HomeMy WebLinkAboutC-2064 - Stage 7 of Federal beach erosion control projectit TO: CITY COUNCIL �.n (Di-I BY THE CITY COUNCIL CITY OF NEWPORT BEACH AUG 131984 APPROVED FROM: Public Works Department August 13,, 1984 CITY COUNCIL AGENDA ITEM NO. F -17 SUBJECT: COOPERATIVE FEDERAL BEACH EROSION CONTROL PROJECT, SURFSIDE TO NEWPORT BEACH RECOMMENDATION: Approve use of leftover of a feasibility study t erosion control project. DISCUSSION: Stage 8 project funds for the local share o modify a portion of the existing beach Since 1963, the City of Newport Beach has participated in a coopera- tive beach erosion control project covering the area from Surfside to Newport Beach. The project has been constructed in a number of stages, with the major work consisting of the construction of groins and placement of beach fill in West Newport, and the placement of several increments of beach fill at Surfside /Sunset Beach. Construction of the Stage 8 beach fill at Surfside was recently completed. The City's share of Stage 8 (1.79 %, or $139,800) was budgeted in F.Y. 1983 -84. (The table appended to the attached letter indi- cates the participants in the cooperative project, and their percentage share of the costs.) A letter dated July 24, 1984 (copy attached) has been received from the Orange County Environmental Management Agency asking the local.partici- pants in.the project to approve the use of funds left over from the Stage 8 contract to perform a study of a structure to be constructed at or near the Naval Weapons Station jetty at the upcoast end of the project. It is felt that the construction of such a structure could save participants in the on- going cooperative project $8 - $11 million over a 50 -year projected life by extending the period between renourishment stages. Sufficient funds remain unexpended from the Stage 8 construction to fund the requested study without additional appropriations should the participants approve. The Public Works Department feels the concept is worth investigating, and the potential cost savings are significant. Approval is recommended. Benjamin B. Public Works BBN:jd Att. J. 9 Nolan Director oZ MURRAYSTORM q -O■ ■ N� O C DIRECTOR, EMA LOCATION: 811 NORTH BROADWAY SANTA ANA, CALIFORNIA 5 3 RANG E MAILING ADDRESS: �/ P.O. BOX 4048 SANTA ANA, CA 92702 -4048 TELEPHONE: (714) 834 -2306 ENVIRONMENTAL MANAGEMENT AGENCY FILE JUL 2-11984 S• �.�`9�� d MB"sRe' ach .� Mr. Robert L. Wynn, City Manager tootcv:u' City of Newport Beach P.O. Box 1768 3300 Newport Boulevard "_- Newport Beach, CA 92658 -8915 SUBJECT: Sunset /Surfside - Newport Beach Federal Beach Erosion Control Project Dear Mr. Wynn: In conjunction with subject project, State of California, Resources Agency, Department of Boating and Waterways is in process of proposing U.S. Army Corps of Engineers, Los Angeles District perform a feasibility study to determine "Federal Interest" in modifying the project to reduce costs of renourishment. Specifically, the Department of Boating and Waterways is requesting local agency approval that remaining funds from construction of Stage 8 of the project be used to fund the established 338 local matching share for the study. The original funding agreements from which the work is proposed to be funded did not envision the study, accordingly, it is requested that as a local agency you advise me as regards approving the use of leftover Stage 8 funds for funding the State Department of Boating and Waterways proposed Corps of Engineers study. EMA will recommend use of its Harbors, Beaches and Parks District's proportionate share of leftover Stage 8 funds be approved by its Board of Supervisors. To assist you in making your determination, the following background information is furnished: 1. Investigations by the Department of Boating and Waterways indicate that accelerated erosion adjacent to and downcoast of Naval Weapons Station jetties (,apparently caused by reflected wave energies off of jetties) causes need for frequent beach replenishment in order to maintain necessary beach widths Sunset /Surfside area and causes unnecessary beach width buildup downcoast. 2. Preliminary Department of Boating and Waterways calculations indicate that construction of minimal structure (i.e., submerged breakwater, groin, Mr. Robert L. Wynn, City Manager Daye 2 etc.) vicinity Sunset /Surfside could save project participants $8 -$11 million over the 50 -year life of a structure by extending the period between renourishment stages. Incidental benefit that could also accrue include (a) conservation of a scarce sand resource and (b) a reduction in planning and design administration costs and costs required in obtaining Federal and State Funding. 3. Federal Interest Study will be conducted by Corps of Engineers by con- structing a scale model at its Waterway Experimental Station, Vicksburg, Mississippi. Based on a seminar to discuss the scope and methodology attended by local participants technical staff, it is believed the condition can be accurately modeled and an effective project designed. 4. Estimated cost to perform Federal Interest Study is $100,000 and would require approximately one year to complete. Although final accounting of Stage 8 construction costs has not been performed, Stage 8 leftover funds in the amount of approximately $1,000,000 to cover the cost of the study are available. 5. Estimated construction costs of a proposed structure are difficult to ascertain at this time. However, Department of Boating and Waterways believes construction costs would range from $500,000 - $800,000. Actual decision to proceed with construction would be made at completion of proposed study. 6. To assist agencies in making decision, attached exhibit has been prepared showing pro rata estimated costs of study and preliminary cost estimates based on project's funding allocation formula. Should you have any questions or require additional information, please contact Bob Wingard of my office at 834 -3808. RFW:dthDR810 -3 7/23/84 Attachment cc: Supervisor Riley Supervisor Wieder Ben Nolan, Public Works Director 9 Very truly yours, h'ata- C -tA_<_ M. Storm 0 0 SUNSET /SURFSIDE - NEWPORT BEACH Federal Beach Erosion Control Project SUBJECT: Cost allocation table, Department of Boating and Waterways proposed Corps of Engineers Federal Interest Study FEDERAL U.S. Army Corps of Engineers STATE Dept. of Boating & Waterways Dept. of Parks & Recreation (Shoreline Owner Share) LOCAL Surfside Colony City of Newport Beach City of Huntington Beach Orange County HBPD (Sunset Beach) Orange County HBPD (Matching share of City of Newport Beach, City of Huntington Beach and HBPD's Sunset Beach total prorated cash) TOTALS RFW:dthDR810 -2 7/19/84 H FEDERAL DESIGN & INTEREST STUDY CONSTRUCTION PERCENT (Estimated Cost) (Estimated Cost) 67.008 1' 16.508 $ 16,500 $ 82,500 - $132,000 8.828 $ 8,820 $ 44,100 - $ 70,560 0.518 $ 510 $ 2,550 - $ 4,080 1.798 $ 11790 $ 8,950 - $ 14,320 0.908 $ 900 $ 4,500 - $ 7,200 0.90 $ 900 $ 4,500 - $ 7,200 3.598 $ 3,590 $ 17,900 - $ 28,640 100.008 $100,000 $500,000 - $800,000 0 0 CITY OF NEWPORT BEACH N.U. BOX 1768, NEWPORT BEACH. CA 92663 -3884 TO: FINANCE DIRECTOR FROM: CITY CLERK DATE: July 21, 1983 SUBJECT: Contract No. C -2064 OFFICE OF THE CITY CLERK (714) 640 -2251 Description of Contract Federal Beach Erosion Control Project Agreement (Stage 8) . Effective date of Contract June 14, 1983 Authorized by Minute Action, approved on April 11; 1983 Contract with County of Orange Address Environmental Management Agency P.O. Box 4048 Santa ana. CA 927024048 Amount of Contract See kaoto& e Wanda E. Andersen City Clerk WEA:lr attach. 3300 Newport Boulevard, Newport Beach 1. 1, * 2 %1 6 0 A? —QUN-r-y OF 5 jjZ I /M,FR^r--j4aa ENVIRONMENTAL MANAGEMENT AGENCY June 27, 1983 Benjamin S. Nolan Public Works Director City of Newport Beach 3300 Newport Boulevard Newport Beach, CA 92633 Dear Mr. Nolan: FILE MURRAY STORM DIRECTOR, EMA LOCATION: 811 NORTH BROADWAY SANTA ANA, CALIFORNIA MAILING ADDRESS: P.O. BOX 4048 SANTA ANA, CA 92702-4048 TELEPHONE: (714) 834-2306 Enclosed please find a fully executed copy of the Federal Beach Erosion Control Project, Stage 8 between the County of Orange Harbors, Beaches and Parks District and the City of Newport Beach. BS:ps Attachment Very truly yours, I.n M. Storm Director BEACH, 1 2 3 4 5� 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 261 27 281 1983, s AGREEMENT FEDERAL BEACH EROSION CONTROL PROJECT STAGE 8 Agreement No. D83 -031 THIS AGREEMENT is made and entered into the Leday of 67_, BY AND BETWEEN and County of Orange, Harbors, Beaches and Parks District, a political subdivision of the State of California, hereinafter called "DISTRICT ", City of Newport Beach, a municipal corporation, hereinafter called "CITY" WHEREAS, Congress has, by the enactment of Public Law 874, 87th Congress, adopted and authorized a beach erosion control project, to be accomplished in stages, which extends from Anaheim Bay Harbor to the west jetty of Newport Beach Harbor in Orange County, and WHEREAS, the implementation of said Federal beach erosion control project is of direct benefit to the beaches owned and operated by "CITY" and "DISTRICT" in providing a source of beach sand for replenishment of natural erosion of said beaches, and WHEREAS, the United States Army Corps of Engineers is prepared to under- take Stage 8 of said project at an estimated cost of $7,995,000, to be financed on the following basis: Federal Government 67 percent State of California 16.5 percent Local Agency shoreline owners consisting 16.5 percent of cities, DISTRICT, private and state division of beaches and parks and WHEREAS, the 5 year sand monitoring program of Stage 7 for the entire 80,000 linear footage of shoreline of the Federal beach erosion project is still in progress, and -1- 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Agreement No. D83 -031 WHEREAS, the "DISTRICT" is prepared to pay the local agency contribution of $599,700 as a share for all local shoreline owners for Stage 8 construction except that portion to be contributed by the State Department of Parks and Recreation, and WHEREAS, the shoreline owners' share of the cost for Stage 8 construction, based upon a formula of 80,000 linear feet of beach frontage within the Federal project area is as follows: Private beach owners: Surfside Colony Storm Water Protection District $ 39,800 Public beach owners: Orange County Harbors, Beaches and Parks District $ 70,300 City of Huntington Beach $ 70,300 City of Newport Beach $139,800 Orange County Harbors, Beaches and Parks District (508 for locally owned public beaches) $279,500 TOTAL $599,700 NOW, THEREFORE, the parties hereto do mutually agree as follows: I "CITY" agrees that remaining funding from Stages 4B and 5 for said project shall be applied to the design cost of Stage 8 of the project which shall cover the entire 80,000 lineal footage of shoreline of the Federal project area including "CITY'S" Newport Pier area, and that the final accounting of Stages 4B, 5 and 7 funding shall be incorporated into the accounting for Stage 8 described in Clause VI herein. II "CITY" agrees to pay "DISTRICT" within 60 days after billing by -2- 1 2 3 4 5 6 i 7i 8 9i 10j 11' 12 1 13 14 15 16 17j I 18 19 20 21 22 23 241 25 26 27 28 Agreement No. D83 -031 "DISTRICT ", "CITY's" portion of the cost of Stage 8 of the aforesaid beach erosion control project, said portion being the amount of $139,800. III "DISTRICT" agrees to coordinate said project with "CITY" and other local shoreline owners, State of California, and the United States Army Corps of Engineer; to the mutual benefit of all parties concerned. IV "DISTRICT" shall, within 30 days of the execution of this agreement and similar agreements by all of the aforementioned local shoreline owners and receipt of billing from the State of California, pay the local shoreline owners' portion of the Stage 8 Federal beach erosion control project in the amount of $599,700 to the United States Army Corps of Engineers to facilitate implementation of said Stage 8 project. V "DISTRICT" shall, and "CITY" may, assign inspector to project to inspect and determine the acceptability of the work to be performed by the United States Army Corps of Engineers as part of Stage 8 project, and it is agreed that the decision of "DISTRICT's" inspector shall be final in relation to the acceptability of said Corps of Engineers work. VI "DISTRICT" will obtain from the State of California Department of Navigation and Ocean Development, the agency coordinating the Stage 8 project with the United States Army Corps of Engineers, an accounting of all expenditures of all funds received for Stage 8 of the aforementioned project and shall pursue refund of any funds which are in excess of ultimate project cost on a proportionate basis to "DISTRICT" and shall, in turn, refund to "CITY" its prorated share of any refunds received within 30 days after receipt thereof by "DISTRICT" in a ratio equal to that stated in the recitals of Page 2 of this agreement. -3- 24 251 26 27 28 s VI I W Agreement No. D83 -031 "CITY" agrees, in recognition of "DISTRICT'S" financial assistance under the terms of this agreement, to allow residents of "DISTRICT" to utilize public beaches of "CITY" on an equal basis with "CITY" residents and without discrimination as to race, religion, sex, political persuasion or area of residency. VIII To the extent permitted by law, "CITY" shall indemnify and save harmless "DISTRICT ", its officers, agents and employees from and against all claims, demands, loss or liability of any kind or nature which "CITY" its officers, agents, or employees may sustain or incur or which may be imposed upon them or any of them for injury to or death of persons, or damage to property as a result of the negligence or wrongful act or omission by "DISTRICT ", its officers, agents, employees or invitees in carrying out the terms of this agreement or exercising the rights herein granted. -4- s 1 2 4 5 6 7 8 9 10 few 12 1 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Agreement No. D83 -031 IN WITNESS WHEREOF, the parties hereto have executed this agreement on the dates opposite their respective signatures: Date: Date: APPROVED AS TO FORM: ADRIAN KUYPER, COUNTY COUNSEL ORANGE COUNTY, CALIFORNIA 1 � By: Date: ATTEST: Y: Chzkirvn of the Board of Supervisors,: jxf a Harbors, Beaches & Parks District SIGNED AND CERTIFIED THAT A COPY OF THIS AGREEMENT HAS BEEN DELIVERED TO THE CHAIRMAN OF THE BOARD BY: u �v�e_) QL e� June Alexander Clerk of the Board of Supervisors of Orange County, California By: CITY OF NEWPORT BEACH BY: Mayor APPROVED AS TO FORM: City Clerk REVIEWED AN APPROVED: City AdmirAstrator Assistant City Attorney BS:dthD800 -3 -5- 3/10/83 RESOLUTION OF THE BOARD OF SUPERVISORS OF ORANGE COUNTY, CALIFORNIA and RESOLUTION OF THE BOARD OF SUPERVISORS OF ORANGE COUNTY, CALIFORNIA, ACTING AS THE GOVERNING BOARD OF THE ORANGE COUNTY HARBORS, BEACHES AND PARKS DISTRICT June 14, 1983 On motion of Supervisor Wieder, duly seconded and carried, the following Resolution was adopted: BE IT RESOLVED that the Clerk of this Board is hereby authorized to sign the Agreements on behalf of the Board of Supervisors, and the Harbors, Beaches and Parks District, dated June 14, 1983, with the City of Huntington Beach, the City of Newport Beach, Surfside Storm Water Protection District and the California Department of Boating and Waterways respectively for funding the local agencies' $1,288,500 por- tion of the $7,995,000 Federal Beach Erosion Control Project, Stage 8. AYES: SUPERVISORS HARRIETT M. WIEDER, THOMAS F. RILEY, BRUCE NESTANDE, RALPH B. CLARK AND ROGER R. STANTON NOES: SUPERVISORS NONE ABSENT: SUPERVISORS NONE Resolution No. 83 -919 Agreements /Fed. Beach Erosion Cont. Proj. /Hunt. Bch. /Nwpt Bch. / Surfside Colony Storm Water Prot. /Cal. Dept. Boating & Waterways /HBPD 1. it 2. I i STATE OF CALIFORNIA ) 2 ) ss. COUNTY OF ORANGE ) 3 I, JUNE ALEXANDER, Clerk of the Board of Supervisors of Orange 4 County, California, and Clerk of the Board of Supervisors of Orange 5 County, California, acting as the Governing Board of the Harbors, 6 Beaches and Parks District, hereby certify that the above and 7 foregoing Resolution was duly and regularly adopted by the said Board 8 at a regular meeting thereof held on the 14th day of June, 1983, and 9 passed by a unanimous vote of said Board. 10 IN WITNESS WHEREOF, I have hereunto set!4n� :Aiand and seal this 11 14th day of June, 1983. �. 12 :• 13 JUNE ALEXANDER-Clerk oft- e Board of Supervisors of Orange•County, California ':, W' off; 15 •., and , .• Clerk of the BPaitl ;_'o Supervisors of X00 Orange County;..Ca3ii�ornia, acting as >w 16 the Governing Board'of the Harbors, oz; Beaches and Parks District 0 g 17 18 19 20 21 22 23 24 25 26 N N O 27 LL ® 28 2. o-L (0� (�U May 5, 1983 Mr. Murray Storm Director. Environmental P. 0. Box 4048 Management Agency Santa Ana, CA 92702 -4048 Attention: Betty Shafer Re: Cooperative Funding Agreement, Beach Erosion Control Project, Stage 8 Gentlemen: Transmitted for action by the Board of Supervisors are copies of the Stage 8 Beach Erosion Control Project Cooperative Agreement. This agreement was approved by the Newport Beach City Council on April 11. 1983. The City wishes to express its dissatisfaction with the language of the indemnification section contained in the agreement. Because of the importance of proceeding expeditiously however, the agreement has been approved as originally written. It would be appreciated if EMA could request the County Counsel's office to work with our City Attorney. Robert Burnham, to develop mutually satisfactory language for the indem- nification section to be used in future cooperative agreements. Very truly yours, G � Benjamin B. I Nolan Public Works Director BBN :rb cc: City Attorney -i TO: CITY COUNCIL FROM: Public Works Department oil 11, 1983 Ou CITY COUNCIL AGENDA ITEM NO. 5;e— 3 /;v_� BY THE CITY COUNCIL CITY OF NEWPORT BEACH APR 11 1001 SUBJECT: ._.. _.._' RECOMMENDATION: _. Approve an agreement between the City and the Orange County Harbors, Beaches and Parks District providing for City participation in Stage 8 of the Cooperative Federal Beach Erosion Control Project; and authorize the Mayor and the City Clerk to execute the agreement. DISCUSSION: By letter dated March 11, 1983 (copy attached), the County of Orange has requested that the City enter into an agreement providing for City parti- cipation in Stage 8 of the Cooperative Federal Beach Erosion Control Project. This is the project under which, in earlier stages, beach fill was placed and the groin field constructed in West Newport. The currently proposed Stage 8 work consists of placing approximately 1,500,000 cubic yards of dredged sand on the beach in Surfside /Sunset Beach. The estimated total cost for the Stage 8 work is $7,995,000; with the Federal Government bearing 67% of the cost, the State of California bear- ing 16'x% of the cost, and local agency shoreline owners bearing 16-12% of the cost. The cost to the City of Newport Beach is $139,800. Payment of the City's share would be due in Fiscal Year 1983 -84, and funds have been included in the proposed Capital Projects budget. Attached for reference and background information is a copy of an earlier.report dated August 22, 1977 on the beach erosion control project. This report contains information regarding the history, nature, and funding of the project. As indicated, earlier stages of the project have been of great direct benefit to the City. In addition, the fill material placed on the upcoast beaches tends to migrate downcoast over time, and eventually to provide further nourishment of the beaches in West Newport. The most recent work on the project was Stage 7, completed in 1979 at a total cost of $3,840,000 and a City share of $102,960. This work con- sisted of placing approximately 1,300,000 cubic yards of dredged sand on the beach in Surfside /Sunset Beach. In addition, a long -term sediment monitoring program was established in Stage 7. The monitoring program has not yet been com leted. Benjamin B. Nolan Public Works Director BBN:jd Att. 0 Y OF NGE VIRONMENTAL MANAGEMENT AGENCY March 11, 1983 Robert L. Wynn City Manager City of Newport Beach 3300 Newport Boulevard Newport Beach, CA 92660 Attn: Ben Nolan, Public Works Director Dear Mr. Wynn: R�sl6 MAR 1 City Manager City 01 Naw, Beach, Enclosed for your processing is the agreement between the Orange County Harbors, Beaches and Parks District and the City of Newport Beach for Stage 8 of the Federal Beach Erosion Control Project. Enclosed also for your review is a copy of the Stage 8 agreement between the County and the State which will be executed upon completion of agreements between the County and the other participating jurisdictions. I have arranged a meeting between all jurisdictions to address -any questions on the monitoring phase of Stage 7 and the Stage 8 agreement. The meeting will be held on Tuesday, March 22, 1983., 1:30 p.m. at the Harbor Patrol Office, 1901 Boyside Drive, Newport Beach. After your City Council has executed the original and four copies of the agreement, please return them to this office. We will return a fully executed copy to you after completed action by the Board of Supervisors. If you have any questions please feel free to contact my assistant, Betty Shaffer at 8344752. BS:ps Attachments cc: Supv. Riley Please note meeting time change M Very truly yours, hza-�.,,,,,,,,_. M. Storm Director f MURRAY STORM DIRECTOR, EMA LOCATION: 811 NORTH BROADWAY SANTA ANA, CALIFORNIA MAILING ADDRESS: P.O. BOX 4048 SANTA ANA, CA 92702 -4048 TELEPHONE: (71 A) 834 -2306 FILE R�sl6 MAR 1 City Manager City 01 Naw, Beach, Enclosed for your processing is the agreement between the Orange County Harbors, Beaches and Parks District and the City of Newport Beach for Stage 8 of the Federal Beach Erosion Control Project. Enclosed also for your review is a copy of the Stage 8 agreement between the County and the State which will be executed upon completion of agreements between the County and the other participating jurisdictions. I have arranged a meeting between all jurisdictions to address -any questions on the monitoring phase of Stage 7 and the Stage 8 agreement. The meeting will be held on Tuesday, March 22, 1983., 1:30 p.m. at the Harbor Patrol Office, 1901 Boyside Drive, Newport Beach. After your City Council has executed the original and four copies of the agreement, please return them to this office. We will return a fully executed copy to you after completed action by the Board of Supervisors. If you have any questions please feel free to contact my assistant, Betty Shaffer at 8344752. BS:ps Attachments cc: Supv. Riley Please note meeting time change M Very truly yours, hza-�.,,,,,,,,_. M. Storm Director 0 01 August 22, 1977 STUDY SESSION ITEM NO. 8 TO: CITY COUNCIL FROM: Public Works Department SUBJECT: FEDERAL BEACH EROSION CONTROL PROJECT Attached is a letter dated July 20, 1977, from the Environmental Management Agency regarding a proposed federal beach erosion control_ project scheduled for construction in the fall of 1978. This construction project will be the next stage in the continuing program for the control of beach ero- sion extending from Anaheim Bay Harbor southeast to Newport Harbor. Because of the.funding complexities of the different stages, a summary has been in- cluded for Council information. The proposed project will place about 1,500,000 cubic yards of acceptable beach material southeast of Anaheim Bay jetty to form a feeder beach about 6,000 feet long and 250 feet wide. The present estimated project cost is $4,000,000. The Department of the Army is presently investigating alternate dredge sites in determining if the high cost per cubic yard of beach sand can be reduced. The complete beach erosion control project is described in House Document No. 602, 87th Congress,and was specifically adopted and authorized by Public Law 874, 87th Congress. The law authorizes the federal government to assist states and political subdivisions thereof in the construction of works for improvement and protection against erosion by waves and currents of their shores, and other purposes. The following is a summary of the previous beach erosion projects: Stage 1 of the project, completed in June 1964, comprised the place- ment of 4,000,000 cubic yards of sand, dredged from the U.S. Naval Weapons Station Harbor, to provide a feeder beach 500 feet wide and 2 miles long in the Surfside- Sunset Beach area. Total cost was $2,159,000. Newport Beach's share was $38,600. Stage 2 was accomplished under two contracts. The first contract, which was completed in February 1968, included the placement of 494,000 cubic yards of sand on the beach between 32nd and 50th Streets at Newport Beach and the construction of an experimental 258 -foot steel sheet -pile groin at 40th Street. The second contract, completed in November 1968, provided an addi- tional 240,000 cubic yards of sand in the upcoast area and the construction of a 190 -foot steel sheet -pile groin at 44th Street and a 60 -foot steel sheet -pile groin at 48th Street. Total cost $700,000. Newport Beach's share was $12,500. 13 August 22, 1977 C 0 C Subject: Federal Beach Erosion Control Project Page 2 Stage 3 provided for the construction of four rock groins and the place- ment of 750,000 cubic yards of sand on the Newport Beach area. The groin work, completed in November 1969, comprised: rebuilding the steel sheet -pile groin at 48th Street to a length of 340 feet; and constructing rock groins at 36th, 52nd, and 56th Streets with lengths of 490, 340, and 570 feet respectively. Sand fill was obtained from the Santa Ana River Channel as part of a flood control channel restoration project. This work was completed in January 1970. Total cost $600,000. Newport Beach's share was $10,761. Stage 4A, which was similar to Stage 1, provided for the additional placement oir2,300,000 cubic yards of sand on the Surfside- Sunset Beach area to maintain a 500 - foot -wide by a 6,000- foot -long feeder beach. Again, the source of material was from the U.S. Naval Weapons Station Harbor. The work was com- pleted in May 1971. Total cost $1,074,000. Newport Beach's share was $19,260. Stage 48 and Sta e 5 provided for rehabilitation of the two steel test groins at 40th and 44t Streets with permanent rock construction. This stage also includes a rock groin at 32nd and 28th Streets and the placement of 100,000 cubic yards of imported fill on the beach in the vicinity of 32nd Street and 40th Street. The sand would bB obtained from the`mouth of the Santa Ana River and the beach immediately downcoast of the river. Total cost $1,526,000. Newport Beach's share was $27,371. Exhibit "A" below is a summary of local funding for the different stages. EXHIBIT "A" .. e LOCAL (STATE, COUNTY, CITY AND PRIVATE) FUNDS FOR FEDERAL BEACH EROSION CONTROL PROJECT Private Beach dwnek Huntington Pacific Corp. $ Surfside Colony Ltd. Public Beach Owners State Div. of Beaches & Parks City of Newport Beach City of Huntington Bch Costs Absorbed by Co. Co. (Sunset Beach) Co. (50% for locally owned public beach) Total Local Costs r Stage Stage Stage Stage Stage Stage I II III 4A 4B & 5 5A (Current) 65,000 $ 21,320 $ 18,275 $ 32,710 $ 46,482 - - -- 10,900 3,555 3,049 5,460 7,755 $ 20,300 125,000 38,600 12,500 10,761 19,260 27,371 77,400 19,300 6,275 5,376 9,620 13,673 38,700 97,200 6,275 198,600 5,376 9,620 13,673 21,513 38,510 54,716 356,000 75,075 64,350 115,180 163,670 330,000 Total Project Cost $2,159,000 $700,000 $600,000 $1,074,000 $1,526,000 $4,000,000 f August 22, 1977 Subject: Federal Beach Erosion Control Project Page 3 Project financing is 67% federal funds and 33% local (State, County, City and private) funds in accordance with the existing Federal -State agreement. It is assumed that the State Department of Water Resources and Department of Parks and Recreation will contribute to the new project on the same basis as in the previous phase of the program. If so, and using previous local funding cost dis- tributions, the County, cities, and private interest costs would be approximately $330,000. The proportionate shares would be about $20,300 for Surfside Colony Ltd., $77,400 for the City of Newport Beach, $38,700 for the City of Huntington Beach and $193,600 for the County. The County plans to budget the total local costs of $330,000 and then get reimbursed from the other local funding sources. Exhibit "B" below shows the cost formulas used in determining the local funding on the different projects. Agency Federal Government State of California (Dept. of Water Resources) Local Share Local Share (Stages I thru5) State Beaches 8 Parks Surfside Colony .(SWPD) Huntington Beach Co. Co. Subsidy of Beach 1/2(16.5 % - 9.3291 %) City of Newport Beach ( 112 of Cots 112 City of Huntington Beach s 1/4 of Co's 1/2 Sunset Co. Beach 1/4 of Co's 1/2 S EXHIBIT "B" Cost Formulas Beach Length Old Formula 28,000(28/80) 2,000(2/65) 12,000(12/65) V Beach Length 67 16.5 16.5 100% 5.775 0.50820 % Amount 67 2,680,000 16.5 660,000 16.5 100% New Formula (Current Project) 40,000(40/80) 8.25000 2,000(2/65) 0.50769 3.04590 (now State)(0) 3.58545 3.87115 1.79355 12,000 1.93558 0.89595 6,000 0.96779 0.89595 6,000 (To be reimb.by Co.) 16.5% 330,000 20,300 193,600 77,400 38,700 16.5% 4,000,000 The City's share to date has been 1.79% of the total project cost. The share for the new project will be 1.935% and is a result of the Huntington Beach Co. now being a part of Stage Beaches and Parks. C0 August 22, 1977 Subject: Federal Beach Erosion Control Project Page 4 The EMA has indicated that the Funding Agreement between the City of Newport Beach and the County of Orange must be executed prior to July 1, 1978, and payment will be required immediately after July 1, 1978. IM:jd Att. R Devlin ks Director . . i CITY OF NEWPORT XALIFORNIA X %.#A A city ifiti" 3300 W..rt 81vd. Area Code 714 DATE January 25, 1979 TO FINANCE ])IPZCMR FROM: City Clerk SUBJECT: Contract No. 2064 Description of Contract Stage 7 of Federal Beach Erosion Control Project with the CounLy. Authorized by Resolution No. Effective date of Contract Contract with Address Amount of Contract 9467 adopted on November 13, 1978 November 21, 1978 Orange County Harbors and Beaches District 1901 Bayside Drive Newport Beach, CA 92662 See agreement City Clerc 4 MINUTES OF THE BOARD OF SUPERVISOR OF ORANGE COUNTY, CALIFORNIA December 19. 1978 f I, ✓qN4 �R� �fWP��ry F C9��FeFACy r� IN RE: AMENDMENT TO.AGREEMENT FOR SERVICES ORANGE COUNTY BURGLARY PREVENTION PROGRAM PROGRAM ADMINISTRATOR CHURCH On motion of Supervisor Riley, duly seconded and unanimously carried, the Chairman and the Clerk are authorized to sign the Amendment to Agreement for Services for the Orange County Burglary Prevention Program, dated.December.19, 1978, between the County of Orange and Orin C. Church, providing for the increase of the Administrator's reimbursement by $3,576.00, from $20,585.00 to $24,160.00 and hours of service by 296 hours, from 1704 hours to 2000 hours, as recommended. IN RE: AGREEMENTS FEDERAL BEACH EROSION CONTROL PROJECT STAGE 7 SURFSIDE COLONY STORM tFATER PROTECTION DISTRICT CITY OF HUNTINGTON BEACH CITY OF NEWPORT BEACH ORANGE COUNTY HARBORS, BEACHES AND PARKS DISTRICT On motion of Supervisor Riley, duly seconded and unanimously carried, the Chairman and the Clerk are authorized to sign the following Agreements for Federal Beach Erosion Control Project, Stage 7, dated December 19, 1978, between the Orange County Harbors, Beaches and Parks District, and the Surfside Colony Storm Wa-ler Protection District, the City of Huntington Beach, and the City of ae°.,7port Beach, providing for funding the local agencies' $142,560.00 portion of the $3.84 million Stage 7 project, as recommended by the Director of the Environmental Management Agency. AGENCIES AGREEMENT NO, SUPFSIDE COLONY STORM WATER PROTECTION DISTRICT D78 -115 CITY OF NEWPORT BEACH D78 -116 CITY OF HUNTINGTON BEACH RECEIVED D78 -117 DEC 211978 , rR)F1073 -2.3 (12/76) �� Aa PLF..ASE i1 ETURN TO CITY CRK CITY 0 ., NFIVORT REACH 3300 N�VIPORT BOULF.V!4Rn NEWPO�T BEACH, CALIF, 92665 AGREEMENT FEDERAL BEACH EROSION CONTROL PROJECT Agreement No. D78 -116 1II STAGE 7 2I THIS AGREEMENT is made and entered into the, day of 3 I 1976, 4 BY AND BETWEEN 5, County of orange, Harbors, Beaches and Parks District, a political subdivision of the State G of California, hereinafter called "DISTRICT ", 7 and 8 1 City of Newport Beach, a municipal corporation, hereinafter called "CITY ". 9 10 WHEREAS, Congress has, by the enactment of Public Law 874, 87th Congress, adopted and authorized a beach erosion control project, to be accomplished in stages, 11 12 which extends from Anaheim Bay Harbor to the west jetty of Newport Beach Harbor in i� I Orange County, and 13 WHEREAS, the implementation of said Federal beach erosion control project 14 15 is of direct benefit to the beaches owned and operated by "CITY" and ", DISTRICT" in I 16 providing a source of beach sand for replenishment of natural erosion of said beaches, and 17 18� WHEREAS, Stage 4B and 5 of the federal project has not been accepted by "CITY" due to concern that the area in the vicinity of the Newport Beach Fier 19 may be experiencing sand erosion as an impact of the federal project, and 20 WHEREAS, the United States Army Corps of Engineers is prepared to under - 21 23�take Stage 7 of said project at an estimated cost of $3,840,000, to be financed I on the following basis: 24 Federal Government 67 percent � 25 State of California 16.5 percent Local Agency shoreline owners consist- 16.5 percent 26 ing of cities, DISTRICT, private and state division of beaches and 27 parks 2 A 9 I /// 11 2 31 :! and WHEREAS, said Stage 7 of the Federal project will include a sand moni- Loring program of approximately 5 years in duration for the entire 80,000 lineal footage of shoreline of the erosion project including the area of the Newport Beach Pier which is of primary concern to "CITY ", and WHEREAS, the "DISTRICT" is prepared to pay the local agency contribution of $316,800 as a share for all local shoreline owners for Stage 7 construction except that portion to be contributed by the State Department of Parks and Recreation, and WHEREAS, the shoreline owners' share of the cost for Stage 7 construction, based upon a formula of 80,000 linear feet of beach frontage within the Federal project area is as follows: Private beach owners: Surfside Colony Storm Water Protection District $ 15,840 Public beach owners: Orange County Harbors, Beaches and Parka District $ 47,520 City of Huntington Reach $ 23,760 City.of Newport Beach $lOZ,960 Orange County Harbors, Beaches and Parks District (50% for locally owned public beaches) TOTAL $126,720 $316,800 NOW, THEREFORE, the parties hereto do mutually agree as follows: I "CITY" accepts Stages 4B and 5 of the Federal beach erosion project and agrees that remaining funding for said project shall be applied to the 5 year sand — ------------ monitoring program of Stage 7 of the project which shall cover the entire 80,000 lineal footage of shoreline of the Federal project area, including "CITY'S" Newport Fier area, and that the final accounting of Stage 4B and 5 funding shall be incorporated into the accounting for Stage 7 described in Clause VI herein. II "CITY" agrees to pay " DIS'TRICT" within 60 days after billing by "DIS- TRICT", "CITY'S" portion of the cost of Stage 7 of the aforesaid beach erosion control project, said portion being the amount of•$101,960. III "DISTRICT" agrees to coordinate said project with "CITY" and other local shoreline owners, State of California, and the United States Army Corps of Engineers to the mutual benefit of all parties concerned. IV "DISTRICT" shall, within 30 days of the execution of this agreement and similar agreements by all of the aforementioned local shoreline owners and receipt of billing from the State of California, pay the local shoreline owners' portion of the Stage 7 Federal beach erosion control project in the amount of $316,8UO to the United States Army Corps of Engineers to facilitate implementation of said Stage 7 project. V "DISTRICT" shall, and "CITY" may, assign inspector to project to inspect and determine the acceptability of the work to be performed by the United States Army Corps of Engineers as part of Stage 7 project, and it is agreed that the decision of "DIS1'RICT's" inspector shall be final in relation to the acceptability of said Corps of Engineers work. VI "DISTRICT" will obtain from the State of California Department of Navigation and Ocean Development, the agency coordinating the Stage 7 project with the United States Army Corps of Engineers, an accounting of all expenditures of all funds -3- received for Stage 7 of the aforementioned project and shall pursue refund of any funds which are in excess of ultimate project cost on a proportionate basis to "DISTRICT" and shall, in turn, refund to "CITY" its prorated share of any refunds received within 30 days after receipt thereof by "DISTRICT" in a ratio equal to that stated in the recitals of page 2 of this agreement. VII "CITY" agrees, in recognition of "DISTRICT's" financial assistance under the terms of this agreement, to allow residents of "DISTRICT" to utilize public beaches of "CITY" on an equal basis with "CITY" residents and without discrimination as to race, religion, sex, political persuasion or area of residency. VIII To the extent permitted by law, "CITY" shall indemnify and save harmless "DISTRICT ", its officers, agents and employees from and against all claims, demands, loss or liability of any kind or nature which "CITY ", its officers, agents, or employees may sustain or incur or which may be imposed upon them or any of them for injury to or death of persons, or damage to property as a result of the negligence or wrongful act or omission by "DISTRICT ", its officers, agents, employees or invitees in carrying out the terms of this agreement or exercising the rights herein granted. —4— , IN WITNESS WHEREOF, the parties hereto have executed this agreement as of the date first above written. n� Date: �Jeee�, GeJl9 /�7 Date: {j bro,n �.1 /9 /97;�' APPROVED AS TO F0101: ADRIAN KUYPER, County Counsel ORANGE COUNTY, CALIFORNIA ay 1o'�t,417 8 Date: oL� /S�� ATTEST" Doris George, y Clerk T.W1 . en977 CAN ORANGE COUNT}[ HARBORS, BEACHES AND PARKS DISTRICT �� i of the ATTEST: r JUNE ALEXANDER Clerk of the Board of Supervisors of Orange County, California CITY OF NEWPORT BEACH Bye`' y or APPROVED AS TO FbjM Dare: h CITY 0 N ; RECEIVED CITY Cf % ^K 9 JAN ? 5 1979 > CITY OF i November 21, 1978 TOt t Public Works PSOit t City Clerk SU&MCTt Agreement with County of Orange, Barbers, Beaches and Parks District for contributions of costs in connection with Stage 7 of the Federal Beach Erosion Control Project. (approved by R19467 on November 19, 1978) Attached are four copies.of the Federal Beach Erosion Agreement with the County. Please return the original and a copy to the County for execution. The other two copies see for you. One copy is to be returned to our office after the County has signed it. Thank you, RESOLUTION NO. 9 46 7 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NEWPORT BEACH AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE AN AGREEMENT BETWEEN THE CITY OF NEWPORT BEACH AND THE COUNTY OF ORANGE, HARBORS, BEACHES AND PARKS DISTRICT, FOR THE CONTRIBUTION OF COSTS IN CONNECTION WITH STAGE 7 OF THE FEDERAL BEACH EROSION CONTROL PROJECT WHEREAS, there has been presented to the City Council of the City of Newport Beach a certain agreement between the City of Newport Beach and the County of Orange, Harbors, Beaches and Parks District, for the contribution of costs in connection with Stage 7 of the Federal Beach Erosion Control Project; and WHEREAS, the City Council has considered the terms and conditions of said agreement and found them to be fair and equitable, NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Newport Beach that said agreement for the contribution of costs above described is approved, and the Mayor and City Clerk are hereby authorized and directed to execute the same on behalf of the City of Newport Beach. ATTEST: ty C ADOPTED this 13th day of November 1978. Mayor DDO /kb 11/6/78