HomeMy WebLinkAboutRS181588_ClearanceHistoryClearance History For Permit: RS181588
Clearance Name Clearance Status Clearance
Cleared For Clearance Comment Clearance Cleared By Clearance Date
Architectural & Structural Plan Check Corrections Dorothy Leever 1/16/2019 12:00:00 AM
Architectural & Structural Plan Check Required
Current Planning/Zoning Approved
RS181588 free standing
pergola raises no
planning issues
Ron Tippets 12/19/2018 12:00:00
AM
Current Planning/Zoning Required
Erosion and Sediment Contol Plan
(ESCP)Not Required Dorothy Leever 1/16/2019 12:00:00 AM
Erosion and Sediment Contol Plan
(ESCP)Required
Fire Authority Exposed Site (Plan
Check)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Exposed Site (Plan
Check)Required
Fire Authority Fire Sprinker (Plan
Check)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Fire Sprinker (Plan
Check)Required
Fire Authority Fire Sprinker Final
(Inspection)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Fire Sprinker Final
(Inspection)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Fire Sprinker Final
(Inspection)Required
1/24/2019 12:58:31 AM
Fire Authority Fuel Mod Final
(Inspection)Not Required Rebecca Schade 12/19/2018 10:09:56
AM
Fire Authority Fuel Mod Final
(Inspection)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Fuel Mod Final
(Inspection)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Fuel Mod Final
(Inspection)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Fuel Mod Final
(Inspection)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Fuel Mod Final
(Inspection)Required
Fire Authority Fuel Modification (Plan
Check)Not Required Rebecca Schade 12/19/2018 10:09:56
AM
Fire Authority Fuel Modification (Plan
Check)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Fuel Modification (Plan
Check)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Fuel Modification (Plan
Check)Required
Fire Authority Plan Review (Plan
Check)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Plan Review (Plan
Check)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Plan Review (Plan
Check)Required
Fire Authority Project Final (Inspection)Not Required Rebecca Schade 12/19/2018 10:10:00
AM
Fire Authority Project Final (Inspection)Required Rebecca Schade 12/19/2018 10:09:52
AM
1/24/2019 12:58:31 AM
Fire Authority Project Final (Inspection)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Project Final (Inspection)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Project Final (Inspection)Required Rebecca Schade 12/19/2018 10:09:52
AM
Fire Authority Project Final (Inspection)Not Required Rebecca Schade 12/19/2018 10:09:50
AM
Fire Authority Project Final (Inspection)Required
Grading Permit Required Not Required
GB150116 for tract
production, Lot 2 grading
final on 2-6-18
Dorothy Leever 1/16/2019 12:00:00 AM
Grading Permit Required Required
OC Waste and Recycling C&D Project Not Required Deysi Munoz 12/19/2018 12:00:00
AM
OC Waste and Recycling C&D Project Required
Sanitation District Approval Not Required Dorothy Leever 1/16/2019 12:00:00 AM
Sanitation District Approval Required
1/24/2019 12:58:31 AM