PROJECT TIMELINE
4
July 2022
Council adopts budget for facility replacement
January 2023
Design contract awarded to COAR for design
2023-2024
Departmental and subcommittee meetings to develop starter concept design framework base on objectives
January 2024
Board of Library Trustees Public Meeting and Community Input
PROJECT TIMELINE
5
March 5, 2024
PB&R Commission Public Meeting and Community Input
May 14, 2024
City Council Public Meeting for Concept Approval
June 14, 2024
Received letter of appeal from Friends of Library Park
Fall 2025
Construction Begins
6
View from Balboa Blvd.
7
View from East Bay Avenue
8
View from Island Avenue
9
OVERALL SITE PLAN
10
LIBRARY INTERIOR
11
LIBRARY INTERIOR
12
INTERIOR FINISHES
13
INTERIOR FINISHES
14
INTERIOR FINISHES
15
INTERIOR FINISHES
SCHEDULE / COST
16
•Final plans and permitting ready for bid Summer 2025
•Construction begins Fall 2025
•Estimated cost is $16,000,000 (~$1,600/SF)
•All-in cost estimated at $17,700,000 (includes design, construction support, other soft costs)
•Cost of temporary Fire Station to be determined
WHAT’S NEXT?
17
•Upcoming milestones
•Coastal Commission Appeal decision
•Realignment of on-site water line
•Permitting of temporary Fire Station
•Bidding and Award of construction contract
QUESTIONS?