBLIC WOKK6 ULPT6 Very truly yours, BY: / i/ t B.C. WALKElt Partner 4 F: 1123 Fro, : Ga; l P cicar-v A .s: spa l,4 C:v: l JAN- 15, liloct Sw6j.• Corer a be.l Nlar Zr preJE e. +s — ALLEN' /Z A+ approx: aAe 4:o0 P.,.,-,. o.-. ?ueSaAy , i,,.,, ., 7. 14, 19 ('9 Ch +e1��4,o,.e Lall was rece.; YOd 61 Ed Mc b.,w ld �.r °„� 1L,e- rr „ P7 Op' t-ar,w IZac3." dross s op o,} 2l°ZO C Coas4 (7¢L� 473 -ti29S Co ro., .t Del IV�ar. /1 Iha ledy ProPr:¢ }or L a.-,w IZa e, 7 re eor +e-d +1 -,a4r ThL co. Pla T was trw s {Lr ra� Yo rvG ��¢ preS Cr Ge oT a+ a PPr° olo,�y w:�1 . -,.mac. ovzr +e Coro. -.c cie-I loob a4 4kh Pr.1. �J11 rr'.YC.I we ., -,¢.+ La.,n IZa�+ o ^J "-- ' "o " sns S,T Mq t.Or� UpO.. G ) �+ -FbG lows\, roo. w�.11 a4 ZsLaf /O:00 :g c 1c—+ CA bolo..✓ }ham c, d +4 se�F spa+ .,d 44'c b,.ld;, -,� (1 1 ,5 GIDe� -1' 'tiCh CS a60Y�- T4,a. 5tor.. -. wt�cr was al'° f (r^ , }lo°r arLa Sow k:..q 1„aJ � loved oYCY' a bu...+ 1 1 c . hen cia a[L �ad PP t rP + ; a y yes 1+ t 1 orders °r T ` 1 \-,�J wlso rece:�a -c1 so..,s s�e.e, waiLr ';'Y.QML SY OrC. �h� carPc� ;� c spo+ o�d sealco -d- . i"l,:a wqs e.c 1s 1e s:a`... o10.. +h�1 Sicr1c �. 1 Y I-.fi GI \CY v,A -� $Yer° =- QO, OC G.NT �4 A bly it ••h o1L' i,., iL,L wall d Y,e4 o6v :o,., sl.i ap Pc-aY- l.. + kc. Cs �a lv \:s\ -, a-� er Cor•e¢.:v�d Ibe.. �ollo,Y :r.� cic. ¢_;•�- (.� :.s Pr °.:ded }o b,LIP cl Gr: iy +�, L. 5,+6 cc �,wt .,,4 desc -r :p t:o' t. z a. 1,4,v2eo►i Sre�P Ata/c- Aia eY ST,,_ _ T.. Be FIi.L-eD ZN W.fe /•l.0 - 9 l D'E'A _ 49F P. 7VEW 1PAVEMEk)-r "lv 9ivr� @E roe4 Jlam,:. -s a..d •�ro..1... i -i-.�. cx psi ;..q Ac ;,4. 4 ,. N,l':Il�d �.rn:. -.: ..y p�JuY i'. ��.0 go...Crwl ♦14..J �.rC0.� :or alo1r�� ii cl t1 i�C Y�G�y P.C.C. n11�7, Pave,- .�o_...^i- �•1�`° ) 1 C.O.w�� Co.•. Cf IY4 p I.V ? ! J o..ior Gh L�.+r a.-.d as y d+- aSl`ai. "� Pre.. ss ^ 1 1p -11n .r`0.lnc,it \r1 C.�_InG.�y.�y Oi Sim. -r Wu CY 4v-, . Wc. TI.-r �h Cv� jA CI � Co.., hG.re Pcrc01< }�� �•I- .ro... s�. +ire w.�4 spot 4 4. e.. eo..er¢.�� Io...:I A qq Vrali aF 4.k1 shore A�a: lei e s�rerJ +kA4 }b:s *s Pe,- eG . y ded �C;cr. 0 1 AS w re..r...1{ a'« O..r 6r. Vt O�CCr�/+c ': O r� . WC ae:e o Ga 4 6 1S n YGg4ld: Cj F� C: l y Or (6rge�srf I:�b:l: 3y +L:e caYC. We d:d Ee JJI 1 L; n �4e ih� F we is id 1 c3JVer�7 e�Csr} io 1�SYe L 11 ♦l a slr:4 "4x4 i, -the. hew P.C.C. .ni:al. A. C- as roo., as �atr:b�C. • 0 // Z 3 C -ritq� �LG �- y 12, t I Mrs. Samuel Brusca 3944 Ramona Drive Riverside, California 92506 January 14, 1969 Subject: Combined Capital Projects, Corona del Mar Area. 1968 -69, C -1082 Dear Mrs. Brusca: Reference is made to your letter dated January 40 1969, regarding completion of the project adjacent to your property at 511 Acacia Avenue. Corona del Mar. We regret the inconvenience that the delays in completion of the work have caused you. Weather and oil refinery strikes permitting, the asphalt concrete paving will be laid on Second Avenue in the next few days. Thereafter the remaining asphalt patching will be completed within the alleys. The work is being done by a private contractor from Riverside. The delays have been caused primarily by the contractor's inefficiency and the City's insistence upon quality materials and workmanship. We sincerely hope that your property will be restored to full use within the next ten days. Very truly yours, Z- Derek H. White Design Engineer DHW /ldg Harbor Investment Company REALTORS 3841 EAST COAST HIGHWAY, CORONA DEL MAR, CALIFORNIA 92625 TELEPHONE 714- 673 -4400 January 13, 1969 Mr. Ed Hirth City Hall 3300 Newport Newport Beach, Dear Ed: California I would be the last one to blame a worthy City Councilman for what has happened on Second Avenue. Certainly it would have tested the patience of a saint. As you may know, we have a traffic gate that permitted us to collect 25p a head for all customers of Security- Pacific National Bank. During the last 60 to 90 days, we have had no way of knowing when our parking would be available and, as a consequence, we left our traffic gate open. I would not be able to estimate the loss of revenue. I can only say that in the past we have been receiving an average of $500.00 per month. In the meantime, the parking lot has virtually has left the surface in a always taken pride in our our landscaping of shrubs look at it, we are sick. sand and dirt tracked into our eliminated our parking lines and deplorable condition. We have parking area as is evidenced by flowers and lawn and now, when we Is there any way we can get the contractor, or the City, to clean up the mess, either by a masterful cleaning job or possibly re- coating the area and re- printing the parking lines? We will appreciate any information you can give us. Yours truly, HARBOR INVESTMENT COMPANY H. R. Ring HRR/bh w 1-1 �- I -7- 0 C - //Z-3 January 13, 1969 Mr. F. A. C. Drew II 426 Armsley Square Ontario, California 91762 Subject: Combined Capital Improvement Projects, Corona del Mar Area. 1968 -69 - C -1082 Dear Mr. Drew: Reference is made to your letter of December 9, 1968 concerning the status of the subject project. We regret the lnconvenlenees you have .faced on your occasional visits to your home at 503 Dahlia Avenue. As you may know from our letter to all Property Owners and Residents. dated July 31, 1968. the project is somewhat complex including construction of a storm drain system, a sewer main. 2000 feet of 12 inch water mains, 3500 feet of six inch water mains. 6000 feet of concrete alleys, as well as complete reconstruction of over 2000 feet of Second Avenue. Unfortunately, delays in construction of the underground portions of the pro- ject have lengthened the time that the street surfaces have been disturbed. This condition has been worsened by the sporadic rainfalls, seasonal vacations, and more recently, the Oil Refinery strike. Additional delays have resulted from our insistence upon quality construction for both subsurface and surface improvements, The project is now approximately 95% complete. Perhaps now you will care to review these items of concern to you. Please let us know if there are any items that you feel we should correct. In designing the various portions of this project, we were attempting to rec- tify system deficiencies that had been brought to our attention over the years, by many property owners. It is not the City's policy to intentionally devalue itself. The amount of "convenient curb -side on- street parking" will be the same as before the project began. page 2 N. Combined Capital Improvement Projects, Corona del Mar Area, 1968 -69 - C -1082 January 13. 1969 A copy of the July 31, 1968 letter is attached. It contains an explanation of -.. the cost and funding of the project. The cost is the result of open bidding and acceptance of the lowest bid. If the expense seems exorbita4't it can only be attributed to the present cost of materials and workmanship. If I can be of further assistance please call at 714 -672 -2110, Ext. 26. Very truly yours, Derek H. White Design Engineer DHW /em Att: ----------- PFrFIVFO JAN 1969 PUBLIC G- 4c, all- F. A. C. DREW II 0 426 ARMSLEY SQUARE 502 DAHLIA • YUKON 48120 ORIOLE 3 -2179 • ONTARIO, CALIFORNIA CORONA DEL MAR December 9, 1O'e r, F I V F'D TC 1vfi081 IT AMY CONCLR;;: Ctty of 1ewport Beach DEC 121968 Newport Leach, Caltfornta Attentton: Ctty Manager PUBLIC NhOri DJ L Jentlemen: Before we can even constder how we feel as to one way streets to Corona Del War, we would apprectate and expect a complete explanatton as to what is gotng on at Second and Dahlta Streets. We use our home at 502 Dahlia on week -ends only to the win- ter months. We knew there were gotng to be tnconventences for awhtle ..... not being able to use the garage .... a prtvy parked to front, etc. The real "shocker" was this past week -end! Some of the brteks and paving that we had provtded to the parkway, at our own expense were rtpped out and broken. Also, the two trees we planted to the parkway several years ago appear to be tmpertled. Thts, coupled with the apparent probable loss of constderable, conventent curb -stde on- street park- ing to the area is a jolt. ,e know that "Chtldren and Fools should never see half - ftntshed work" but at thts potnt, the whole project looks ""i pretty dtsmal. We would very much, ltke to know what you have to mtnd and also tf what you are doing is really worth what must be an exorbttant expenditure of funds, as well as the destructton and posstble devaluatton of our property and the netghbor- hood. Thts letter is to part to regtster a protest agatnst thts project. Very t ru,pl�yy yours, F! A. -C.' Drew IT 426 Armsley Square Gntarto, Caltfornta 01762 RECFIVE1) DEC 121968 'PUBLIC WOE ' DrDT Fac, m : 0 bEcEtAeclz 'y' 1'16,F' j?, C- 1123 cA . #073-9360' Z z -Z. p C.0 01C.0 c - //Z 7 �o "�ZL za RECFIVEp cc 1968 PUBLIC WOnh� bLPT. November 27, 1968 70: FIELD ENGINEER FROM: Design Engineer SUBJECT: Combined Capital Projects 1968 -69, Corona del Mar Area, C -1123 Attached are six prints of Sheet 17 showing Vie design grades for the new curb and gutter to be constructed along the Westerly side of Fernleaf Avenue to 2nd Avenue Northerly to the Catch Basin. Please transmit copies to the Contractor. Derek H. White Design Engineer DHW /eem I 1r I ----; --� - - --- Uvorside, California Dear. .0tua: PC I a Ak4tizag, you at the instruction of Vr* White of the amity of n Fovt)-..oer 141 1968:1 was praceedia."g down the alley between Larksp4r and Farguerite and my car ,-became, imbedded in looseljz2' packed. gravel at the exit us the alley and before I could drive out or. 6acond Avenue. There were no weAml ng #via of any land posted. ortunat.ely no one was injured but the enclosed bill frog' Glyde Durc,er shows that Ly;ear became so deeply imbed&W- in the that it took supports and a Low truck to get It oLt. would appreciate having your check for this amount. I am enclosin,L., he names of two witnesses who will support that this intersection was not marked as being hamaridous to traffic*. 'iiiey are Kr. Simpson of 521 Poppy, Corona d Marl, phone num 'iW 673-6094 and :'Xs. Lillian Connor of 427' r9u ZIa *rites. Uorona.tQ1 '.ter pone number 673-6122. 0 L rS Very truly, /7r NO O 8 "r-ne D. 919 -Dayside Lrive,, PUBLIC WORKS- bICPT ieach, Cali ornia 0 CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT RECORD OF ORAL INFORMATION FROM' D /GK IN PERSON 9 FIRM'�iJgc.c c�z�/3OTt3TELa TELCON C —I To' . G o r-.. D . FORM' C � A--, - (�s . TEL. SUBJECTZ C�//w OUTLINE OF INFORMATION RECEIVED I�GOVEN I —I Ll NO.i rINITo DATE �ASST.P P,We DIRECTOR W. D!R. UTILITY SUPT. TRAFFIC ENGR, ASST, CITY ENGR, SJBDIV, ENGR> DESIGN ENGR, CO-OP, PROD. ENGRe FIELD ENGR, SECRETARY F iLE' C —// Z 3 DATE' //— ' -gLX Z: � � �. c.�� e - L -,� J" /i - /ate ;;� ACTION REQUIRED PERSON RESPONSIBLE NOTE% MAKE COPIES FOR ADDRESSEES INDICATED BY "C" IN No. BLOCK. DATE DUE BRYSON HICKMAN & ASSOCIATES Bartholomew Insurance, Inc. nSO ra nce - Bonds - Investments 23330oazt Highway - P. O. Box 8, Corona del Mar, C 2625 / 675 -5444 675 -3793 545 -3165 SIGNED DATE OF REPLY INSTRUCTIONS TO SENDER: R I a N L KEEP YELLOW COPY. 2. SEND AND COPIES WITH CARBON INTACT. 1 WRITE R[iLY, 10=Fl OVY i0 SENDER. November 13. 1968 Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: fir. R. Bates Subject. Combined Capital Projects 1968 -69. Corona del Mar Area C (l2 3 Gentlemen. Reference is made to your letter of October 28, 1968 requesting an extension of time for the subject project. Time extensions may be granted only by the City Council. Section 8 -06 of the Standard Specifications provides that delays caused by acts of the City, such as increasing the limits of the work; or by unusually severe weather will not result in liquidated damages being assessed against the Contractor. Upon completion of the work, your request for an extension of time, if required, will be acted upon by the City Council. I was pleased to hear from you yesterday however, that you now feel that you will be able to complete the project within the original time allowed, weather permitting. We have previously informed you of our concern that the project was pro - grassing very slowly. I hope that you will make every effort to abide by the schedule that you outlined with our inspector in the field on Friday, Novem- ber 8, 1968, and restated to me by telephone yesterday. It is of utmost importance, as discussed at our pre - construction meeting and on various occasions since, and as outlined in your written approved schedule. that alley construction be completed without delay. Allays 22b, 22c, and 23a, for example, have now been out of public service since September 4, 1968, approximately 10 weeks. We must, therefor, insist that, once reconstruction of Second Avenue begins, you complete the work with dispatcu. Very truly yours, Derek H. White Design Engineer DHW /ld CC: Field Engineer CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT 3300 W. Newport Boulevard TO: Walker and Bates 5947 Jasmine Street Riverside, California 92504 ATTENTION: Mr. R. W. Bates ,i SUBJECT: Combined Capital Projects 1968 -69 Corona del Mar A a C -1123 i We are Transmitting the following: No. Copies Description 3 Sheet 8 of 25 Revisions to Alley 23 -A grades Remarks: Payment for this additional work can be made on an equitable basis derived by you and our Field Engineer Copies to: CC: Field Engineer - 2 By: Der White Design Engineer 1 Y J. David Nennigan ... Attorney at taw. Law offices` Suite 2170 Lew Building post office.Box.:1229 aV Riverside, California 92501 Re: klley'.replac ®meat project in Corona Dal Mar . Deaf Mr. Hennigan: er of October 17 Thank you for your lett, 196.8: In with Mr. Ben Nolan, our City reviewing the project Engineer, he has advised me that the City�s field.. inspector has been directed to give the contractor written instructions with respect to work done.ih private driveway areas. We would be glad to sit down with you and your client to discuss any problems which have arisen: during the course of the project. It is suggested that we keep the number of persons in attendance.at such a meeting to a min imum. The dates of Tuesday or Wednesday, November 5th or 6th, would be convenient for us to attend such a meeting: If you will call me at 673 - 2110, Extension 35 we will attempt to work out a:wtually cortvenient-t1me..to discuss the project with you._._..:. J. David Nennigan ... Attorney at taw. Law offices` Suite 2170 Lew Building post office.Box.:1229 aV Riverside, California 92501 Re: klley'.replac ®meat project in Corona Dal Mar . Deaf Mr. Hennigan: er of October 17 Thank you for your lett, 196.8: In with Mr. Ben Nolan, our City reviewing the project Engineer, he has advised me that the City�s field.. inspector has been directed to give the contractor written instructions with respect to work done.ih private driveway areas. We would be glad to sit down with you and your client to discuss any problems which have arisen: during the course of the project. It is suggested that we keep the number of persons in attendance.at such a meeting to a min imum. The dates of Tuesday or Wednesday, November 5th or 6th, would be convenient for us to attend such a meeting: If you will call me at 673 - 2110, Extension 35 we will attempt to work out a:wtually cortvenient-t1me..to discuss the project with you._._..:. CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT RECORD OF ORAL INFORMATION FROM. INIT. IN PFRSON :-77- FIRM. TEL. TELCON I I 0 NO. INIT. i DATE P.W. DIRECTOR J �ASST.P.W. DIR. Gr7TC, �" a2 rC./O /✓C7Te.lJ . Cam/ �s .4l >2CLZ7 UTILITY SUPT. TRAFFIC ENGR. ASST. CITY ENGR. SIJBD IV. ENGR. _ DESIGN ENGR. / CO-OP. PROD. ENGR. FIELD ENGR. /u 0 SECRETARY TO< d/ /CC IJ/ITLrS �P02TCJ t>�J FORM: rt/,oc` �o >r TEL. SUBJECT. ®O��z cis of �a2nc� O/�ici�Y of FSLE. ` 2 9 FeveonAA+ I/0./%YC+ZSJ DATE. /u-2W '6P� OUTLINE OF INFORMATION RECEIVED I71 GIVEN I. ([/r ��- •� --�-- ��,.�d 7� //s GY�TL- ��'/1C' -C.0 G'7� TI.B SiT"� ?o S�� /F d eDerZs o F /u /Z f- / >4o i3cz w c o e.eim o �T. Tic h�o c4cexJ Z) c!c t�ioT�s �oPiSO., •asct� /J OTCS cc by CcCnti -ter° iO.CiO rOGG E Y rO� ®�D,d C H CS ffd4 -C� T �CZ'x> T�'k -G'.t� G.d2 Cr U F , f'c h'/✓O ,C+O .Oti sav�� Q�iT �sscr2 � � r Ti�%o/- ff� UiDZico C,lGL �i'�fiG L Fd2 Gr�L7%�.Q � /LrLP rOiC /.G T�i� E-" C�✓/L � !J F ,ar3tlzi� .O S 5��..c/ - ,p S �o � Sr B L �. I TOG U Q.OT�3 77r /•ST iC�✓ciC3TS /�i®ON' TO J ,�.�°GC.m ErX TS' A.tiO� Gr7TC, �" a2 rC./O /✓C7Te.lJ . Cam/ �s .4l >2CLZ7 �rej,�7- rr/jS' /cot �7ti.O.CJ CuAS' tiOT ,AGL Ti1.OT Cer7 4,Zi Aoe- .O[3r2t9! Btrr 7iYG'r O��s c tirt<- GwT .v .c reZcl m ou Gc.at� t o �ea�soeG y ACTION REQUIRED PERSON RESPONSIBLE DATE DUE \ l�✓Er%1� 1 NOTE: MAKE COPIES FOR ADDRESSEES INDICATED BY "C" IN NO. BLOCK. L 0 �- ,CO e,sa,oJ �?- Ctrh,irl C"X7"CD %J/.oT Tfs'.4T.4"e"C.O/JC.G L�,rJGX�T Sfje�G /J G C'T THE O.e�,j-C`zT /3AC,c o.a.. SC/-/4rga Lt- /JATC�r /�7 C"LTis"ciC� //AO 2C'�uGSTGIJ 77�n cr G"3cTC7��5 /O.J .aCI cuP,Ti.vC. TU C07a�PG y 1-U "777' S PGrCS' /.✓ C Ash /st A7,G HT .G CZYJ / T c OTNYL . `e- c- �c�ZSAT�o,J �.eioc2a @ /2.'a-v a� F'2,cx.ocy /,3.os /s_ CtiGUCO L T "BC- /J?c�i/ /! ?a/L�' A1cZP �'C�OGSCr .Yc� tuariCO.c..T "�"C.ou� �TLSo.viOG.LY" 5'006x -'o /7!U/LL'- 'i //s7� a.G." Th'L� T/J' /•u -O.c.+ L�i��i.�LT TD 3L- TT -C72 O e G o ci l z�G� _ OTC S 7frC�v .0s ecD •� 3�se c� AC70"2 oti 4e/t1492-C- 7Xr C- T/3 sraa0/�/Lc'- u�e,C Car,�vc� -may G"e CS S., 7h /s- Lv.OS GidC�C..J , k�0�'"S ae..OS /x so Toc"U 7�1lJ7` �/3'CrLS /1"C70 �C��^srct' CJhiP T�5'TS F-o2 Gum /y�3o @ i.'3efly :5- 1-7- 2 �roo y /�i 4f/c- i,3fZ4uS� .'mac Li�O.c..r F�2'Z tic Coz /moo .. ,os t c-0 Tc. e s ./dv. ,� %avAT �IGXI yr: c.d �2,uAT�"' C.o- c��ch2sO77o"� WET"' �YC%LS <lt�f/o H.aO T✓ST /J•e/L,.,m� q.�o "Pcr� "" �iaa� -,� ,roc aor� .) f'or� r.�� c.v�e- /�,oc,�. 7-o KG✓3 , se,-j i e,/7-Al' cdrr»7 ex T 7,;r17- "Arc- ie ,cam /ra c ocr 77rc - :5- 1-7- 0 CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT RECORD OF ORAL INFORMATION FROM. �• i- IN PERSON P.W. DIRECTOR FIRM. C• __-(3 TEL. TELCON I I 6 NO. tNBT. DATE P.W. DIRECTOR �.� A� SST.P,W. DcR. UTILITY SUPT. �TRAFFiC ENGR. j ASST. CITY ENGR. SUBDIV. ENGR. DESIGN ENGR, I;u OmOP. PR)J. ENGR. F� tE� LD ENGR. bgr i L SECRETARY c, �' To' d,.0 FpRM.GCJAGKCx%�Oi es TEL. SUBJECT. C'G,�qe� -u,O pF- TB F i LE. DATE. OUTLINE OF INFORMATION RECEIVED 1 I GIVEN 144� �T A�%'.•QO'jL / /,'c�O /f. OG GOYCX.S' cc/ p c T 7v /'fe�2 �CiG L /ylc�/ F.eim 77� i-c.. 5 � .OG G c' i �-� C�°•02.flT /oti � U fiiov oce� fii�i 7rs.OT / CG GXl -c.J v� CcNPi .C.DT .2C`� �. /x.i /�1l�+Grt7 /.O TL°� �O.e G`Y% OF Uiii27't iC/dt.. -� /.cJ �.Pc7�2c°TS <.cT7` 7f ✓/S //9ri9� CX.T� , � G v .s/i/�7 / -7/•OT S�/JC G� .B�e011 iC.��Z,cJ AC LAS' Ai'�ieo.t7CryCs f CiCi�T ,4C. <- 7-A' T• /•MtisT Bf_ �'iGe.. G.b /K% .�Y•CiiGyT <�Ri i�z sJ. �.� ,�% H-OS BCZ'� rJi,00c!— •c.c.m C71d7 /s nrnC'3 Oc.2ivG TNC' ACTION REQUIRED PERSON RESPONSIBLE DATE DUE NOTE% MAKE COPSES FOR ADDRESSEES INDICATED BY "C„ IN N0. BLOCK. 0 0 GC.e�L� AT cor,W"Px o of 4f;u,52, T epe2Fo.eC' r �.O.c..TCD .Cio G C%LCTX -/Y iO,G 6U �/7'iE.C� ?S o2 C� G C� S tTS F�sY+� /1%YCYL S" . GOT S/Iil7C- A-c.�Y Gl,.Qi'", .�FTC7L .PO 19Jici/ �7Z +G0 � %YC72 -S Sfrd! /CL.� /F .f/CtCSS.O.e�✓. �i2 U.OTCS CuAS .CisT �1iAiG.OBG� O�C.J T.C3 - S, Tom" /✓T Ti`f /5 T /h7 L'-J ,pc.0 fi'�O.C. T .��Cx -+ SC'�"x -+ C�1RGi02. Vim =, CITY OF NEWPORT BEACH - PUBLIC WORKS DEPARTMENT MEMO TO: 131"T/a_5 FROM: r� DATE �p -� / ��� 'f 7 �d /j�•�l SUBJECT: lF//t/- t /ice env ✓/ sjrr — eVA,riz.•leTa° /C- /s j7/ /N pie�cT/cy /71 i T ; ? /s; J �i_'Grrl G V �/1ye �' T�( /�C'� T/i'/44/' /�•G�. OA,f SFT76 O /�o,zTii�tis cnG �.� ,%/� /-/ i 17•;Nc° i/ ffJ /-V/;y 2 1!f AZ 190YL /A/1 T /Z[re"C/U7 "..2e eCN r/0,1; er 7 GO /Z /3 10r,C7 -1:0 To C11;7li.c/ j�%c FY lv D ""Oe �// /FT ✓ci�i r✓�_ orpr- �Ci />Pt /ilAJC(? W/rH T//.tsE 1,41372UCT 1OA/-S /s ,ZiQi / //�i�0 y S /.uCt l3 �•�� :i2.a c Tc� /t v✓.4 5 7-,5-1;;'A 1 Tt/N T T /1, ✓0/3 a✓��i /t u :/: ✓. -.: J /C // C 0 P IEB T0: G 2�2/ /i✓l(fj,6 ` z _ SIGNED ✓/L ii PUT IT IN WRITING . . . . . WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS c -iiZ3 i Order No. 6904 p Dept Dale /0 In '—Co 1� 19� Name 1� 4) iCJ PW �JGY i� V00 �i m Address �+ fJ City 1 SF*To R 6 kJ% N SC ill luq SALESMAN _ n P IN ♦ ♦ / i_- ' wpm, • i i ' . M- UMV . .�. ri 0 a WALKER & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 8947 JASMINE STREET ENGINEERING i BUILDING RIVERSIDE. CALIFORNIA 92804 October 28, 1968 City of Newport Beach City Hall 3330 Newport Blvd. Newport Beach, Calif. 92660 RE: Combined Capital Projects 1968 -69 Corona Del Mar Area Attention: Derek White PHONE*, 686 -9890 689.7409 On the above mentioned project the existing drive way slabs do not match the new grade of the alleys as shown on the plans, your inspector in the field is ordering us to cut the existing slabs back to match up to the new alley grades. This is a very time consuming, expensive job as the cuts and removal must be done after the concrete forms are set as the grade of the forms does not confirm to the plans either. ,Consequently I am asking at this time for A 20 day extension of time just for the work that is completed to date. Any additional work after this date will have to be considered and additional time requested. I am also requesting at this time an extension of time of 10 days for ,`additional concrete alley paving that was added above the original contract, Evidently the people that handle your soils testing are swamped with work because we are unable to obtain testing as requested, and in several instances have been unable to secure any tests only on certain days that are dictated to us. Consequently this is holding our operation up and causing us considerable expense. We have offered to hire a private testing lab at our own expense and your inspector in the field said that he would not accept their test results. Futhermore the people taking your tests have been unable to take any more than 4 tests per day and as a rule only 3 tests. At this time I am requesting a time extension of 10 days plus costs to this date and if this practice continues in the future we shall have no choice but to cut the job force to coincide with the testing. RECEIVE® RWB /hl T 2 9 1968 W.OM6 D& Very truly yours, WALKER & BATES BY: R.W. BATES Partner I <') I J. DAVID HENNIGAN J. D. BUTTERWICR ZERNE P. HANING III FRITZ L.DUOA RONALD R. HEUMANN BRUCE HOTCHKISS HEHIG,gn, BUTTEkWICK,Hflf nG & DUD41 ATTORNEYS AT LAW Mr. Tully Seymour City Attorney Newport Beach, California Dear Mr. Seymour: SUITE 217 LAW BUILDING 3972 MAIN STREET POST OFFICE BOX 1229 RIVER51Df,C31LIf04n1A 92501 TELEPHONE (714) 606-3092 October 17, 1968 Confirming our rather brief telephone conversation, I have advised my client, Walker and Bates Construction to proceed to follow the directions of your engineer pursuant to Section 22 of SP 13 of 19 in the specifications to remove and replace in kind any concrete driveways or other approaches necessary to meet the grade of the newly constructed facilities. In order to avoid any future trouble, however, I would ask that you advise your engineer to give us instructions in writing as to just how far back we are to go each time. Some of the driveways can be adjusted in an 8" cutback and replacement if the difference in grade is only an inch or two. Others, however, where the difference in grade is substantial should be cut back several feet in order to make a proper and usable approach to the newly constructed alleys. I want to avoid any problem in the future as to the amount which was ordered done by my client as the contractor. In other words I don't want him to cut back two feet in order to make a proper driveway approach and have it claimed later that he was instructed only to cut back one foot in order to save the city money. I ask, therefore, that you have your engineer give us a written memorandum as to which driveways are to be cut back, reconstructed and replaced in kind and to what R Er, FIitrn OCT 2 1968 PUBLIC Wiuttii�� iitr� CC,��f��f�! 21 1969 Mr. Tully Seymour Page 2 October 17, 1968 extent.this is to be done. I think this.would save possible trouble or dispute in the future. I am also somewhat concerned over the possible claim of liability against my client if, pursuant to instructions of the City Engineer he removes and regrades private driveways. It would seem to me that this is a possible problem of the City as well as of the contractor and if at all reasonably possible would suggest that the consent and approval of the property owner also be obtained on each driveway rebuilding. I would think this should be fairly simple to obtain if there is anyone home but, of course, would be more difficult if only a tenant is present or if the property owner is away on vacation. I would suggest, however, that it be done whenever possible to avoid any possible future difficulties. I know I would be very much disappointed if I, as a property owner, returned to find instead of my driveway leading down to a somewhat delapidated asphalt alley a shiny new concrete alley had been replaced but it was 18" lower than my driveway and this 18" was all taken up in an 8` span giving me an unsurmountable obstacle to entering the driveway. It might be that some of the property owners would be willing to pay a part of the cost of rebuilding their driveways in consideration of the slope being made more gentle at their request. We would be happy to meet with you or your engineer at any reasonably convenient time. Very truly yours, HENNIGAN, BUTTERWICK, HANING & DUDA ;/J. David H2nfrigan JDH:at Walker b Bates 5947 •.`asmine Street Riverside,, California 92504 Attention: Mr. R. Bates Subject; Combined Capital Projects 1968 -69. Corona del Mar Area, C -1123 Gentlemen: 0 c -1122 October 14, 1968 I certainly appreciate your letter of October 9, 1968. My primary concern is. of course,, that the people of Newport Beach receive the maximum in materials and workmanship for their tax dollars. Secondly, it is important that we attempt to minimize their inconvenience during execution of the work. Harmonious working relations between us can help realize these ends. If there is any thing I can do, at any time, to maintain these improved relations, please let me know. Very truly yours. Derek H. White Design Engineer I»iW /am CITY OF NEWPORT BEACH - PUBLIC WORKS �1 MEMO To:/i�-��i'�,�3 - ��t /like A5� r� 3 FROM:,3I �ljiSciv- t/ /vQ SUBJECT: �(C /1�%/✓P ®F V/� 3 /rte ove r? s1VAI DEPARTMENT Z 3 DATE le - 7 '--° S /1,1Ti: I.9�Qcj T flU0 /- %Zc /y1 2 �j�v.� �.vT�•rc.To�z is /= CiizTN��e Dikl=t! Tr; O Ty Ag11- 1rrNiN Ti:rViO �/� Gf .4/7T r.tJ T /loW /S LP /iL X-t 7-1 CJ TlJ feolr� Z �O Aar COP IES T0: I GNED PUT IT IN WRITING . . . . . WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS CITY OF NEWPORT BEACH - PUBLIC WORKS DEPARTMENT MEMO ,Y TO:,% %Yii25 - 14141 k#le /� - 5971r3 DATE /110- Z1` -68 FROM:D.c�o/D`i3oN- `�N SUBJECT: (,a yTr's >E TVA /� /�E /y7 /N��r.� o/= Po5,i ll3t L I T'Y C/= /NC/�/���NT� I,C111;/9Th`fs�. �,p/j�,t/) !' ✓rriyir/ T//�' i. "XT Z H/E -E,CS, Aj P,eG7l;c T /1/tC4u Tv r,Vi57 /�Cl COPIE8 T0: �A LdE 411WWY - zoex5:.Pay ✓s ac VTS ,,3ZTN, JIGNED /PUT IT IN WRITING . . . . . WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS CITY OF NEWPORT BEACH - PUBLIC WORKS DEPARTMENT y MEMO TO:,C/, l yf es y/ACKFiK � Owri,;�3 DATE FROM /N - SUBJECT: /C f/17o1/tjL ' or- Z N� V� eoNT/�lz4 a reoe— lws7wac�t 7a %zr'AWof1 11 i% 6;I 2 ,Ps;Ar10 "� Z ~�/t�/E�z \/3 (/yr /c. /// //��L�4 s!/i3 /ZfiDE /�l�o/Zl� ✓fzO .e Ahoy /,/y,��C�x 1�� .� H//U,� ,o��.✓ /�igs�o - /•� � ,1'�s.,�o/ Foe f�, c� � e �� ATig/2. vv. rT Aj d xAYS Ve /.s lvoytpxbrie nJ Z la l/A /•FC/2d14 of- 4.-- A-f G >Fc0 .T IA DS /T e CoP1FES ,rJ To: G SIGNED PUT MAN WRITING . . . 'WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS 11 WALKER & BATES PUBLIC WORKS . ENGINEERING PROJECTS . COMMERCIAL GENERAL CONTRACTORS 6947 JASMINE STREET ENGINEERING A BUMDING RIVERSIDE, CALIFORNIA 92604 PNON621 686.6630 689.7409 October 9, 1968 City of Newport Beach City Hall 3330 Newport Blvd. Newport Beach, Calif. 92660 RE: Combined Capital Projects 1968 -69 Corona Del Mar Area Attention: Derek White In reference to your letter of October 2, 1968 directed to Mr. Walker. On October 1, 1968 we reached a very workable agreement. I am quite please with your attention to this matter and wish to express my appreciation of your decision as I am certain it will be an asset to the progress and quality of the job. Very truly yours, WALKER & BATES BY: RWB /hl 1R.W. BATES Partner RFPIFIVED 0CT 101968 PUBLIC 3310 AIRPORT WAY LONG BEACH, CALIFORNIA 90806 4264355 (L. &) 636 -2386 (L.A.) 828 -6432 (ORANGE CO.) 1514 -D NORTH HARPER ST. SANTA ANA, CALIF. 92703 JEfferson 1.2045 f of .Sou fhr vie L'ciliJn4iti «. iYrr Since 1898 October 3, 1968 City of Newport Beach Public Works Department 3300 Newport Blvd. Newport Beach, California 92660 Attention: Mr. Ed McDonald Projects NEW CONCRETE ALLEYWAYS Dear Sirs 0 INSPECTION & MATERIAL ENGINEERING CHEMICAL & PHYSICAL ANALYSIS RESEARCH & ENVIRONMENTAL TESTING CORROSION RESEARCH & ANALYSIS RECEIVED OCT 41968 PUBLIC WORKS DEPL I wish to thank you for our recent conversations regarding our firms interest in providing testing of materials and inspection services for above project. I am pleased to submit the following Schedule of Fees covering the items in our discussion. If more information is desired or if I can be of further service, please feel free to contact me. Concrete Mix Designs ............ ..............................A each $ 20.00 (Includes analysis of aggregates to derive mixture) Additional Mix Designs based on Original Analysis .............. each 10.00 Preliminary Trial Mixes, Concrete Flexure Beams ................ each 12.50 (Minimum of 8 beams) Concrete Flexurg Beams, 611 x 611, ASTM C78 ...................... each 8.00 Concrete Flexure Beams, stored and not tested .................. each 4.00 Make Test Specimens in the Field ........................... per hour 7.00 (No Charge for pickup or delivery of test specimens to laboratory) Respectfully submitted, TWINING LABORATORIES OF SOUTHERN CALIFORNIA, INC. Chas. B. Locke Manager, Santa Ana Laboratory hlr'a CBL:slb SCIENTIFIC AFFILIATION OF PRINCIPALS AMERICAN ASSOCIATION OF ENGINEERS, AMERICAN CONCRETE INSTITUTE. AMERICAN SOCIETY OF CIVIL ENGINEERS, AMERICAN SOCIETY OF ENGINEERS S ARCHITECTS. AMERICAN SOCIETY OF TESTING & MATERIALS. AMERICAN WELOING SOCIETY. CONSTRUCTION INSPECTORS ASSOCIATION, NATIONAL SOCIETY OF PROFESSIONAL ENGINEERS, STRUCTURAL ENGINEERS ASSOCIATION. "One Test is worth a thousand expert opinions- *121 'Walker & Bates 5947 Jasmine Riverside, Calif. Re: Job In Corona del Mal r Oit.,T of Newport jeach Gentlemen: My h--me address Ist I o V 4 435 r, Feral, 92625 One of your skip I eders, while lo-dIng broken asyhalt pavement from the alley in back of our .ome, ran into and brace a portion of a concrete block wall at the side of the house. it loalt going to be much of a job to fix Ito and I would have done tpF work iT..ys-lf If someone would have simply apologized for the damage. But aow I think you shou'Ld either repair the wall to my satisfaction or reimburse me for my labors to about the e.-,tent of $20 or authorize a block wall con- tractor to do the work. Very truly yours ... .... .... Harry K. Young October 1, 1968 Copy to Derek White City of Ae-eport i3tach X300 We:A iewport Blvd. A W;;Ort Bach, Calif. 92660 RtCFFVF0 . OCT 31968 PUBLIC wohh� Uj:r RIP-_ ...... . r October 2. 1968 Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: Mr. Walker Subject: (C Fr apital Projects 1963 -690 Corona del Mar Area -11 Gentlemen: Enclosed is a copy of each of two letters from Mr. Bates dated September 30, 1968. On the basis of our conversation on October 1. 1968, and the letter to you of the same & te, we feel you may wish to reconsider both the content and mood of Mr. Baties� letters. Please let us know if you wish to revise the letters or if you wish that we answer them as received. Very truly yours, G. P. Dunigan, Jr. Assistant Civil Engineer GPD /ldg Enc. 0 E WA L K E R & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 5947 JASMINE STREET ENGINEERING i BUILDING RIVERSIDE. CALIFORNIA 92504 September 30, 1968 City of Newport Beach 3330 Newport Blvd. Newport Beach, Calif. 92660 RE: Combined Projects 1968 -69 Corona Del Mar Area C -1123 Attention: Mr. Derek White Gentlemen: PNONEM 686 -3630 689 -7409 Your inspector on the above mentioned project has taken it upon himself to decide when we are ready to have compaction tests. We wish to advise you that when we are ready for compaction tests we will request such in writing or by telephone. Your inspector has also taken it upon himself toccall out the water de- partment for repairs without just cause. If there is any problem on our Job we have competent men qualified to make any repairs necessary, and if we find any situation that we are unable to handle we will then request your assistance in writing or by telephone. We will not accept the re- sponsibility for any bills incurred by your inspector. In advance of grading operations in the alleys we had men attempt to locate property line stakes for individual lots. A few were located, but in most instances there appeared to be no stakes. Having made every effort to locate these stakes, and as yet have torn none out we must assume there were none from the beginning on certain lots, therefore we wish to advise you that we accept no responsibility for replacement. Many of the existing water meters were leaking prior to our working, we have noted them on our plans, and due to this condition is one of the reasons the alleys have spongey spots. We will not accept responsibility for the repairs of same. Another condition exists that is going to cause some problems is in some of the alleys there is no paving or concrete or the existing paving or concrete is lower than the new concrete edges and will hold water causing the ground in these areas to become spongey. With heavy traffic the concrete will probably crack, due to these facts we will accept no responsibility for these conditions. RECEIVED OCT 21968 RWB /hl PUBLIC buur�N� UEPTO Very truly yours, WALKER & BATES 1�BY: R.V. BATES Partner 0 L] WALKER & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 5947 JASMINE STREET ENGINEERING k BUILDING RIVERSIDE. CALIFORNIA 92504 City of Newport Beach City Hall 3300 Newport Blvd. Newport Beach, Calif. 92660 Attention: Mr. Derek White Gentlemen: PMONE9t 686 -3630 689 -7409 September 30, 1968 RE: Combined Capital Projects 1968 -69 Corona Del Mar Area C -1123 We are informing you at this time that the alley profiles do not coincide with the existing improvements in the alleys to receive concrete. Because of the inability of your inspector on the above job to make a decision that he will stand behind in writing we have no alternative but to cease all activity on this portion of the work until a solution is reached. Very truly yours, WALKER & BATES BY: � I :? /U P RWB/h1 RICHARD TAT. BATES Partner RFCF�vED 04 �- 1968 r ti u6tj4 0 0 CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT CONTRACT COMPLETION STATUS CONTRACTOR: (�� _ CONTRACT C_iiz3 REPORT DATEE -IS--S R DATE OF AWARD/EXECUTION TIME ALLOWED (CALENDAR DAYS) /� 0 ,/ ORIGINAL COMPLETION DATE . ..�' /�T /�f �. RECOMMENDED EXTENSION" nn CORRECTED COMPLETION DATE L CALENDAR DAYS USED CALENDAF DAYS REMAINING 19,Fw PERCENT TIME USED 7-8 %® PERCENT VALUE COMPLETED Z % 0 +TIME EXTENSIONS MAY BE GRANTED BY CITY COUNCIL ONLY. EXTENSION NOTED WILL BE RECOMMENDED BY PUBLIC WORKS DEPARTMENT. REMARKS: SIGNED BY: C- CITY# NEWPORT BEACH - PUBLIC WORKS ARTMENT MEMO TO:,�22111YAa- A/fzCii.K # /3�rirs DATE FROM: ��r� iS eN SUBJECT: i2 ,5.j-x1f1z 1,47- .fe/i43 /j% /.✓ ,li,��s e G�oNr�gcroe is .PFipria0�0 TNid T .9Ny � i9c c. .S/i N/ /ii�3 Dd /hNL�€'O .8y ,y /1 p�y�'.9Tisl7it/S .. /i/dS T Br !Z!c /lN�•t'�'/7 Tv ?/�F itit/!, ✓iy��/ls Syr /S.<= HLT /Ort/, ,u,�_ q,� /rJD,e�'il.�:..� HoT STIJ�p� oi= ",Ove)K3 *I 13104-17&5 ,C/N/JN /yl/76�D ih// L NOT /fC ;;w0"yirT#-7v ca 14 WNf-eE PDSSii3LC /rJijt//H / ✓ /CHG �(0 /NT3 W/c L 13,C ee1V,5 roelJC TFD . /'/LOmPr COPIES T0: Tif/,r- ABDvn- 'DNOiTio vs IGNED All? T -0110. PUY IT:IN WRITING . . . . . WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS CITY# NEWPORT BEACH - PUBLIC WORKS 6ARTMENT V MEMO TO: -Z). ^"g,es - M41lewo x/5/7 s DATE FROM: SUBJECT: 01y,f1r�yero,� J3 ,�fi,Q�/Jy o•eo, ia. a To cjoN�n�uCT /Z I�CR /! /L//.r/ 7-0 ,� /v� ti/��oE /1,s -�rllourw ox/ R.c,v/us ? t / ,l2rJ<r�,�!//OJZf� �li�c/T,�lCTo2 [U /6G JvoT �Or✓..sT2c /�T` /a7 L`f� alfj,4i tAl,r//1A.1 /',C G/- S7 A,' ro E111-4 _)lA.lr /G ST6 /tin �.�11/AI 1f11e C1:: /LL PUT IT,'IN WRITING . . . . ...WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS CITY# NEWPORT BEACH - PUBLIC WORKS ARTMENT MEMO Q TO: 9,,L ml e-5 - W4te .e T�NTt<J DATE 7 aZ 7 —L 8 FROM: e, SUBJECT: �w?i :,WCL &Lxl oy 04CeArl4t ZN -S7DAe1? f'7TT� / ✓T /znJ /3 �lk'.$eTrri%/ TG' �� -Grf OF 1�/'"/3 .5-747 z*,ic1 �LC l�sl c T.3,r VD ;le- Tf/ o AYvY ,J iic` OT!-,4a2 IrO,+15 oG 1VO.e7G W191CH W116 Ail T/I/ Oti 2i e e e-iLL- w14 e- Ne ff 13,F edAl -f retie 7;�, i% /.✓T /L �� �'orhPAc710, 6�,-hV Cop i Es T0: -�• SIGNED PUT IT: IN WRITING .WRITTEN MESSAGES SAVE TIME AND A4010 ERRORS CITY# NEWPORT BEACH - PUBLIC WORKS WARTMENT I / MEMO TO: 210Y A?_5 - l�%,� %z ,�NT�33 DATE FROM:!/ �/ SUBJECT: 14 tlaTiLN ti Si w���L /V!7 NoD.+J ,UNCO/ #^4eT�1� -57O.e 14' f/.wi u, i11U3 D/ T3 /1B.eF /LL lwell V-5 /I.Zr li77-446" y� � POiHPNaTiO� iGll1ST �� su�ir/irT'�p � �/��,QDiJ.SO l.3y ��� w d ;r`y. O ✓J / �r f� "Al rla) /s AAMM 7J.I eed fV O: 7W d/iB13F4L "0,6i 2 Of- vi���c n'co co�vr'rZAe -TD/Z wN /cH .MW 190 ,w 4? 7we/- r/:/i/,v ,ti!� oiv Y- /7 -GY. &Pv row e7-v/z n/5Iz /* v,e b 3 'l� /w @ ,vcWAv l9PeX) W�fHOC�> /�}/v� z A i l iN � C PIES 0: 47 U44A)1-kAA--J /�-iIAI§T IT.IN WRITING . . . . .WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS WA L K E R & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 6947 JASMINE STREET ENGINEERING k RUILDING RIVERSIDE. CALIFORNIA 98804 PNONEA, 686.3630 689.7409 September 13, 1968 City of Newport Beach City Hall 3300 Newport Blvd. Newport Beach, California 92660 RE: Combined Capital Projects 1968 -69 Corona Del Mar Area C -1123 Attention: Derek H. White Gentlemen: We respectfully request that you add the following Subcontractor to our list of Subcontractors. This Suboncontractor will construct Storn Drains and Catch basins on the above mentioned project. RECFIVtb SEp 1 1968 ?UBUC wOKKS DEPL RWB /hl C & R Concrete 127 Virginia Place Costa Mesa, California Phone: Liberty 8 -4115 Very truly yours, WALKER & BATES BY: a4 R.W. BATE Partner W C —i /Z3 September 3, 1968 Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: Mr. R. W. Bates Subject: Combined Capital Projects 1968 -69, Corona del Mar Area, C -1123 Gentlemen: Reference 1s made to your letter of August 29, 1968 Quoting a price of $135.00 each for installing 1 -inch water services at four locttlons to act as air release valves for the 12 -inch main in Second Avenue. This price is acceptable to us. Please proceed with the work at your earliest convenience. Very truly yours, '-4v— Derek H. White Design Engineer DHW /ldg CC: field Engineer WA L K E R & BATES PUBLIC WORKS . ENGINEERING PROJECTS . COMMERCIAL GENERAL CONTRACTORS 5947 JASMINE STREET ENGINEERING ✓p BU=ING RIVERSIDE, CALIFORNIA 92504 PmoNm 686 -5690 689.7409 August 29, 1968 City of Newport Beach City Hall 3300 Newport Blvd. Newport Beach, California 92660 RE: Combined Capital Projects 1968 -69 Corona Del Mar Area C -1123 Attention: Derek H. White In reference to your letter of August 21, 1968 regarding the installation of 1 inch water services at four locations and in accordance with Standard Drawings STD - 503 -C. Meter boxes to be supplied by the City. Our unit price to install these services is $135.00 each. RWB /hl :?P _ R�c�rv�a SEP 0 31968 'T Very truly yours, WALKER & BATES BY: .� c RJI. 8ATES Partner 'Nt-- August 21. 1968 Mr. S Mrs. Harry D. Smith 18237 Saticoy Drive Reseda, California 91335 Dear Mr. 8 Mrs. Smith Reference is made to your letter of August 19, 1968. Unfortunately the City does not have the manpower available to negotiate with the contractor for work to be done on private property unless it is essential to the project and required for the common good. However, on past projects, the contractors have negotiated with individual owners for work to be done on their property. The contractor, Walker and Bates, has expressed a willingness to do the same. Their address and telephone numbers are listed below. Please contact them directly. If we may be of other assistance, please let us know. Very truly yours, Derek H. White Design Engineer DHW /meh Walker and Bates 5947 Jasmine Street Riverside, Calif. 92504 Tel.- 689 -7409 675 -3082 0 6 RECEIVE? � AUG 2 21968 0 August 21, 1968 Walker E Bates 5947 Jasmine Street Riverside, California 92504 Attn: Mr. R. Bates. Partner Subject: COMBINED CAPITAL PROJECTS 1968 -69. CORONA DEL MAR AREA C -1123 Gentlemen: c -�rz3 Reference is made to our recent discussion regarding the need for air release valves at various locations along the 12 inch water main that you are now installing in 2nd Avenue. It appears from the plans that valves are required at pipe stations 18~35. 9+45. 7 +20. and 4+20. Please install standard 1 inch water services at these four locations in accordance with our Standard Braving STO- 503 -G. The motor boxes will be supplied by the City. The meter box for the service at station 9+45 should be placed at station 9+55; in order to avoid the sidewalk. Please submit a unit price for doing this work. Very truly yours. Derek N. White Design Engineer OHW /meh cc: Field Engineer The Westernasualty and Sur *r Company FIDELITY AND SURETY DEPARTMENT 916 WALNUT STREET BUILDING City z"Ineer KANSAS CITY, MISSOURI 64106 City Nall Newport Beach, California RE: Bond No. 355006 H.O. Dated 7 -30 -68 Name and address of Contractor (Principal) Walker 6 Bates Riverside, Calif. Bond Is In Favor of (Obligee) City of Newpwt Beech, Calif. FPS Amount $ 118.152.50 Perf. 118,152.50 Pay, Description of Contract Combined Capital Improvement Projects, Corona Del Mar Area 1968 -69 Contract 1123-Constr. of Storm Drain, Water Main ��r,,,,e�,pp.lacementii2nd Ave, Constr. & Allay Constr. We have executed, as Surety, tWie�apuone�6oned �o ZganA t e contract described and will, therefore, very much ap- preciate your giving us information regarding the present status of this contract as requested below. You will find enclosed a stamped return envelope for your convenience. Yours very truly, THE WESTERN CASUALTY AND SURETY COMPANY 2. 3. IF CONTRACT IS FULLY COMPLETED PLEASE ADVISE: A. Date of completion B. Total final cost of completed contract $ C. Amount paid to date $ IF CONTRACT IS NOT COMPLETED PLEASE ADVISE: A. Percentage of acceptance Balance due $ Amount paid contractor $ B. Amount withheld as retained percentage on completed work $ C. Change, if any, in amount of contract: Increase $ Decrease $ D. Has work progressed satisfactorily to date? Estimated completion date? HAVE ANY LIENS OR CLAIMS FOR UNPAID LABOR OR MATERIAL BILLS BEEN FILED TO DAT If so, list below, name and address of each claimant and amount of their claim. Dated at —'�a _ %- Signed This day of 9—By: FORM FS 5122 -R3 ATF 3 /= CITY]# NEWPORT BEACH - PUBLIC WORKS D TMENT ff MEMO TO: 6yAGKF!t >Tcs , My�'S i DATE FRONt J�. /J /ice'/.✓— �Fi!/%I.N/ E /�{L /2. �{_: SUBJECfr 7-Ile-- e e,/)Ti/7�A TG' l7liiti4 40C (4 /ll_-;� 7;s'• %U4 h` <'f'Ai.�i L`XF /GGIf/O 'i;» rf/ / f i To 7/= Tir:/+i %f/ y ✓rrN ZFAMO P �N1iz! /ETdr� yJ�LL 4,'-5 Ui /3L4:� TD . < "•-.r /GO'r_" ` /' /eo!f /� / /t. ";Cry /GG , .i�i,/N:i �r�'C;!i iLG i;�%GL •.�� �'G! / / /�G1i r=L7 �� Pik /fJ Al IEs To (1�aiti / /r /,t% /3Fri .cJ irlvrw T/ IBNEO PUT IT IN WRITING . . . . . WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS rLes�.S�._G::�:h.._.:; :._. ..... ... ...... ....... .e... -.'a:. .. ��...F. 6-,. .e.o_•�r. _. ..cC `: .: {ur. n. .. .e... 2�,.iiasa�+"� -'.� CITY 10 NEWPORT BEACH - PUBLIC WORKS OORTMENT MEMO TOI�rG F/Fr/ ' C.l�t' /G' /N/� !/frG / "�e/3 % /(/.t� DATE- FROM: / . SUBJECT: rL'LGGWi �7icr f i > N' j .� /�� /t� B:.'r✓i✓ �y /c:C���.= 'ir.E. ! ��j %eli /,//.� /G /l! � o •✓0 COP IEB TO' ( j../YL- ..,�_'• l.� SIGNED PUT IT IN WRITING WRITTEN MESSAGES SAVE TIME AND AVOID ERRORS 6 41 Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: Mr. Walker October 1, 1968 Subject: appal Projects 1968 -69, Corona del Mar Area C -1123) Gentlemen: This will confirm our conversation this morning regarding the allowable deviation from the planned alley grades. 1. The flow line shall be held as close as possible to the planned grade. 2. The edge elevations may be varied up to 0.15 foot up or down from the planned grade if this adjustment will cause the new concrete to more closely meet the grade of the existing improvements. 3. In no case shall the above adjustments be made where the resulting alley "vee" would be greater than 0.50 foot or less than 0.10 foot. 4. Tile above adjustments will not be made where the plans show removal and replacement of the existing improvements outside of the alley right of way. It is felt that the above will.allow sufficient flexibility to provide the desired finished product. Should greater deviations appear desirable in isolated cases, these can be handled on an individual basis. Very truly yours, �Dunigan, Jr. Assistant Civil Engineer GPD/Idg CC: Jezowski and Markel - Attention Mr. Tabb 0 Paul V. Stuart 2365 E. Coast Highway Corona Del Mar, Calif. 92625 4 C —l/Z ? September 24, 1968 Subject: COMBINED CAPITAL PROJECTS 1968 -69, CORONA DEL MAR AREA C -1123 Dear Mr. Stuart: In reference to your letter of August 28, 1968 regarding the subject project and your proposed development. It appears from your 8% x 11 inch plot showing the outline of the proposed construc- tion, that you intend to requsst vacation of the ruhlic alleys from Goldenrod Avenue to Second av -rue. 'dithin this alley are situated an 8 -inch sewer line and a 6 -inch water line. Gas, electrical, and telephone facilities are probably also located in these rights -of -way. It is virtually impossible to provide additional service stub outs at this time, should they be needed, without detailed plans of your proposed development. The current project calls for reconstruction of Second Avenue after installation of the 12 -inch and 6 -inch water mains which are shown on the attached print of your plot plan, along with the other water and server mains mentioned. de appreciate your concern regarding future disturbance of these new improvements. However with the information currently available to us it appears that we should proceed with the project as conceived. If we may be of further assistance, please call at 673 -2110, Ext. 26. Very truly yours, Derek H. H. White Design Engineer DHW /meh WALKER & BATES GENERAL CONTRACTORS ENGINEERING B BUILDING City of Newport Beach, City Hall 3300 Newport Blvd. Newport Beach, Calif. Calif. 92660 PUBLIC WORKS - Sept. 18, 1968 PROJECTS - COMMERCIAL 5947 JASMINE STREET RIVERSIDE. CALIFORNIA 92504 PNONm 666.9830 689 -7409 Att: Mr. Derek H. White Re: Combined Capital Projects 1968 -69 Design Engineer Corona Del Mar Area C -1123 Gentlemen: We wish to bring the following to your attention. 1. Upon the verbal request of your inspector in the field, we have changed the location of storm drain structure #1 as the plans are in error by approximately 5k ft. in showing location of existing 36" RCP. 2. In moving the storm drain structure X11 the required 5'k ft. an 8" sewer line was encountered resulting in minor damage. At the present time this has incurred a cost to us of $42.00 including labor and materials at cost. If any further repair will be necessary, please advise. At the present time, the line is not leaking and appears to be in as good condition as originally. 3. In alley 23 -A, due to the fact that the existing gas, water and sewer lines were approximately 2 ft. off as shown on the plans, the cleanout at station 8 + 67 was damaged. It is our conclusion that this item should be paid for as an extra. Please advise as to how we should proceed. 4. Where the 6" water line ties on to the existing 6" cast iron pipe at the intersection of Second Avenue and Heliotrope, the existing approach at this location will have to be removed and replaced to make the tie in, as the existing water line is not as shown. Please advise when to proceed and on what basis. Also, as there has been an addition to the original bid of 110 water services, we are at this time requesting an extension of time of 15 days for installation and testing. RWB /n RFCFIVEQ SEP 191968 PUBLIC WORKS DEPL Very truly yours, WALKER & BATES �� IBC/• i� R. W. Bate REALTOR, S,E.C, 904, THE MUTUAL BUILDING 2865 East Coast Highway, Corona Del Mar, California 92625 (714) 675 -4070 August 28, 1968 City of Newport Beach Department of Public Works 3300 Newport Newport Beach, California Gentlemen: I am in receipt of your notification of work in process affecting water and sewer lines and curb and street im- provements on Second Avenue between Dahlia and Heliotrope, and in connection with your improvements to be made in pro- perty which I own that lies between Goldenrod and Heliotrope abutting Second Avenue there are some questions I wish to pose and request your assistance. According to a plat of the subject property which is enclosed together with a Districting Map #16 of Newport Beach, California, I am proposing a major development upon the pro- perty which may be affected by your current plans. In effect, • locations of existing water and sewer facilities in the alley connecting Goldenrod and Second Avenue and the possibility of any public utilities such as gas, electricity or telephone installations and the depths to which they have been installed. My project will probably be eight months in process before we can start any physical construction, however; it would be important to know at this time the feasibility of relocating any existing utilities at the time construction would begin on our project and the provisions which could be made through your department for any connecting T's or sewer chimneys and the possibility of a preliminary installation of underground con- duits or pipes for other public utilities which may be in- stalled at a later date. It would seem to me that if streets, curbs, sewer, water, etc. are to be disturbed prior to the time of commencement of my project it would be wise to provide for these facilities now rather than to effect a street dis- turbance at a later date. I will appreciate your cooperation in the above matters at your earliest convenience. Very truly yours, r Paul V. Stuart PVS:cw Enclosure 10 �a Exist 00 ,4,TC i w W a. 0 (Y' E O H .1 W x THIRD AVE. T SHOWING EXISTING AND PROPOSED CONSTRUCTION RELATION TO LOT LINES Buildings 1) Shell oil. ... ... � ........ ... 11 -1 (2) Stationary Store Propo ed Apartments 90 units I (3) Sncuri i y Rant: Proposed Two Level — (4) il:ic. ;e L'ui.lding Parking Structure L (5) Office Building p , . 0 G - „z3 F August 19, 1968 TO: FIELD ENGINEER FROM: Publf*�Works Department - Design EW neer SUBJECT: COMBINED CAPITAL PROJECTS 1968-W, CORONA DEL MAR AREA Attached is a breakdown of an approximate distribution of the estimated quantities. Items 1 and 35 are the revised estimated quantities and the renegotiated prices. Items 3 and 4 have been increased to reflect additional work i8.alley 15c. GENERAL FUND - STREETS (Non -Gas Tax) Account No. 02 -3397 -177 Item No. Quantity Unit Price Amount 3 5,700 SF 0.50 $ 2,850.00 4 75,800 SF 0.70 53.060.001 G�� /' 5 31 Ea. 225.00 6,975.00) 6 2.500 SF 0.65 1,625.00 7 2,700 SF 0.80 20160.00 8 4,300 LF 2.00 8.600.00 9 500 LF 2.00 1,000.00 10 3.600 SF 0.50 11800.00 12 1,400 SF 2.50 3,500.00 39 LS 500.00 40 LS 250.00 - 44 1,300, Tons 20.50 26,650.00 45 3.300 Tons 3.00 9 900.00 Total $118"870.00 Budgeted $139.000 (Remainder to other projects) GENERAL FUND - DRAINAGE Account No. 02 -3497 -175 Item No. Quantity Unit Price Amount 11 20 CY 30.00 600.00 13 LS 2.500.00 14 LS 800.00 15 LS 900.00 16 LS 2.500.00 17 LS 2,500.00 18 LS 21500.00 19 LS 600.00 20 LS 400.00 -- 38 850 Tons 5.00 4.250.00 41. 480 LF 28.00 13,440.00 42 32 LF 22.00 704.00 43 24 LF 16.00 384.00 44 80 Tons 20.50 1 640.00 Total $33317TUOO Budgeted $28.500 (Additional funds required - use 02- 3397 -177) /; 0 0 August 19, 1968 Page 2 Subject: Combined Capital Projects 1968 -69, Corona Del Mar Area C -1123 Derek N. White Design Engineer DHW /ldg CC: Finance Director GENERAL FUND - SEWER Account No. 02- 5691'42 Item No. Quanti 1t 1 "` Price Amount 21 160 LF 10.00 $ 1,600.00 22 50 LF 6.00 300.00 23 2 Ea. 450.00 900.00 45 400 Tons 3.00 1 200.00 Total Budgeted $4,000.00 WATER FUND Account No. 50- 9297 -041 Item No. Quantity Unit Price Amount 25 3..soo 17� - -m -fM$ o.00 - 35 100 Ea. 90.00 9 000200 Total ' Budgeted $50.000 (Includes next project) /��O" 5° JyZQ 7 06 3 Item No. Quantity unit Price �unt 1 1,700 LF 0.75 $ 1,275.00 2 200 LF 2.00 400.00 24 1,900 LF 10.00 19,000.00 26 1 Ea. 10000.00 1,000.00 27 1 Ea. 600.00 600.00 28 1 Ea. 75.00 75.00 29 1 Ea. 200.00 200.00 30 1 Ea. 150.00 150.00 31 3 Ea. 350.00 1,050.00 32 8 Ea. 75.00 600.00 33 24 Ea. 150.00 3,600.00 34 6 Ea. 150.00 900.00 ---- 35 50 Ea. 90.00 4,500.00 36 1 Ea. 450.00 450.00 37 1 Ea. 250.00 250.00 -- 38 750 Tone 5.00 3,750.00 -- 44 120 Tons 20.50 2 460.00 Total ,.00 Budgeted $41,000 (Exhaust this fund first) Derek N. White Design Engineer DHW /ldg CC: Finance Director 1 I 0 ` y: F; I\„...... f•' c //Z 3 August 15, 1968 Walker 6 Bates 5947 Jasmine Street Riverside. California 92504 Attention: Mr. R. Batess Partner Subject: COMBINED CAPITAL PROJECTS 1968 -69. CORONA del MAR AREA. C -1123 Gentlemen: Attached for your use are 3 sets of revised sheets of the subject project.* You will note that these revisions include: 1. The increase of all curb radii to 151. 2. Change in length of the curb & gutter joins to 51. 3. We showed the additional utilities as mentioned in our letter of August 5, 1968. 4. Increase the length to be constructed of alley 15 -C (Contract sheet 6 of 25). Very truly yours, Derek White Design Engineer Dtiw /rjh Att. cc: Pat Dunigan * Sheets 3. 40 5, 6, 70 8, 9, 100 11, 14, 16, 17 of 25 4 .KY PILOT EDITORIAL PAGE i A Time for Patience Motorists in Corona del Mar — "old" Corona del Mar — will be detouring around a lot of rubble the rest of the summer. But the inconvenience will be worth it. The city next week will start tearing up much -trav- eled Second Avenue. Many alleys throughout the com- munity below East Coast Highway will also be torn up and closed off. All of it will be part of the biggest public works pro- ject in Corona del Mar since its annexation by the city of Newport Beach 40 years ago. The cost is $215,000. A new storm drain and water main will be buried along Second Avenue, which will then be repaved, from Avocado to Heliotrope. The alleys, those in "really rot- ten shape," as one city aide puts it, will be reconstruct- ed. Storm drain and sewer replacement work will take place in other areas, as well. The work has been long needed. But why do it now, one might ask, in the middle of summer? To beat the rains, explains Public Works Director Joseph T. Devlin. Corona del Mar's clay soil won't ab- sorb water quickly enough to make the project practical except during the dry season. So the work must be done now, when the traffic is heaviest. Residents, then, can only be patient. And they should surely find some satisfaction in knowing that here is concrete evidence — no pun intended — of their tax dollars at work. All of the $215,000 comes from revenue generated by the city's $1.225 tax rate. About a dime of that tax rate goes toward the Corona del Mar project. That's a lot of money, but it is still a bargain. It would have cost an estimated 15 percent more had not all the work been combined into one "omnibus" pro- ject. It is this kind of planning and engineering that en- ables the city to keep up appearances, with economy. Municipal officials serve the taxpayers well with such all approach to their responsibilities. Potential Money Saver U. S. Army air defense crews may soon be shooting down paper rockets — for training purposes. That's a prospect as a result of a newly developed Philco -Ford Aeronutronic product. Company officials took the wraps off the proposed military air target at a press conference the other day. They call it LOCAT, for Low Cost Air Target. The fuselage of the 15 -foot long, 155 -pound rocket - powered device is made of rolled paper tubing. The fins and nose cone are made of the same type of plastic used for surfboards. In other words, it's a cheap item. And that, it seems to us, is as it should be. It is, after all, designed only to be blown out of the sky by air defense gunners. Philco-Ford executives say LOCAT will work just as well as costly military targets now in use. It travels at 500 miles an hour, they say, and simulates a low flying jet. And it won't cost much. We hope this won't rule it out for consideration by the Department of Defense. Lockabey's Walrus Win Newport Beach lifeguard Logan Lockabey last week won an impressive victory in the annual Walrus'Swim. In the race around Newport Pier, Lockabey out- scored his closest opponent by 1,414,503 points. Now that's a substantial margin, even in these days of rising everything — except for Dodger baseball scores. Lifeguard Lockabey deserves congratuli}tla�;�€; splendid performance. The scorekeepers, of e7 , " ayother matter. g. ..,..7.- r 0 ,: August 13, 1968 Walker and Bates 5947 Jasmine Street Riverside, California 92504 Attention: Mr. n. Bates, Partner Subject: Combined Capital Projects 1968 -69, Corona del Mar Area, C -1123 Gentlemen: Attached for your information and files is a fully executed copy of the contract for the subject project. Please proceed with construction in accordance with the Plans, Specifications and Special Provisions. The contract was executed by the City on August 12, 1968. With reference to your letter of August 7, 1968. the revised unit prices for Items 1 and 35 are most acceptable. Thank you for your consideration. V�ry truly yours, Derek H. White Design Engineer DHW /ldg Att. CC: Field Engineer August 12, 1968 TO: CITY CLERK FROM: Public Works Department llZ3 SUBJECT: COMBINED CAPITAL PROJECTS 1968 -69,, CORONA DEL MAR AREA, C -IM Attached are three sets of Contract Documents and one set of Insurance Certificates for the subject project. These documents have been reviewed and approved, as noted, by the City Attorney's office. When all documents have been executed by the Mayor and your office, please retain your copy and return the Contractor's and Public Work's copies to me. ,Z=a1V Derek H. White Design Engineer DHW /ldg Att. • Corona del Mar Chamber of Commerce Box 72 Corona del Mar, California Attention: Mr. John Semple President 0 457=11Z3 August 8, 1968 Subject: Combined Capital Projects 1968 -69, Corona del Mar Area Contract 1123 Dear Sir: The City has awarded a contract to Walker and Bates of Riverside, California for the subject project and work will begin in a few days. Attached for your information are copies of the following: 1. Sheet 1 of the Plans showing the location of the work. 2. Sheets 3 and 4 of the Special Provisions regarding traffic control. 3. A general letter sent to residences to be affected by the work. 4. A letter sent to Councilman Shelton and others regarding the Contractor's temporary storage area. I hope that this information will be of value to you and request that you mention the project at your next meeting in case we have accidently overlooked any property owner or resident of the area that may be affected by the work. If you have any questions, please call Mr. Ed McDonald or me at 673 -2110, Ext. 26. Very truly yours, Derek H. White Design Engineer DHW /ldg Att. • 171 WALKER & BATES PUBLIC WORKS • ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 5947 JASMINE STREET ENGINEERING 3 BUILDING RIVERSIDE, CALIFORNIA 92504 PNONE61 686 -5690 689.7409 August 7, 1968 City of Newport Beach City Hall 3300 Newport Blvd. Newport Beach, Calif. 92660 RE: Combined Capital Projects 1968 -69 Corona Del Mar Area C -1123 Attention: Derek H. White Gentlemen: We are in receipt of your letter dated August 5, 1968. As you requested we have reviewed our unit price on Item No. 1, Temporary A.C. Pavement and if the quanities will increase as you anticipated we will do this at the unit cost of 75 cents per lineal foot. On item No. 35, we feel that $90.00 each would be an equitable price for Replacing Existing Water Services,(including new services). Please let us know if the above changes in unit prices meet with your approval. RWB /hl Very truly yours, WALKER & BA:'ES R.W. BATES Partner RECEIVE R -i�Z 3 ,. ,,. " <, �,✓ �rEL;,s August 7, 1968 T0: FROM: Public Works Department SUBJECT: COMBINED CAPITAL PROJECTS 1968 -69, CORONA DEL MAR AREA, C -1123 For your information, Walker and Bates, the contractor for the subject project, will begin moving in on the job this week. We have authorized the contractor to erect a small storage shed and chain link fenced area.within the Bayside Drive right -of -way between Goldenrod and Heliotrope Avenues. This will be maintained until the project is complete, about four months. Upon completion of the work, the site will be returned to the same condition as it is today. Since such storage areas are particularly attractive to vandals, we request routine surveillance by the Police Department during its normal operations in the area. Stockpiles of pipe will be placed, this week, at intervals along Second Avenue between Avocado and Goldenwood Avenues in prepara- tion for installation of the new water lines. The pipe will be banded and the stockpiles identified with night - lighted barricades. Derek H. White Design Engineer cc: Utilities Supt. Traffic..Engineer Field Engineer 6 Walker a Bates 5947 Jasmine Street Riverside, California 92504 6 c (/iz 3 August 5. 1968 Subject: Combined Capital Projects 1968 -69, Corona Del Mar Area C -1123 Attention: Mr. R. W. Bates. Partner. and Mr. D. Myers, Superintendent Gentlemen: We are in receipt of your proposed work schedule for the subject project, dated August 1, 1968. It has been reviewed and approved by our Field Engineer, Mr. Pat Dunigan, and myself. In answer to your request at our pre - construction conference on July 25, 1968. in our Field Engineers office, the following is a list of those in attendance: Mr. R. Bates, Walker a Bates, Partner Mr. Vj Myers, Walker a Bates, Superintendent Mr. E.'. Olsen, Southern California Edison Co., Customer Service Planner Mr. P. Eaton, Pacific Telephone a Telegraph Co.. Engineer Mr. W. Beyeler, City, Assist. General Services Director Mr. J. Frost, City, Utilities Division Mr. P. Dunigan, City, Field Engineer Mr. D. Robison, City, Field Inspector Mr. E. McDonald, City, Designer Mr. D. White, City, Design Engineer We are still reviewing potential equipment storage areas and will let you know the results within a few days. It appears that the area within the Bayside Drive right -of -way that you had hoped to use as a small disposal site is not suitable due to the potential drainage problems. Please check with Pat Dunigan for alternate locations. Page 2 Walker 6 Bates August 5. 1968 Subject: Combined C -1123 41 Capital Projects 1968 -69, Corona Dal Mar Area The approved schedule of work is generally the reverse of that which we had anticipated during the design statue. Consequently the quantity of Proposal Item No. 1, Temporary A.C. Pavement - -Trench Areas may increase from 200 to approximately 1900 lineal feet. In view of this increase in quantity, I request that you reconsider the unit price. I suggest that approximately 75 cents per lineal foot, rather than the bid price of one dollar per lineal foot, would be an equitable price. Also, as we discussed. it appears that we underestimated the quantity of Proposal Item No. 35. Replace and Reconnect Existing Water Services ((including new services). The estimated quantity required is closer to iSO than 50. In view of this large increase in quantity and the very substantial cost that it represents at the bid price of 100 dollars each, I request that you reconsider the unit price. I suggest that approxi- mately 85 dollars each would be an equitable price. I realize that labor costs represent a large portion of the price and are constant, regardless of the quantity. Your co. iderat /on of these requests is appreciated. Attached are xerox copies of additional information received from the utility companies during the last week. We will revise our plans to show these underground conditions, but wish to keep you informed until then. These include underground telephone cable at the intersection of Alley 20-0 and First Avenue; gas lines at the intersection of Alley 18-D and Second Avenua; and underground Edison cable at the intersection of Ailey 14 and Avocado Avenue. Very truly yours, lzw Derek H. White Design Engineer DHW /rjh Att. cc: Pat Dunigan 0 a WA L K E R & BATES PUBLIC WORKS - ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 3947 JASMINE STREET ENGINEERING 8 BUILDING E r� I V E D RIVERSIDE, CALIFORNIA 92504 PHONES, 686.9690 689 -7409 City of Newport Beach 3300 Newport Blvd. Newport Beach, Calif. A4-4 0 2 1968 „�s_LiC ��URKS _DEPT, August 1, 1968 RE: (A) Storm Drain (B) Water Main Reconst. (C) 2nd. Ave. Reconst. (D) Alley Reconst. Contr.1123. Listed below is our work schedule for work on the above project. 1. a. Install 12" main line on Second street, from Avocado to Helitrope. b. Make 6" tap at Avocado. C. Install all valves and fittings along this line. d. Pressure test 12" line. e. Make all short length connections into cast iron pipe. f. Temporary pave ditches on Second street. Traffic will not be interrupted during this operation. Small barricades flashers will be used for warning and control. 2. a. After testing of 12" lines, 6" lines in alley will be started, proceeding from Second street outwardly to end of lines. b. After line is installed and services are installed to meter., the line will be tested and then connected to existing cast iron pipe and meters hooked up to services. So that the home owners will not be inconvienced more than necessary this work will be coordinated with the Inspector so notification can be sent to the home owners. This stage of work will require the closing of various alleys for approximately two days at a time in each block. Complete operation for this stage will be approximately six weeks. 3. a. Storm drain & sewer work will begin about five weeks after start of project. This work will be independent of water works. b. This work will require closing of streets from Fernleaf to Dahlia for approximately six weeks. These streets will be barricaded with Class I barricades with warning signs set at proceeding blocks, marked closed to through traffic. Residence in this area will be allowed to pass through. 1p WALKER & BATES PUBLIC WORKS . ENGINEERING PROJECTS - COMMERCIAL GENERAL CONTRACTORS 5947 JASMINE STREET ENGINEERING & BUILDING RIVERSIDE, CALIFORNIA 92304 PM9NE91 888 -9890 Page 2 August 1, 1968 :89.7409 4. a. Alley grading and paving will start at completion of testing and connections of each alley water line. This will be about three weeks behind the water crew. b. This work will close alley for about five days at a time and will be coordinated with the Inspector. 5. When all water, storm drain, sewer, and alley work has been finished, Second street will be closed and construction completed. It is our estimation that the above schedule will permit Walker & Bates to complete this work with very little inconvience to the home owners in this area as Second street will be closed for a short period of time. In general all work and installations will be started at the West end of the project and proceed East and extending outward from second street. We are looking foward to a pleasant association with The City of Newport Beach and the home owners in the area and will endeavor to complete this project with as little inconvience to the home owners as possible. RWB /hl Very truly yours, WALKER & BATES BY: (/s /' 'Alc �t a R.W. BATES Partner: 6 C —// z -7 July 24, 1968 TO: FIELD ENGINEER FROM: Design Engineer SUBJECT: COMBINED CAPITAL PROJECTS 1968 -69, COMM DEL MAR AREA, C -1123 Attached for your use is one set of Plans and Special Provisions for the subject project. The inspector has picked up two sets previously. Also included is a print of the Bid Swrwry. A breakdown of the accounts and amounts to be charged against each will follow before construction begins. Mr. Don Myers, Superintendent for the Contractor, Walker and Bates, will be here at 2:00 P.M., July 25, 1968 to begin working out his schedule of work with us. It would be preferable if both you and the inspector could attend this meeting. Representatives of the Utilities Division and the General Services Department will be present. I have suggested that we use your conference table for the meeting. Derek H. White Design Engineer DHW /idg Att. CC: Public Works Director Asst. Public Works Director PO R T L AN D C E M E N T A S S O C1 A T I O N 680 WILSHIRE PLACE, LOS ANGELES. CALIFORNIA 90005 • TELEPHONE 386 -8450 • AREA CODE 213 LOS ANGELES DISTRICT July 17, 1968 Mr. Joseph Devlin Public Works Director Newport Beach, California Dear Mr. Devlin:- There are three reasons for this letter. First: to express my appreciation for permitting the Portland Cement Association to assist you in the preparation of the plans and specifications of the Second Avenue project in Corona del Mar. Second: to develop an outline for your use in presenting the advantages of portland cement concrete pavement to the city council. Third: to enumerate the services that our Association would be pleased to provide to the city in the event that concrete is selected. Advantages 1. Background A. Historical 1. There are 20.5 miles of concrete streets in Newport Beach constructed, in the main, during the 1920's. 2. The sections vary from 4 to 8 inches. 3. By and large, the quality of the concrete used for construction was good. 4. The pavements were built for the light traffic loads of the day. B. Present day 1. Forty years later, these streets are still successfully carrying a large volume of moving wheel loads of 1968 r AN ORGANIZATION TO IMPROVE AND EXTEND THE USES OF CONCRETE 0 0 Mr. Joseph Devlin - 2 - July 17, 1968 traffic including trash trucks, moving vans, ready mix concrete trucks, and school busses. 2. The only maintenance necessary has been infrequent joint filling. 3. In the case of concrete, no "beefing up" of the section to carry the increasing traffic loads has been necessary II. Design and construction considerations A. The most current design method, the California Division of Highways' Rational Design Method for Portland Cement Concrete Pavements and the latest construction techniques have been employed by your staff. This insures an adequate economic pavement accommodating the heaviest traffic over a conservative design life of 40 years. Modern methods of placement, finishing, curing, and jointing are included. III. Economic considerations A. Maintenance is a necessary but often -times an omitted cost item. Using maintenance costs developed by the City of Los Angeles and the "annual cost" analysis method it will be noted that over a 40 -year period, a concrete pavement for Second Ave. will benefit Newport Beach by some $8,000. Similar costs have been substantiated through an interview with the former city engineer of Costa Mesa. That city recently completed a "face - lifting" operation of some 25 miles of municipal streets whose ages varied from 3 to 8 years. It is to be noted that these are pure and simple maintenance requirements -- not widening or lengthening projects (see attached newspaper clippings). IV. "Fringe" benefits A. An inherent safety feature of concrete is the character- istic of gaining strength with age. B. Lower street lighting costs due to the higher light- reflec- tive qualities of concrete can be anticipated. C. Concrete will not soften and stain during the hot summer months. V. Portland Cement Association services A. Publicity arrangements will be made with newspapers and professional magazines (American City et al) covering construction of the first modern concrete city street pavement project in Orange County. Ll Mr. Joseph Devlin - 3 - July 17, 1966 B. The project will be given further publicity through scheduled inspection trips by consulting and municipal enginees and administrators. C. A "concrete inspector's" training course will be provided. D. An Association engineer will be available during the construction period. It is certainly gratifying to me to observe Newport Beach in the forefront of the ever increasing number of cost - conscious engineering organizations who are taking a closer look at their street and alley pavement construction and maintenance programs. An example is the excellent study recently completed by engineers Ed McDonald and Derek White of your staff. The $1.3 million improvement of a 2 -mile portion of Hoyt Ave, in E1 Monte is a recent example of a city, in cooperation with Los Angeles County, using the Total Cost Evaluation Concept* to select concrete in preference to lower first -cost blacktop. Finally, Mr. Devlin, it is my feeling that a decrease in the Public Works Department street maintenance fund requirements would be most welcome to the city council in these times of spiralling taxation. *Total Cost Evaluation Concept = Initial cost + Periodic resur- facing costs + Engineering, inspection, traffic delay, and restrip- ing costs + Annual scheduled maintenance costs. Very truly yours, District Engineer Warren G. Burres *mn cc - Ben Nolan Derek White John Van Steveren Gayle Pickart Ed McDonald Stan Scholl PORTLAND C E M E N T A S S O C I A T I O N ^� 580 WILSHIRE PLACE. LOS ANGELES. CALIFORNIA 90005 TELEPHONE 386 -8450 AREA CODE 213 F• LOS ANGELES DISTRICT AA._. .. , _ ... ..'�ibar;r /WS7 !!Loft/** do✓10 /.9456 ews I • w I CM Resurfacing Advances : COSTA AfESA — Smoother work is nearing completion. 'riding gloms for drivers as one Southworth said this program 'of txto street projects nears Involves coating of slurry seal completoc. ;on numerous westside streets, The $180,0*program calls for'which were not resurfaced last e mpllte resurfacing of some year, and all 'streets in the Col. ilege Park and Halecrest subdi• vision- areas. He said his department has .also completed about two-04--'s of a resurfacing program. This On Pages B14,. Cs calls for adding 1% inches of - new material to pavements on :major streets, Southworth ex- rnp* ib rv* fares, according'plalned. to Qty- Engineer Don South- He said streets resurfaced or "Ah' scheduled for work include Vale He adds that Um recoating of,Drive, Fairview Rnad, Superior othet roasts which support light - Avenue, Placentia Avenue, East er traffle,loada is presently un-� 15th Street; Street' East 17th Street, der' way. Baker Street fnd Royal Pahn ` The eathrW6d.cbat of the re -Drlve Isldantial street piejeM which Southworth, amid the cost at covers ppprokimately 25 miles,Ithis package is estimated at Is t14o;o0, "thiroi•th said. Thi, l$14a,t1o0; who ratirod. i School Parking. Lot Work OKd SANTA ANA — A $13,9oo can - Aract for repairs and recoating asphalt at seven parking areas of the Santa Ana Unified School District has been awarded by trustees. The contract for seal coaft parking areas at the adminis tration building and Diamod Edison, Martin, Wilson, Valle and Willard schools was swan ed Tuesday night to Alpha Coating Co., Fullerton. AN ORGANIZATION TO IMPROVE AND EXTEND THE USES OF CONCRETE P- �`: .r. 6`iL ` f�•+fi� -tea' c..c'.>��t�' Ga.1c.�f�' �°AVe.,�c��' .. FJ ... /4i'esin%i� � ... _. � ..i�Of- yGq -' ` •:I3 �i,.arcrrc:3Gi'i� • i a >: Q /at.� �c�,o PA✓c��cr�f ,D, l•��fro � c;'a.�f �2. ' ✓ �'�IG e9- GIIJH�� � /d � fiv�i• v9� ��G/ . 2• �G.?r.��7�BCi:�rs . �. /�y��' �� ' Ei7ginCG"�nli 'o:,d /��,�� eCr /c�7 /O/o emu/ /,pro /.,�c• / /��a //•✓o•�' /o,�� 3. .Pc.�'u. • fvci. i Jn `as= c�.1' yr �. �� T.So /1% , �. E- ��i -7L"C r /��n 3i)p- /- v✓`�4°Gli'C -) /Q /p r� v j /Gc5'o� ✓ 2. 325 3,r'po 3.so 950 3�•5 0 3j .ODD ¢Od Ave,- Southern Counties Gas Co. P. 0. Box 1319 Santa Ana, California July 18, 1968 Attn: L. M. MacMillan, Section Supervisor Subject: CO :XINED CAPITAL PROJECTS, 1968 -69, CO: °ONA OEL MAR AREA C -1123 Gentlemen: Attached for yair inforaati.n are one set of Plans and Special Provisions for the suhJect project. This is the project to which we referred in our memos to you of 4- 2847, 6- 23-67, and y- 106-67. We hope that we have recorded your facilities correctly; if not, please let us know and we will make the corrections. The contract will be awarded to Walker -Bates Const. Co. of River- side on July 22nd, 1968. Construction should be in 3 -4 weeks there- after and is expected to take 3-4 months to complete. A pre - construction meeting will be arranged with the contractor. If you wish to be represented, please let me know. and I will notify you of the time and place when determined. In the meantime, if you have any questions, please contact Mr. Ed McDonald or myself at 673 -2110, Ext. 26. Very truly yours. Derek H. Fite Design Engineer DNW /rjh Att. C i /23 July Ia. 1968 Southern California Edison Company 1r39 Main Strnet Ilunti :9ton Beach. California Attn: Mr. E. T. Olsen, Customer Service Planner Subject: COMBINED CAPITAL PROJECTS 1968 -69, CORONA DEL MAR AREA C­1 Gentlemen: A*tached for your information is one set of the Plans for the subject project. If any of your facilities are s "dn incorrectly, please let us know so that we may correct the Plans. Thn contract % -iii M: 7konrded to Walker- C?ates Con::truction Co. of Riverside on July 22nd, 7 968. Const:- cction shou'id begin 3 -4 weeks thereafter and is ex;+ected to take 3 -4 months to complete. A pre - construction meetine will be arranged with the contractor. If you wish to be represented, please let me know, and I will notify you of the time and place when determined. In the meantime, if you have any questions, please contact Mr. Ed McDonald or myself at 673 -2110; Ext. 26. Very truly yours, Dere �H6r0ite Design Engineer DHW /rjh Att. July 18. 1968 Pacific Telephone 6 Telegraph Co. 311 E. Balboa Boulevard Newport Beach, California 92661 Attention: Mr. A. Schvarz, Senior Engineer Subject: COMS14ED CAPITAL PROJECTS 1968 -69, CORONA DEL MAR AREA C -1123 Gentleman: Attached for your information is one set of the Plans for the subject rroject. If any of your facilities are shown incorrectly, please let us kn!,^w so ttllat ;:e may correct the Plans. The contract will be awawded to W&Uer -Bates Constructi -n Co, of Riv ,erside on 3uly 22nd, 1958. Sonstruction should begin 3 -4 weeks thereafter and is ?xp-acted to take �'•l month3 to complete. A pro - construction meeting will be arranged with the contractor. If you wis'.t to be represented. please let me know; and I will notify You of the time and place when determined. In the meantime, if you have any questions, please contact Mr. Ed McDonald or herself at 673 -2110, Ext. 26. Very truly yours, /! Derek H. White Design Engineer DHNjrjh Att. • Orange County Sanitation District 10844 Ellis Avenue P. 0. Sox 5175 Fountain Valley, California Attn: Mr. Robert Galloway ®uly 18. 1568 Subject: COMBINED CAPITAL PROJECTS 1968 -69. CORONA DEL MAR AREA C -A I Z3 C�n'.;1 seen Attached for your information is one print each of shoots 1, 12. and 19 of the Plans for the aubject project. !f any of yov, facilities am- sh-vin ':ncvrre0;l),,, ;Tease let us; ?now bc} that we may correct the Plans. The contract will be awarded to Walker -Bates Construction Company of Riverside or July 22nd, 1960. Construction should begin 14-4 weeks thereafter and is expected to take 3-4 months to complete. A pre - construction meeting will be arranged with the contractor. If you wish to be represented, please let me know. and I will notify you of the time and place when determined. In the meantime, if you have any questions, please contact Mr. Ed. McDonald or myself at 673 -2110. Ext. 26. Very truly yours. C�_ l� Derek H. White Design Engineer DIIW /rjh Att. a c -,,23 July 170 1968 TO: POLICE DEPARTMENT and FIRE DEPARTMENT FROM: Public Works Department SUBJECT: COMBINED CAPITAL PROJECTS 1968 -69, CORONA DEL MAR AREA Attach +)d for your information is one print of the Title sheot of the construction drawings for the subject project showing the various locations of the work. Also attached are sheets 3 and 4 of the Special Provisions which include items relative to Traffic Control. The contract trill be awarded on 'luly 22nd, 1968 and construction is expected to begin 3 -4 weeks there- after. Completion of the project is expected to take approximately three i:,onths. If you need additional information. please contact Ed McDonald or wself. Derek N. White Design Engineer Att. I. • 0 L% —ts, L--rT-A, .. . ........ .. . ..... ------ - ------ ---- -V rL 1oc) b � --g� 0 .. . ..... ZOC)R� A DDli-70AVL 20.�, S<D CD, e cz(:6 SeniGr 4ao0 3,230 ¢ 7 70 3.1.47 f S�3 �frnrin/ ,�r • O 1 /o<av if p ,5-� "000 i2 �%�' /ain .tii vc� I 4/ 000 Alilkolw,4 1 �J 1 � I � j I 1 33785 t 7Z /S j 34 420 � 74 �Z, o00 27Coa t �,�s ¢95oa � ZiS863 133,637 27800 � Z36,3as M TO: TRAFFIC ENGINEER FRON: Design Engineer July 17, 1968 SUBJECT: COMBINED PROJECTS 1968 -69, OMNA DEL MAR AREA, C -1123 Attached for your information is one print of the Title Sheet of the construction drawings for the subject project showing the various locations of the work. Also attachel are sheets 3 and 4 of the Special Provisions which include Items pertaining to TRAFFIC CONTROL find EXISTVt6 TRAFFIC SIGNS AND MARKERS. The contract will be awarded on July 22nd, 1968 and it is anticipated that construction will begin 3-4 weeks there- after. Completion of the project is expected to take approximately three months. If there are my pavement markings that you wish to record before they are removed. p;t:se eo so before the middle of August. I presume that you will arrange for resigning and striping of the area after the construction is completed. If you have any questions, please contact Ed or oyself in the veM near future. Lire ite Design Engineer Att. C��z3 li TO: FRO": SUBJECT: 6 4 July 17. 1968 GENERAL SERVICES DIRECTOR Public Works Department COMBINED CAPITAL PROJECTS 1968 -65. CORONA DEL MAR AREA C -1123 Attached for your information is one sat of plans and specifications for the subject project. Bids were opened on July 16. 1968, and the low bidder is WALKER -VTES of Riverside. The contract will be awarded on July 22nd, 1968; and, construction is expected to begin 3 -4 weeks thereafter. Construction is expected to take approximately three months to complete. Mfore beginn?ng construction, the contractor will be meeting with us to discuss his proposed schedule of work. Since your operations are considerably affected by the work, you are invited to attend the meeting if you wish to do so. I wilt let you know the time and date. In the meantime, if you have any questions. please contact Ed McDonald or myself. Derek H. White Design Engineer i /Z3 TuS - .�sr os 4r-. ir�a /ii%cc(/ .®n �lo,r��l0 — . �f� -'�✓�� C(o%C' � Q�rl�i'g c/ .S. O_ �7�I -GG �� C� �r Jid LX/C /�S �, ✓ /Ol�fn F1I=//1 i GG�GA� �� r . S < /�r� in� G/�n Sir /� . s G ✓G�[ 7 /G{ /heir hri S3 't Gcrt 0��9L /<i /�`4 / /pc 0Qv ,/ 116; loon :'. (/� /� q.9o�it a ✓erok 63./ �rrrte % /eGa,S� �cvGrinq� . .. 0 4 THE PACIFIC TELEPHONE AND TELEGRAPH COMPANY 311 East Balboa Slvd, Newport Beach, California, 92661 RECEIVED AUG 01 1968 July 30, 1968 PUBLIC WORKS DEPT City of Newport Beach 3300 Newport Blvd. Newport Beach, California, 92660 Attention: Mr. Derek H. white Design Engineer Sir: Enclosed is a copy of a portion of our record indicating the approximate location of our underground facilities which you requested for your city contract No. 1123 for 1968 -1969. Encircled in red is the only portion of our plant which may fall within the proposed construction area. Thank you for advising us of the proposed improvement work. If you have any further questions please contact our engineer Mr. L. P. Eaton, 673 - 00116. Sincerely, J. Monk- J LPE:ej Dist. Const. & Engr. Supt. Enclosure /O'CL /�'C� AD [,A 0 P. � � X SOUTHERN COUNTIES COMPANY L ORANGE COUNTY DIVISION • P.O. GO% 1319 • SANTP ANA. CALIF. 92702 JUSTIN M, KENNEDY OWN SON Y-111 July 31, 1968 City of Newport Beach 3300 Newport Boulevard Newport Beach, California 92660 Attention: Mr. Joseph T. Devlin Subject: Combined Capital Projects - Corona Del Mar - C -1123 Gentlemen: Thank you for the opportunity to review your improvement plans ahead of construction. Our review indicates that existing gas facilities are, in general, accurately shown except for the apparently intentional omission of services. Enclosed are prints that show one area of recent change in 2nd Avenue e/o Acacia Avenue. We will have some minor relocation of meter vaults at various locations. This can be done without delaying your contractor. Please notify me or Bill Stickney of the time and place of your pre- construction conference. hvw /ad enclosures cc: W. C. Stickney Sin e7r l \ \y, H. V. Weaver Distribution Supervisor r RFt',FIVED AUG 0 i 1968 PUBLIC vvuimo UEPlj OS 7/S II 6 SS � t -_ - ..... ._ ----- — — X11 yr 67 i i '1 A.-7 7717 t=-3T •:3 -7 �Q ¢ MIN- -, ' M h VLJJ rl 7 ai t� Q x V x m R C zz -r1 m ni -v N Z ca P Q X N N 3 �1 3, � a L —C 0 mob 1 t i y s I f A �'a�R b' n� v � i• 1 v ri n C ,� \ r r n T to A� p c °d N�rr� �. r- r. t a 0 W o log is it L N N ► A yl M C4 D, N 8 " D 808 z �s 100 1$ � f y �r ,g 1$ 8 E D of I a S r . r �8 o 00 0 18 � �8 IS If P C a 0 J o C , g ,g it PUS 0 Z B� ig ig ` 4 d � • -1 4 0 ti D o n p� 0 D zz -r1 m ni -v N Z ca P Q X N N 3 �1 3, � a L —C 0 mob 1 t i y s I f A �'a�R 5 s m T OD 0 8 it / t 1 l -� ff 0 w nOx V44 'B i2 -ice ■R f rl.�� i z m m mn v; z 1 A' mF;� 0 g 5 ■ N C 3 D { d31Y99739999H� Yl� uiwiu�e��� �n IIIIIMII�INIINIIa INININA��nnn���i0 IYIIII�II��p�llll��ll� oiA�uu�u�nn� INYIININb�IINIRI�� ��I �Il�llllll���li ■R f rl.�� i z m m mn v; z 1 A' mF;� 0 g 5 ■ N C 3 D { TO: FROM: SUBJECT: a July 12 1968 UTILITIES SUPERINTEMM Public Works Department"- COMBINED CAPITAL PROJECTS C.D.M. - 1968 -69 Attached for your information is one set of Plans and Special Provisions for the subject prolict. The plans include replacemen"f some water mains, some services. and no sewer mains in the alleys. Some alleys, therefore, will be reconstructed with 6k" concrete with none of these underground facilities being replaced at this time. This concept is the result of our periodic reviews and discussions with you and other members of the Public Works Department over the past 12 months. We realize that subsequent field inspections may adjust the quan- tities of replacements shown. For this reason we have attempted to establish bid items that will simplify adjustments. We assume that your people will coordinate with the Field Engineer during construction to facilitate these adjustments. We also realize that the water services may complicate preparation of subgrade in the alleys due to their proximity to the surface. We also hope that you will assist the Field Engineer in this regard. In order to help facilitate these and any other problems, I would request your attendance at the pre - construction meeting. I will advise you of time and date later. lJ Derek H. Mite Design Engineer DHW /rjh