HomeMy WebLinkAboutC-2952 - Sewer Improvements in Pacific Coast Highway at Riverside Avenue.! !
CITY OF NEWPORT BEACH
OFFICE OF THE CITY CLERK
P.O. BOX 1768, NEWPORT BEACH, CA 92658 -8915
(714) 644 -3005
Cr ��7�rcC�itL
TO: FINANCE DIRECTOR
-/3 y.3
FROM: CITY CLERK
DATE: September 13, 1993
SUBJECT: Contract No. C -2952
Description of Contract Reimbursement Agreement for Construction
of Sewer Improvements in Coast Highway at Riverside Avenue
Effective date of Contract September 8, 1993
Authorized by Minute Action, approved on June 28, 1993
Contract with County Sanitation Districts
Address P.O. Box 8127
Fountain Vallev. CA 92728 -8127
Amount of Contract (See Agreement)
"X� 6'e
Wanda E. Raggio
City Clerk
WER:pm
Attachment
3300 Newport Boulevard, Newport Beach
CITY OF NP
June 28th, 1993
CITY COUNCIL AGENDA
ITEM NO. /z
APPROVED
TO: Mayor & Members of the City Council
FROM: Utilities Department
SUBJECT: AGREEMENT FOR CONSTRUCTION OF SEWER IMPROVEMENTS
IN COAST HIGHWAY AT RIVERSIDE AVENUE AND
COST SHARING WITH THE COUNTY SANITATION DISTRICTS
OF ORANGE COUNTY ( CSDOC)
RECOMMENDATIONS:
Approve an agreement with CSDOC on cost sharing
and providing for construction of certain sewer
improvements in conjunction with the Coast Highway
Trunk Sewer Project.
2. Authorize the Mayor and City Clerk to execute the
Agreement.
3. Require CSDOC to obtain a public works encroachment
permit on behalf of their contractor, for all project
improvements and waive fees for same.
DISCUSSION:
The proposed CSDOC Coast Highway Trunk Sewer Project will
provide for replacement and reconstruction of their large diameter gravity
sewer in the north side of Coast Highway, from Dover Drive, easterly to 'The
Arches Interchange ".
The City has had frequent maintenance and stoppage problems
in the sewer siphon across Coast Highway at Riverside Drive. The siphon
was originally installed in 1946. In 1988, the City hired a consulting civil
engineer to design a replacement of the sewer siphon. However, because
of the difficulties with traffic control and utility conduit conflicts, the
project was not implemented.
Because CSDOC is proposing some significant sewer
construction in the area, the City has an opportunity to coordinate work
and complete it under the CSDOC contract. The City requested CSDOC
to include the replacement of the sewer main across Coast Highway at
Riverside Avenue. CSDOC agreed, and incorporated those improvements
into their project plans and specifications. The City provided the
previously prepared design information to CSDOC's consulting engineer.
This proposed Agreement provides for reimbursement to
CSDOC for construction of City sewer improvements.
• Pap
CSDOC Cost Sharing Agreement
Coast Highway Trunk Sewer Project
June 28, 1993
The agreement was not in final form as of the writing of this
staff report, however, the principal terms of the proposed reimbursement
Agreement with CSDOC are as follows:
1. CSDOC includes 8 -inch diameter sewer main and
manhole replacements at Coast Highway and Riverside
Avenue and a segment easterly of the new "Pelican Wall"
into their ( CSDOC Contract 5 -37 -4) Coast Highway Trunk
Sewer Project construction.
2. City provides CSDOC consultant with design information.
3. City performs surveying and field excavation of existing
utilities to verify design.
4. CSDOC solicits bids for City improvements and, if bid
price is acceptable to City, CSDOC awards contract and
administers its construction.
5. City reimburses CSDOC for actual construction costs plus
inspection costs for City's portion of the construction.
The estimated cost to City is $46,000.
6. City reimburses CSDOC consultant for drafting expenses
to include City design in CSDOC project plans.
7. CSDOC obtains Caltrans and City encroachment permit
and meets all permit requirements for construction and
traffic control.
8. City waives encroachment permit fees.
The City's sewer improvements proposed by this agreement will
greatly reduce the required maintenance and cleaning of the gravity sewer
line serving the southerly side of Mariner's Mile and the numerous
restaurant and commercial establishments. Funds are available in the capital
projects portion of the Wastewater Enterprise Fund carried over to fiscal
year 1993 -94 under account number 7533 - 98530001.
The CSDOC project is currently advertised and is anticipating an
award of contract in July 1993, with a proposed construction start date
around late September 1993.
The Agreement is recommended for approval.
JEFF SrANEhar
Jeff Staneart, P.E.
Utilities Director
JS: sdi
t
0 c -z,s2
REIMBURSEMENT AGREEMENT WITH
CITY OF NEWPORT BEACH
THIS AGREEMENT is made and entered into, to be effective the stn
day of _September , 1993, by and between:
AND
COUNTY SANITATION DISTRICT NO. 5 OF ORANGE
COUNTY, CALIFORNIA, hereinafter referred to as "District"
CITY OF NEWPORT BEACH, a municipal corporation,
hereinafter referred to as "City ".
WHEREAS, the District is replacing and rehabilitating a sewer pipeline and
related facilities in the Pacific Coast Highway which has been designed as
"Replacement of Pacific Coast Highway Gravity Sewer, between the Arches (Old
Newport Boulevard) and Dover Drive, Contract No. 5 -37-4; and
WHEREAS, the City wishes to reconstruct sewer appurtenances, e.g. sewer
lines, new and modified manholes, etc., in a portion of the Pacific Coast Highway
which is included within the District's Project; and
WHEREAS, the Parties mutually agree that combining the District's sewer
project with the City's sewer appurtenances project would minimize costs and
construction impacts at the site; and
WHEREAS, a combined "Project" shall consist of construction of the
District's improvements to Pacific Coast Highway Gravity Sewer Replacement and
Rehabilitation ( "Sewer Portion "), and the construction of the City's sewer
appurtenances and related facilities at the location of the Project shown on District
plans for Contract No. 5 -37 -4 on Plan Sheet No. 14 of 29 as Item 7 with manhole and
appurtenances herein referred to as "City's portion'; and
0
WHEREAS, District and City desire to set forth their respective rights and
obligations concerning the Project.
NOW, THEREFORE, the parties agree as follows:
Section 1: Project Design
District shall prepare, or cause to be prepared, plans and specifications for the
entire Project, including the City's portion of the Project. City of Newport Beach
shall be responsible for the drafting cost of their portion of the Project at no cost to
District. District's consultant shall incorporate City's design into Project plans and
specifications. City shall compensate District's engineer directly.
Section 2: District's Responsibilities
District shall be solely responsible for the preparation and awarding of the
contract pursuant to the applicable public bid requirements for the construction of
the entire Project, including the construction of the District's Replacement and
Rehabilitation Sewer portion and the City's portion of the Project. District shall be
responsible for the preparation of all legal documents, including the notice inviting
bids, instructions to bidders, schedule of prices, and any related construction
agreements, surety bonds and insurance certificates. District shall be solely
responsible for the administration and performance of the contract awarded to
contractor for the construction of the entire Project.
Section 3: Right of Access
City shall have the right of access to the construction site of the Project at
all times during the construction of the Project.
Section 4: Costs
A. District's Costs
District shall pay all costs associated with the Replacement and Rehabilitation
of the District's portion of Pacific Coast Highway Gravity Sewer Project, including
excavation, construction, surveying, inspection and contract administration.
0 0
B. City's Costs
The City shall be responsible for all costs associated with design and
construction of the City's sewer appurtenances portion of the Project, including
engineering, design, excavation, construction, surveying, and inspection. The City
shall provide the design to District's consulting engineer for incorporation into
Project plans and specifications.
The Parties agree that the estimated cost for the City portion of the Project is
$31,000. The final cost for the City's portion shall be based upon the appropriate
Schedule of Prices and associated bid item(s) for the work to be done for the City
and any applicable Change Orders thereto and then eight (8 %) percent shall be
added to the cost to cover District's administrative and inspection costs. Costs are
depicted on Exhibit "A ".
Section 5: Environmental Impact Report/Permits
District shall act as Lead Agency and shall be responsible for full
compliance with the provisions of the California Environmental Quality Act
( "CEQA ") for the Project. For purposes of CEQA, all work hereunder shall be
deemed a single project and reference will be made to District's adopted Master
Plan of Sewer Facilities - 1989, as amended and supplemented, and related
approved Environmental Impact Report. District shall also obtain all necessary
permits to construct the Project.
Section 6: Change Orders
City shall be given the opportunity to review and approve all change
orders issued by District pertaining to the "City's portion" of the Project except for
changed conditions requiring immediate action. In which case, District inspector
will review changed condition with City inspector, if he is on -site, however
District's inspector shall have final say concerning decisions requiring immediate
action. City will provide an inspector with authority to approve change orders
during the time the contractor is working on "City's portion" of the facilities to be
installed as a part of this Project.
0 0
Section 7: Payment
A. City shall pay $20,000 of its share to District following receipt of an
invoice and shall remit funds within sixty (60) days from date of award of the
construction contract.
B. City shall pay District the balance of its share of the costs for the City's
sewer appurtenances portion during construction within thirty (30) days from
receipt of District's invoices for same. Final invoices shall be paid within thirty (30)
days after acceptance of the construction of the sewer appurtenances portion of the
Project by City. The final invoice shall include all costs due pursuant to Section 4,
subparagraph (B), above. District agrees to invoice City proportionate to District
contractor's completion percentage of the work items to be reimbursed by City.
Section 8: Hold Harmless
District shall defend and hold City, its elected and appointed officials
harmless from any and all claims, damages, or demands arising out of District's
performance of its obligations under this agreement. City shall defend and hold
District harmless from any and all claims, damages, or demands arising out of
City's performance of its obligations under this agreement.
Section 9: Insurance
District shall require the construction contractor for the Project to maintain a
policy of public liability insurance for personal injury and property damage,
including motor vehicle operators, during all times of the contract in the amounts
consistent with Districts' policies for all construction agreements. Said policy shall
name the City, the District, their officers, agents and employees as additional
insureds thereon.
Section 10: Integration
This Agreement represents the entire understanding of the City and the
District as to those matters contained herein. No prior oral or written understanding
shall be of any force or effect with respect to those matters covered by this
Agreement. This Agreement may not be modified, altered or amended except in
writing by the City and the District.
9
P
IN WITNESS WHEREOF, the Parties hereto have executed this Agreement on
day and year first above written.
'DISTRICT' COUNTY SANITATION DISTRICT NO. 5 OF
ORANGE COUNTY, CALIFORNIA
By
Assistant Secretary, and o irectors
APPROVED AS TO FORM;
THOMAS L. WOODRUFF
DISTRICT GENERAL COUNSEL
t.l 1 1
%-I l JF NEWPORT BEACH
By �c .
ATTEST: Clarence Turner, Mayor
Wanda Raggi , ity Clerk
APPROVED AS TO FORM:
CITY ATTORNEY
CITY OF NEWPORT BEACH
By ,^ CLGtC� ' Nl�i, b,
Robert Burnham, City Att ney
eng \537- 4 \agree.npb
ATTACHMENT "A"
Replacement of Pacific Coast Highway Gravity Sewer, between
The Arches (Old Newport Boulevard) and Dover Drive
Contract No. 5 -374
14161
1. Plan Sheet 11 of 29
Construct 8 -inch PVC; new 48 -inch manhole;
plug and remove interfering portions of existing
8 -inch CIP; remove existing 48 -inch manhole and
install new 8 -inch VCP ........................ ............................... $17,000.00
2. Plan Sheet 14 of 29
Remove existing cleanouts and install one 48 -inch
manhole and install approximately 80 feet of 8 -inch
VCP west of pump station including three laterals........ $14,000.00
SUBTOTAL $31,000.00
Contract Administration & Inspection (8`%,) 2,480.00
TOTAL $33,480.00
e n g\ 5-37-4 \a tta c h. n pb
fik
a
Jeff Staneart, P.E.
Utilities Director
City of Newport Beach
P.O. Box 1768
Newport Beach, CA 92659 -1768
Subject: Reimbursement Agreement for construction of city sewer facilities in
connection with Replacement of Pacific Coast Highway Gravity
Sewer, between The Arches (Newport Boulevard) and Dover Drive,
Contract No. 5 -37 -4
Enclosed herewith please find one fully- executed copy of subject agreement for
your files.
Penny K e
Assistant Board Secretary
PK:mas
Enclosure